This is a 100% design submission specifications document for the USDA Jamie L. Whitten Building Perimeter Security Enhancement at Parking Lot 9 in Washington, DC, prepared by AECOM on April 16, 2021. The specifications outline detailed technical and administrative requirements for construction activities under Contract Number AG-3142-C-16-0008, Task Order 12314218F0214.

The document establishes comprehensive general requirements and execution standards across multiple divisions of work, including concrete, masonry, structural steel, electrical systems, paving, bollards, stormwater conveyance, and landscaping. Key administrative provisions include work hour restrictions limiting noisy operations to government-unoccupied hours (5:00 p.m. to 7:00 a.m.), mandatory use of GSA's electronic Project Management (ePM) system for all documentation and submittals, and requirement for HSPD-12 security clearances for ePM access. The contractor must maintain a full-time project coordinator, prepare detailed shop drawings and coordination drawings with minimum ten working days for architect/engineer review, submit a schedule of values within fourteen calendar days, and provide monthly waste management reports with recycling goals. Payment procedures require submissions by the first of each month with supporting documentation for work completed and stored materials. Submittals for substitutions of cause must be submitted immediately upon discovery but no later than 15 days prior to needed preparation, while substitutions for convenience must be submitted within 60 days of Notice to Proceed. All submittals must comply with specific formatting requirements including PDF electronic files with metadata tags, unique identifiers using contract number and specification section numbers, and comprehensive identification information. The specifications emphasize coordination with GSA Building Management, Federal Protective Service, and WMATA (given the metro lines beneath the site), along with preconstruction, progress, and project closeout conferences.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

Jamie L. Whitten Building Perimeter Security Enhancement at Parking Lot 9 Washington, DC

Specifications

100% Submission 16 April 2021

Contract Number: AG-3142-C-16-0008 Task Order: 12314218F0214 AECOM Project Number: 60585108

Prepared by AECOM

USDA HEADQUARTERS JAMIE L. WHITTEN BUILDING 100% Submission PERIMETER SECURITY ENHANCEMENT AT PARKING LOT 9 16 April 2021 Contract: AG-3142-C-16-0008

This page intentionally left blank.

Division Section Title

TABLE OF CONTENTS TOC - 1

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

NOT APPLICABLE

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

011400 WORK RESTRICTIONS

012500 SUBSTITUTION PROCEDURES

012900 PAYMENT PROCEDURES

013000 ELECTRONIC PROJECT MANAGEMENT

013100 PROJECT MANAGEMENT AND COORDINATION

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013220 PHOTOGRAPHIC DOCUMENTATION

013300 SUBMITTAL PROCEDURES

014000 QUALITY ASSURANCE AND CONTROL

014200 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

015639 TREE AND PLANT PROTECTION

015930 SECURITY PROCEDURES

015950 SAFETY AND HEALTH

016000 PRODUCT REQUIREMENTS

017000 EXECUTION REQUIREMENTS

017310 CUTTING AND PATCHING

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017810 PROJECT RECORD DOCUMENTS

