Attachment 1 SOW Lot 9 11.19.2026.pdf
PDF 327 KB Posted
- Solicitation number
- 124PCA27Q0002
About this file
This is a Scope of Work for a Design-Build federal contract to complete perimeter security enhancements at Parking Lot 9 of the USDA Headquarters Jamie L. Whitten Building in Washington, DC (Solicitation #124PCA27Q0002, dated November 19, 2026).
The Design-Build contractor must complete design and construction work within eleven and one-half months from Notice to Proceed. Key responsibilities include: conducting site surveys to assess existing conditions and inventory materials; determining areas requiring demolition such as cracked mud slabs; remedying sinkholes per Langan's January 28, 2026 report recommendations using Option #2 and subject to WMATA approval; updating AutoCAD construction drawings dated April 16, 2021; obtaining required approvals from WMATA and DDOT; providing structural engineering modifications for north-side bollards to meet M50/P1 crash ratings with manufacturer certification; restoring pipe railings with lead paint abatement; resurfacing and re-striping the parking lot; installing granite curbs (long-lead item with 16-week delivery); ensuring accessibility compliance with 1:12 slope ramps and stainless steel handrails; updating landscape drawings with irrigation system; coordinating moveable bollard functionality with USDA Office of Safety, Security, and Protection; and implementing electrical work per James Posey Associates specifications. The contractor must conduct bi-weekly WMATA meetings (contractor pays WMATA bills), submit design packages at 35%, 65%, and 100% completion stages, provide three copies of half-size drawings with electronic copies, and furnish twelve-month warranties on materials and labor plus a two-year warranty and preventive maintenance contract for moveable bollards. All architects and engineers must be registered in DC, with final design documents stamped by a DC-licensed professional engineer. The construction contractor must hold a valid DC general contractor's license. Work must comply with applicable Federal, DC, WMATA, and IBC 2024 requirements, and meet Anti-Terrorism Force Protection standards.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK Design/Build Perimeter Security Enhancement Parking Lot 9, 12th Street USDA Headquarters Jamie L. Whitten Building, Washington, DC 20250
Solicitation # 124PCA27Q0002
SCOPE OF WORK
Design/Build Perimeter Security Enhancement
Parking Lot 9, 12th Street USDA Headquarters Jamie L. Whitten Building
Washington, DC 20250 dated November 19, 2026
1. BACKGROUND
The United States Department of Agriculture (USDA) Headquarters (HQ) Complex in Washington D.C. consists of two buildings: the Jamie L. Whitten and the Agriculture South Buildings, both of which are listed on the National Register of Historic Places and as such are subject to the Section 106 Historic Preservation Review Process for any modifications. The headquarters buildings are classified as Level IV facilities. In 2014, the USDA commissioned an A/E firm to develop the “Concept Site Improvements and Perimeter Security Plan,” because the Department’s perimeter requires hardening to prevent unauthorized motor vehicle entry. The Concept Plan was approved by the General Services Administration (GSA), the District of Columbia State Historic Preservation Officer, the District of Columbia Archeologist (DCA), the National Park Service (NPS), the Commission of Fine Arts (CFA) and the National Capital Planning Commission (NCPC). The GSA, CFA and NCPC approved the design development for the perimeter security enhancement at Parking Lot 9 of the Whitten Building, which is the site of the Farmers Market. It is held every Friday between May and October, drawing large crowds of employees and tourists. The Lot 9 construction was underway; unfortunately, it was deemed to be in the best interest of the government to allow the construction contract to expire. The Washington Metropolitan Area Transit Authority (WMATA) orange, blue and silver line infrastructure is less than 7’-0” below the Lot 9 parking surface, making excavation high risk.
USDA requires further development of the original Lot 9 construction document package dated April 16, 2021. The design package is the construction bid set for the perimeter security enhancements at Parking Lot 9. The oversight authorities have already approved the Lot 9 design, necessitated because of its prominent location adjacent to the National Mall. Additional approvals are not necessary unless the design substantially changes. Other required approvals will include the Washington Metropolitan Area Transit Authority (WMATA) as portions of Lot 9 are located directly over the Smithsonian Metro Station and the District Department of Transportation (DDOT) which owns the sidewalk surrounding Lot 9 at the east and south boundaries.