017822 OPERATION AND MAINTENANCE DATA

018200 DEMONSTRATION AND TRAINING

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

030130 MAINTENANCE OF CAST-IN-PLACE CONCRETE

031000 CONCRETE FORMING AND ACCESSORIES

032000 CONCRETE REINFORCING

033000 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

042000 UNIT MASONRY

DIVISION 05 - METALS

051200 STRUCTURAL STEEL FRAMING

TABLE OF CONTENTS TOC - 2

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

NOT APPLICABLE

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

NOT APPLICABLE

DIVISION 08 - OPENINGS

NOT APPLICABLE

DIVISION 09 - FINISHES

NOT APPLICABLE

DIVISION 10 - SPECIALTIES

NOT APPLICABLE

DIVISION 11 - EQUIPMENT

NOT APPLICABLE

DIVISION 12 - FURNISHINGS

NOT APPLICABLE

DIVISION 13 - SPECIAL CONSTRUCTION

NOT APPLICABLE

DIVISION 14 - CONVEYING EQUIPMENT

NOT APPLICABLE

DIVISION 21 - FIRE SUPPRESSION

NOT APPLICABLE

DIVISION 22 - PLUMBING

221429 SUMP PUMPS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

NOT APPLICABLE

DIVISION 25 - INTEGRATED AUTOMATION

NOT APPLICABLE

DIVISION 26 - ELECTRICAL

260010 SUPPLEMENTAL REQUIREMENTS FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

TABLE OF CONTENTS TOC - 3

260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

260543 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS

260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

260800 COMMISSIONING OF ELECTRICAL SYSTEMS

262416 PANELBOARDS

262726 WIRING DEVICES

265613 LIGHTING POLES AND STANDARDS

265619 LED EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

NOT APPLICABLE

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

NOT APPLICABLE

DIVISION 31 - EARTHWORK

311000 SITE CLEARING

312000 EARTH MOVING

DIVISION 32 - EXTERIOR IMPROVEMENTS

321216 ASPHALT PAVING

321313 CONCRETE PAVING

321373 CONCRETE PAVING JOINT SEALANTS

321713 PARKING BUMPERS

321723 PAVEMENT MARKINGS

321726 TACTILE WARNING SURFACING

323305 FIXED STATIC & ACTIVE BOLLARDS

329113 SOIL PREPARATION

329300 PLANTS

DIVISION 33 - UTILITIES

334200 STORMWATER CONVEYANCE

DIVISION 34 - TRANSPORTATION

NOT APPLICABLE

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

NOT APPLICABLE

DIVISION 40 - PROCESS INTERCONNECTIONS

NOT APPLICABLE

TABLE OF CONTENTS TOC - 4

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

DIVISION 42 - PROCESS HEATING, COOLING, AND DRYING EQUIPMENT

NOT APPLICABLE

DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE

EQUIPMENT

NOT APPLICABLE

DIVISION 44 - POLLUTION AND WASTE CONTROL EQUIPMENT

NOT APPLICABLE

DIVISION 45 - INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT

NOT APPLICABLE

DIVISION 46 - WATER AND WASTEWATER EQUIPMENT

NOT APPLICABLE

DIVISION 48 - ELECTRICAL POWER GENERATION

END OF TABLE OF CONTENTS

FY15 Update Oct. 1, 2014 Summary 011000 - 1

SECTION 011000 – SUMMARY

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Name and Location: USDA HEADQUARTERS JAMIE L. WHITTEN BUILDING

PERIMETER SECURITY ENHANCEMENT AT PARKING LOT 9

B. Project Summary Description:

The U.S. Department of Agriculture (USDA), in cooperation with the U.S. General Services

Administration (GSA), proposes to amend the 2014 People’s Garden Site Improvements and

Perimeter Security Plan (2014 Plan) for the USDA Headquarters Complex. The purpose of the proposed action is to improve the safety of public gatherings held at parking Lot 9 to the east of the

Jamie L. Whitten Building by responding to a different threat than envisioned in 2014. USDA has identified new concerns regarding the safety of public gatherings at the site.

The Whitten Building is located along the National Mall near the Smithsonian Metrorail stations on

Independence Avenue, an arrival point for visitors to the National Mall and commuters to the adjacent federal office buildings. The site hosts a weekly farmers market during the summer and fall, attracting large groups of people. On market days, 12th Street is typically closed. The site also hosts

USDA social outreach, and education events, and supports other activities, such as providing a first aid station for the Marine Corps Marathon, a food truck gathering point for the Smithsonian Folklife

Festival, and U.S. Presidential Inauguration staging. The redesign of Lot 9 access and the extension of the perimeter security northward would provide for greater security for public events at the site.

C. Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by: AECOM, 3101 Wilson Blvd., Suite 900, Arlington, VA 22201.

D. Project Delivery Method: Traditional

1.4 SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY

A. The project includes the following Government furnished property to be installed by the Contractor.

The contractor shall advise GSA at least 30 days in advance of when the property should be delivered.

1. Coordinate with GSA customer agency, any relocation of equipment or the customer’s need.

1.5 MISCELLANEOUS PROVISIONS

A. Work in existing facilities shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.

FY15 Update Oct. 1, 2014 Summary 011000 - 2

B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.

Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.

1. Replacements of existing conditions that are removed shall match similar existing conditions.

2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.

3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.

4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.

C. Existing structures will remain in place.

D. Existing utility services with related meters and equipment will remain in place.

E. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011000

FY15 Update Oct. 1, 2014 Work Restrictions 011400 - 1

SECTION 011400 - WORK RESTRICTIONS

1.1 CONTRACTOR USE OF PREMISES

A. The Contractor will review and document the existing conditions surrounding the project premises. Provide documentation to the Government prior to the commencement of any construction activity.

B. During the construction period, the Contractor shall have full use of the designated premises for construction operations, including full use of the indicated work site, limited only by the Government's right to perform work or retain other contractors to perform work on portions of the project.

C. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for Government occupancy and public use.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.

3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.

4. Maintain existing building in a safe and weather-tight condition throughout the construction period. Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect the building, its occupants and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one (1) hour of notice should an emergency occur.

5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.

6. Space on the premises will be made available for the Contractor's storage and related activities, provided that its use will not interfere with operations of the Government.

Arrange and gain approval for use of this space through the Contracting Officer.

7. Use of the existing loading dock facilities will be shared with Government activities on a first-come-first-served, wait-your-turn basis.

8. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.

9. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading operations, turn off engines when docked.

10. Smoking is not permitted in or around the building, see Facilities Management Regulation (FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41 CFR Part 102-74.

11. No parking will be available on site during working hours for building occupants. The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site.

FY15 Update Oct. 1, 2014 Work Restrictions 011400 - 2

12. Cell Phones: Contractor is to provide company cell phone during this contract. All cell phones to be “on vibrate” at all times. If a telephone begins audibly ringing, the building guards will take the cell phone and hold until the end of the working day prior to the con-tractor leaving the property. Cell phones are only permitted in construction area and contractor’s office space.

13. No apparatus with an open flame is allowed to be used within the facility without the prior receipt of a burn permit. Contact the Field Office to obtain burn permits. Burn permits are required for each separate occurrence.

14. Permits: Refer to FAR 52.236-7

15. The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.

16. Coordinate with the GSA Building Manager and the COR for site access.

17. Coordinate with the GSA Building Manager and the COR on correct response procedures for any building system alarms occurring during or resulting from the construction process.

18. All building systems outside the immediate construction area shall be kept fully operational during normal working hours.

19. Protect building site from flying debris.

1.2 GOVERNMENT OCCUPANCY

A. The Government will occupy the site and the existing building during the entire period of construction. Cooperate with the Government's representatives during construction operations to minimize conflicts, mitigate noise, and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government's operations.

B. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.

2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.

1.3 WORKING HOURS

A. Government Occupied Hours: Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through Friday, except for established Government Holidays 07:00 to 17:00

B. Government Unoccupied Hours: Government personnel are not scheduled to occupy the building during times not indicated as Government Occupied Hours.

C. Contractor's General Working Hours: The Contractor working hours shall be generally established to occur during Government Occupied Hours.