The A/E who developed the Lot 9 design concept, obtained approval from the oversight authorities.
Subsequently, the A/E created drawing and specification documents for the Lot 9 perimeter security enhancement project based upon the approved design. The drawing and specification documents, dated April 16, 2021, detail the project requirements in general. Though the provided specifications and drawings may appear to be fully engineered solutions they cannot be relied upon to be such for any portion of the work. Shortly after the construction contractor began work in February 2024, a sink hole developed in the southwest portion of the site requiring remediation.
The WMATA engineers have examined the sinkhole. The results of Langan’s site surveys and remediation recommendations are in a report dated January 28, 2026. The D/B contactor must ultimately determine the full extent of the sink holes and develop a remediation plan approved by WMATA in accordance with Langan’s recommended solution Option #2. The Lot 9 north boundary will require an engineered solution, either a stepped mud mat foundation or shimming of the shallow footed bollards with appropriate steel shapes or concrete blocks to ensure the top of each bollard is at least 36” above grade and certified by the bollard manufacturer Guardiar, or approved equal, as meeting a crash rating of M50/P1. While it is desirable to utilize the bollards on site, the purchase of taller bollards for the north border is a potential solution. The Design-Build (D/B) contractor is responsible for fully developing the design drawings, details, and construction specifications to meet performance specifications. WMATA will review the all Design packages & submissions. The drawings/sketches and details shown on the original A/E packages dated April 16, 2021, are program requirements only and not considered as a final design package. The D/B contractor is responsible to propose innovative means and methods to achieve the full scope of the work.
No work has been performed on site since the summer of 2025. The original contractor completed the mud matt foundation for the shallow footed barriers, the installation of the streetlamps along 12th Street, the hydraulic (moveable) bollards, power boxes at the center of the lot, and the building identification signs at the four corners of the property. Of the work completed, some will require demolition or modification. Additionally, four lengths of granite curb, the 63 shallow footed bollards, accompanying bollard covers, and 12 of the 13 deep footed bollards were delivered to the site. A construction fence encloses the site.
2. OBJECTIVE
Provide Level 4 perimeter security enhancement for the Jamie L. Whitten Building at Parking Lot 9, updating the original construction documents (drawings and specifications) as necessary, following determination of areas requiring demolition and sink hole remediation by continuing construction where the original contractor stopped work. The Design-Builder shall incorporate all referenced documents and requirements into the updated construction documents, as applicable.
3. PROJECT INFORMATION
1. Prospective bidders will be required to visit the site to acquire firsthand knowledge of site conditions, inventory existing materials and completed work as well as to determine what work requires demolition such as cracked mud slabs.
2. The Design/Build Contractor will engage WMATA immediately to focus on WMATA’s requirements and areas of concern. WMATA requirements will likely include but are not limited to a building permit, railroad insurance, and a videographer to document existing conditions.
3. Plan and budget for bi-weekly meetings and site visits with WMATA to ensure approvals are timely and to develop a professional working relationship. WMATA bills for all interaction.
4. Determine the extent of the sink hole or sink holes and remedy accordingly, subject to WMATA’s approval. Using guidance provided by Langan in their report dated January 28, 2025, stabilize subsurface and repair sinkholes using Option 2 as specified in Langan’s report throughout the Lot 9 boundaries. Sink holes have been identified near the WMATA elevator and over the tunnel.
5. Update the A/E AutoCAD drawings dated April 16, 2021. Obtain required approval from the oversight authorities as necessary mainly WMATA and DDOT. The historic preservation oversight authorities have previously approved the April 16, 2021, design.
6. Restore pipe rail at top of moat per specifications which includes lead paint abatement.
Paint to match existing color.
7. Protect the air quality of adjacent occupied area from being affected by construction activities.
8. Ensure the perimeter bollard protection system is built to performance specifications;
furthermore, ensure the bollard manufacturer (Guardiar), or approved equal, certifies compliance at project re-initiation and completion.
9. Remove rust from bollards stored onsite.
10. Provide structural engineering for modifications to north side bollards and bollard foundations to meet M50/P1 performance requirements.