FY15 Update Oct. 1, 2014 Work Restrictions 011400 - 3

D. Contractor's Required Working Hours: The following work shall be performed during Government Unoccupied Hours:

1. Noisy and/or odor-producing work that may disrupt tenant operations in adjacent spaces.

E. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. Contractor shall submit a proposed schedule and gain the Contracting Officer's approval at least 48 hours before proceeding with any work during Government Unoccupied Hours.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011400

FY15 Update Oct. 1, 2014 Work Restrictions 011400 - 4

This Page Intentionally Left Blank

FY15 Update Oct. 1, 2014 Substitution Procedures 012500-1

SECTION 012500 - SUBSTITUTION PROCEDURES

1.1 RELATED DOCUMENTS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division 016000 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

2. Divisions 02 through 49 Sections for specific requirements and limitations for substitutions.

1.3 DEFINITIONS

A. Substitutions: Proposed changes to the Contract Documents by the Contractor for products, materials, equipment, and methods of construction.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner

1.4 SUBMITTALS for Cause or Convenience:

A. Substitution Requests: Per Submittal Procedures Section 013300 submit electronic copies through ePM of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Coordinate with ePM.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Government and separate contractors that will be necessary to accommodate proposed substitution.

b. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, energy and resource performance goals, warranties, and specific features and requirements indicated.

Indicate deviations, if any, from the Work specified.

c. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

d. Samples, where applicable or requested.

e. Certificates and qualification data, where applicable or requested.

f. List of similar installations for completed projects with project name, location and contact information of owner and architect/engineer of record.

g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

h. Research reports evidencing compliance with building code in effect for project, when applicable for the proposed substitution.

i. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. Provide a schedule fragnet with a time impact analysis to allow the Government to consider the proposed substitution.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

k. Proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

l. The Contracting Officer may require the Contractor to provide a contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. The Contracting Officer or Contracting Officer’s Representative (CO) or (COR) Action: If necessary, the Contracting Officer or COR will request additional information or documentation for evaluation. The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project Schedule. The Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty working days.

1.5 Failure by the government to respond does not constitute acceptance of the proposed substitution.

1.6 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.7 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: The Contracting Officer (CO) will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, the Contracting Officer (CO) will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan. .

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: The Contracting Officer (CO) will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of the Contracting Officer (CO) or the Contracting Officer Representative (COR).

1. Conditions: The Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied.

a. Requested substitution offers the Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional obligations the Government incurs..

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan.

e. Requested substitution has received necessary approvals of authorities having jurisdiction.

f. Requested substitution is compatible with other portions of the Work.

g. Requested substitution has been coordinated with other portions of the Work.

h. Requested substitution provides specified warranty.

i. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 3 EXECUTION (Not Used)

END OF SECTION 012500

FY15 Update Oct. 1, 2014 Payment Procedures 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and to process Requests for Payment.

1.2 DEFINITIONS

A. Schedule of Values: A detailed written statement (masterformat/uniformat) furnished by the Contractor outlining the portions of the contract sum, which allocates values (price & percentage) for the various parts of the work and used as the basis for payment application and reviewing progress payments. The Agreement provides further details.

B. Request for Payment: A contractor’s invoice and request for progress payment with substantiating information consistent with approved schedule of values.

1.3 SCHEDULE OF VALUES

1. Coordination: Submit completed Schedule of Values no later than 14 calendar days prior to scheduled date of initial Requests for Payment.

A. Format and Content: Contractor shall be responsible to complete the GSA Schedule of Values Workbook and compile the values into electronic Project Management (ePM) System. Contractor will enter values into workbook prior to ePM input and provide associated electronic baseline copy to contracting officer for record. Contractor will follow guidelines in the Schedule of Values workbook to support ePM upload.

1. Identification: Complete the following Project Identification fields in the Schedule of Values:

a. Project Name

b. Project Number

c. Project Location, City, State

d. Base Contract Number

e. Task Order Number

f. Modification Number

g. GSA Project Manager

h. Contractor's Name and contact information

i. Date of submittal

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Requests for Payment and progress reports.

a. Work activity – (by division or specific work activity)

b. Dollar value of each specific work activity – both with an amount in dollars and whole cents, and as a percentage of the Contract Sum to nearest one-hundredth percent.

Adjust the amounts to total to the Contract Sum and the percentages to total 100 percent.

c. Each item in the schedule of values and Requests for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

(i.e. no stand alone item for Overhead, and Profit)

FY15 Update Oct. 1, 2014 Payment Procedures 012900 - 2

d. Modifications that affect value.

e. Update affected work branches and subordinate line items and

f. resubmit the schedule of values before the next Request for Payment when

Modifications result in a change in the Contract Sum

g. Line item for mobilization and de-mobilization

h. Line item for close out (% to be negotiated with GSA COR)

3. Each item in the Schedule of Values and Requests for Payment shall be complete. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at the government's option.

4. Revise and update workbook in ePM with all items affecting scope, schedule or cost and resubmit within 14 calendar days as coordinated with project manager or contracting officer.

Contractor shall provide a final as-built schedule at project completion. Update affected work branches and subordinate line items and resubmit the schedule of values before the next Request for Payment when Modifications result in a change in the Contract Sum

1.4 REQUESTS FOR PAYMENT

A. Requirements for Requests for Payment are in Section III, Terms and Conditions of the Agreement.

B. Each Request for Payment following the initial Request for Payment shall be consistent with previous Requests.

1. Initial Request for Payment, Request for Payment at time of Substantial Completion, and final Request for Payment involve additional requirements.

C. Payment Request Times: Submit Request for Payment to GSA by the 1st of the month. The period covered by each Request for Payment is one month, ending on the last day of the month.

1. Submit one paper draft copy (aka pencil copy) of Request for Payment to the CO or enter in ePM along with construction progress report seven days prior to due date for review by GSA.

Provide documentation evidencing the cost of work performed to be included in the Request for Payment. Resolve questions resulting from GSA review of draft Request for Payment and construction progress report prior to submitting Request for Payment.

D. Request Preparation: All payments must be executed by a person authorized to legally bind the Contractor.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts for work completed following effective date of previous Request for Payment, whether or not payment has been received. Include only amounts for work completed as of effective date of current Request for Payment.

3. Include amounts of Modifications issued before last day of construction period covered by Request.

E. Stored Materials: Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, and consent of surety to payment, for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices.

Match amount requested with amounts indicated on documentation.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of effective date of previous Request for Payment.

FY15 Update Oct. 1, 2014 Payment Procedures 012900 - 3

b. Value of previously stored materials put in place after effective date of previous Request for Payment and on or before effective date of current Request for Payment.

c. Value of materials stored since effective date of previous Request for Payment and remaining stored as of effective date of current Request for Payment.

F. Initial Request for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Request for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule per Agreement (startup if not final).

4. Products list (preliminary if not final).

5. Sustainable design submittal for project materials cost data.

6. Sustainable design action plans.

7. Schedule of unit prices.

8. Submittal schedule (preliminary if not final).

9. List of Contractor's staff assignments.

10. List of Contractor's principal consultants.

11. Copies of building permits.

12. Copies of authorizations and licenses from authorities having jurisdiction for performance of the

Work.

13. Initial progress report.

14. Report of preconstruction conference.

G. Request for Payment at Substantial Completion: After GSA issues the Notice of Substantial Completion, submit a Request for Payment less previous payments made for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This Request shall reflect Notices of Substantial Completion issued previously for GSA occupancy of designated portions of the Work.

H. Final Payment Request: The Agreement provides further details

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012900

FY15 Update Oct. 1, 2014 Payment Procedures 012900 - 4 ePM Updated June 2020 ELECTRONIC PROJECT MANAGEMENT 013000 - 1

SECTION 013000 - ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM

1.1 PURPOSE

A. The Contractor shall use GSA’s web-based electronic Project Management (ePM) system, which is a fully configured version of Meridian Systems’ Proliance Construction Management

Software.

1.2 DEFINITION

A. ePM is a web-based project management tool which provides GSA’s Public Buildings Service with an automated workflow, collaboration, document management and project management solution to help manage GSA design and construction projects. ePM is integrated with

GSA’s gBUILD (Green Building Upgrade Information Lifecycle Database ) to share project creation and data storage information.

1.3 PROJECT COLLABORATION AND DOCUMENTATION

A. General

1. The Contractor shall effectively manage the ePM database including maintaining adequate staffing levels and ensuring that personnel attend the mandatory GSA-provided training sessions.

2. The Contractor shall use ePM to upload, store, capture, preserve, record, maintain, update, and route all project-related documentation to comply with GSA's Document

Security Requirements. Classified material is not permitted to be stored in this system.

3. The Contractor shall use the workflow processes contained within ePM to submit and receive approval for all project deliverables.

4. The Contractor shall continuously monitor and review ePM to ensure the Contractor data is current through completion of the Close-out Phase of Construction.

5. The Contractor is required to store documents from their subcontractors and vendors in ePM. If a subcontractor or vendor does not obtain an ePM license, the contractor will be responsible for uploading and processing documents in ePM on their behalf.

B. Contents of ePM

1. The Contractor shall use ePM as the electronic filing cabinet for all project-related correspondence and submittals. The Contract Documents specify certain documentation that the Contractor shall provide during performance of the Contract. For the avoidance ePM Updated June 2020 ELECTRONIC PROJECT MANAGEMENT 013000 - 2 of doubt, and unless specifically stated otherwise in the Contract Documents, in addition to any documentation that the Contractor submits to GSA as set forth in the Contract

Documents.

1.4 SCHEDULING REQUIREMENTS

1. The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule and is compatible with Meridian Proliance.®

1.5 EQUIPMENT AND TRAINING

A. Equipment

2. GSA will not furnish any equipment related to accessing ePM. ePM is web-accessible, and can therefore be accessed via any computer with an Internet connection. For up to date ePM desktop requirements: http://www.gsa.gov/epm. (This is the GSA Public website for anyone who needs access to ePM.)

B. ePM Training

1. GSA will provide no cost training to familiarize team members with the ePM system. The

GSA Project Manager will ensure that appropriate personnel should attend training and what roles they will be set up within the system based on their project responsibilities.

C. ePM Support

1. GSA will provide ePM system administration and end user support, for the duration of the project.

1.6 PERSONNEL REQUIREMENTS

A. An HSPD-12 security clearance is required to access ePM. Project Team members without an HSPD-12 clearance will need to work with the GSA Project Manager to initiate the clearance process, and request a temporary waiver for ePM access until clearance can be confirmed. A waiver means that once the individual’s HSPD-12 clearance is confirmed, an ePM username and password will be provided. For up to date GSA

HSPD-12 information: www.gsa.gov/hspd12. Obtaining clearances vary in length and may take time to receive them.

1.7 DATA OWNERSHIP

A. GSA shall retain ownership of all data entered into the system and shall administer all information contained therein. And distribution of any system data shall be made upon request.

http://www.gsa.gov/epm http://www.gsa.gov/hspd12 ePM Updated June 2020 ELECTRONIC PROJECT MANAGEMENT 013000 - 3

1.8 DOCUMENT SECURITY

A. ePM security access levels ensure that sensitive documents can only be accessed by the appropriate personnel. It is the contractor’s responsibility to ensure their employees, subcontractors and vendors have the appropriate level of security to ensure document security.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013000

ePM Updated June 2020 ELECTRONIC PROJECT MANAGEMENT 013000 - 4

FY15 Update Oct. 1, 2014 Project Management & Coordination 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:

1. General project coordination.

2. Coordination drawings.

3. Conservation.

4. Administrative and supervisory personnel.

5. Conferences and meetings.

6. Utility service interruptions.

7. Cleaning and protection.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space.

Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices. Assure all controls can be reached and operated.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.

3. Minimize roof penetrations.

B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.

C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work.

Administrative procedures include but are not limited to the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

3. Security packages and systems by others (i.e. U.S. Marshals Service (USMS), Federal

Protective Service (FPS), tenants, etc.)

4. Audio Visual (AV) and technology requirements and packages for tenants and/or end users.

5. Telecommunication, data, internet and other tele-work systems for GSA, tenants and/or end users.

FY15 Update Oct. 1, 2014 Project Management & Coordination 013100 - 2

6. Delivery and processing of submittals.

7. Progress meetings.

8. Project closeout activities.

9. Startup and adjustment of systems.

1.3 COORDINATION DRAWINGS

D. Prepare coordination drawings and/or BIM model and data where coordination is needed for installation of products and materials fabricated by separate entities, and prepare coordination drawings where limited space availability necessitates maximum use of the space for efficient installation of different components.

1. Show the relationship of components from the separate shop drawings. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems

2. Indicate required installation sequences.

3. Indicate minimum access space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

4. Show locations and sizes of all access doors on vertical and horizontal surfaces throughout the facility.

5. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.

6. Comply with shop drawing requirements for sheet size and submittal methods specified in

Division 1 Section "Submittal Procedures."

E. Refer to Divisions 23, and 26 Plumbing, Heating Ventilating and Air Conditioning, and Electrical for specific coordination drawing requirements for mechanical and electrical installations.

F. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.

G. Work installed prior to approval of coordination drawings shall be at the Contractor’s risk.

Subsequent relocations required to avoid interferences shall be made without additional expense to the Government. In case interference develops, the Government will decide which work shall be relocated, regardless of which was installed first.

H. Digital Data Files of Coordination Drawings: Prepare coordination digital data files in accordance with the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as the original Drawings.

2. File Submittal Format: Same digital data software program, version, and operating system as the original Drawings and Portable Document Format (PDF).

3. GSA will furnish Contractor one set of digital data files of the Drawings for use in preparing coordination digital data files.

FY15 Update Oct. 1, 2014 Project Management & Coordination 013100 - 3

a. GSA makes no representations as to the accuracy or completeness of digital data files as they relate to the Drawings.

b. Digital Data Software Program: AUTOCAD

c. Execute a data licensing agreement in a form acceptable to the GSA, if required for

Project.

1.3 CONSERVATION

A. Coordinate conservation of energy, water and materials in the conduct of construction operation.

Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.

B. Comply with Green Purchasing Plan requirements.

C. Waste Management Plan: Establish a program to maximize recycling of waste materials.

Program shall include the following:

1. Designation of a waste management coordinator.

2. Identification of recyclable materials.

3. Identification of available local recycling firms and agencies to receive recyclable materials.

4. Establishment of quantity goals for collection of each recyclable material.

5. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.

6. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.

7. Implementation of the Waste Management Plan: Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the Contract.

a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.

b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant stakeholder of the project, including the Government.

1.4 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. The Contractor shall provide administrative and supervisory personnel for proper performance of the Work.

B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including all systems required in the project. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:

1. Scheduling and sequencing of Work.

2. Sharing access to work spaces.

FY15 Update Oct. 1, 2014 Project Management & Coordination 013100 - 4

3. Installations.

4. Protection of work.

5. Cutting and patching.

6. Selections for compatibility.

7. Preparation of coordination of drawings.

8. Inspection and tests.

9. Temporary services and facilities.

C. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1 Section "Safety and Health."

D. Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.

1.5 CONFERENCES AND MEETINGS

A. Preconstruction Conference: The government shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. The conference shall review responsibilities and personnel assignments.

1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:

a. Government.

b. Architect.

c. Major design consultants.

d. Contractor.

e. Major subcontractors.

f. Major suppliers.

g. Other concerned parties.

2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:

a. Tentative construction schedule.

b. Critical work sequencing.

c. Designation of responsible personnel.

d. Procedures for processing field decisions and Change Orders.

e. Procedures for processing Applications for Payment.

f. Distribution of Contract Documents.

g. Submittal of Shop Drawings, Product Data, and Samples.

h. Preparation of Record Documents.

i. Use of the premises.

j. Parking availability.

k. Office, work, and storage areas.

l. Equipment deliveries and priorities.

m. Safety procedures.

n. First aid.

o. Security.

p. Housekeeping and progress cleaning.

FY15 Update Oct. 1, 2014 Project Management & Coordination 013100 - 5

q. Working hours.

r. Energy and resource efficiency / sustainability

s. Waste management

B. Progress Meetings: The Government or designee shall conduct progress meetings at the Project Site at regular intervals. Dates of meetings shall be coordinated with preparation of the payment request.

1. Attendees: In addition to the Contractor's and Government's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.

a. Contractor's Construction Schedule: Review progress since the last progress meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. Provide 2 week schedule look ahead.

b. Review the present and future needs of each entity present, including but not limited to the following:

1) Interface requirements.

2) Time.

3) Sequences of operations.

4) Status of submittals.

5) Deliveries.

6) Off-site fabrication.

7) Access.

8) Site utilization.

9) Temporary facilities and controls.

10) Hours of work.

11) Hazards and risks.

12) Housekeeping and progress cleaning.

13) Quality and work standards.

14) Change Orders.

15) Documentation of information for payment requests.

16) Updating of Record Documents.

3. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. The revised schedule shall be issued concurrently with the report of each meeting.

C. Partnering Meetings:

FY15 Update Oct. 1, 2014 Project Management & Coordination 013100 - 6

Projects with an estimated construction cost (ECC) over $10 million are required to hold Partnering Meetings. To most effectively accomplish this contract, the Government requires that the Contractor and its Subcontractors participate in a cohesive partnership with the Government. Key personnel from the Government, Contractor, its Subcontractors, and the Designer of Record will participate in the Partnering process.

The Contractor shall provide the Contracting Officer with a list of the key personnel from the Contractor and its Subcontractors who will participate in the partnering sessions. The Contracting Officer may, in his/her sole discretion, add or remove any individual from the list. The Contracting Officer shall provide a list to the Contractor with the names of the individuals who will participate in the partnering sessions on behalf of the Government and its designer and on site construction manager. The Contractor shall issue the invitations to all of the individuals who will participate in the partnering sessions and generally serve as the host during any such session’s team. The Contractor shall provide the Facilitator, meeting room, and other incidental items for the partnering sessions over the life of the project.

Before a Partnering session, the Contractor shall coordinate with the Facilitator all requirements for incidental items (i.e. audio-visual equipment, easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards, etc.) and have these items available at the Partnering session. The Contractor will copy documents for distribution to all attendees. The participants shall bear their own costs for meals, lodging and transportation associated with Partnering.

The Facilitator shall be acceptable to both the Government and Contractor. An acceptable Facilitator is experienced in leading the team in a timely manner and ensuring issues are identified and resolved. A list of Partnering Facilitators is available from the Contracting Officer.

1. The Initial Partnering Session shall be a duration of one day minimum (8 hours plus an additional 30 minute lunch break). It shall be located at a place off the construction site as agreed to by the Contracting Officer and the Contractor. It may take place concurrently with the Pre Construction Meeting.

2. The Follow-on Partnering Session(s) generally lasts a half day or less. They will be scheduled at 6 month intervals. Participants are encouraged to utilize electronic means to expedite meetings.

Meetings may be held at the project site, or in a Government Facility. Follow-on meetings may be held concurrently with other scheduled meetings. Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session is recommended to achieve best results and for continuity.

D. Project Closeout Conference: GSA will schedule and conduct a Project closeout conference, at a time convenient to Contractor, CM and Architect, but no later than 90 days prior to the scheduled date of Substantial Completion.

Attendees:…