11. The moveable bollards are installed and wired. The sump pump on the drawing for draining bollard cavities is not required and not installed. Operation of bollards to be verified and warranty extended to two years after project completion.
12. Coordinate and install traffic control arms, badge readers/key fobs, and moveable bollard functionality with the USDA Office of Safety, Security, and Protection (OSSP) to ensure desired outcome meets with OSSP approval.
13. Implement electrical scope prepared by James Posey Associates dated 10/29/25. Verify that electrical service completed by original contractor is built according to construction documents and meets current requirements and functionality.
14. Update grading plan including area north of the parking lot including adjacent People’s Garden. Provide a new grading plan. Grading of Lot at NE inlet to be confirmed; lower inlet if necessary
15. Granite curbs were not procured by the original contractor except for four 8’-0” lengths. This is a long lead item, reportedly with a 16-week delivery time.
16. Ensure that site access meets all accessibility codes, especially with regards to transitions from the People’s Garden, from the sidewalk at Independence Ave and from the sidewalk at 12th Street to Lot 9. The north side ramp to the People’s Garden will have a slope of 1:12 with stainless steel handrails powder coated to match the black bollards. Provide extended granite curbs on the west and east side of the ramp. The redesign and modifications to the area around the People Garden are greater in magnitude than the original design.
17. Resurface the existing parking lot surface by milling and applying a new layer of asphalt.
Stripe and number parking spaces and provide signage.
18. Update landscape drawings for resolution of existing conditions and bollards. Landscape material substitutions will not be permitted. Install per specifications at optimal planting time. Revise scope to include an irrigation system. Landscaping material was not procured by the original contractor.
19. Develop a Critical Path Method (CPM) Schedule within 3 weeks of Notice to Proceed; update weekly. Submit the Schedule of Values within 3 weeks of Notice to Proceed; Update biweekly.
20. Schedule and conduct weekly project meetings via Microsoft Teams, prepare and distribute meeting minutes, and provide regular project status reports throughout contract performance.
21. Parking will not be provided.
22. All work shall be coordinated and reviewed by the USDA Office of Operations (OO)
Engineering Branch.
The design shall meet the requirements in the Lot 9 Construction Documents provided dated April 16, 2021. The drawings and sketches in these documents convey general conceptual ideas and shall not be construed as architectural and/or engineering design drawings. Drawings will be made to scale, and electronic copies will be provided in AutoCAD. All project drawings and documents will become the property of the USDA.
The Design Build Contractor is responsible for providing temporary space for their project management personnel and staging area. Part of the sidewalk along the 12th Street SW is possible temporary office space and staging area, but subject to the review and approval of the District of Columbia (DC) government. The contractor is responsible for all permits including but not limited to WMATA, DC Government, and other entities as well as railroad insurance and all other associated costs. The temporary space shall not interfere with the traffic in and out of the USDA South Building parking lot entrances and normal USDA business. The Contractor is responsible for protecting and returning the adjacent sidewalks to the pre-construction conditions.
The design and construction of this project shall meet applicable Anti-Terrorism Force Protection (ATFP) and blast requirements.
4. PROJECT DESCRIPTION
The Perimeter Security Enhancement project will be executed through the Design-Build delivery process.
The work of the Lot 9 project includes, but is not limited to, the following design disciplines and their related building / site / utility systems:
a. Civil Engineering
b. Geotechnical Engineering
c. Hydraulic Engineering
d. Landscape Architecture
e. Environmental / HAZMAT Remediation Engineering
f. Life Safety Engineering
g. Architecture
h. Historic Preservation
i. Structural Engineering
j. Blast & ATFP Engineering
k. Plumbing Engineering
l. Electrical Engineering
The work shall be planned by the Contractor to proceed as efficiently and safely as possible, without disruption to normal USDA operations. USDA normal building hours are 6:00 am to 6:00 pm Monday through Friday excluding weekends and holidays. All noise producing activities affecting normal building operations shall be done outside of the above specified time, unless approved by the COR. The site will be enclosed by temporary fencing. The fencing will be kept locked to prevent pedestrians from entering when no construction activities are ongoing. Provide means to control dust spreading outside the construction zone. Areas within and outside the construction zone are to be kept clean daily.
Government Acceptance, Beneficial Occupancy and the Commencement of Warranties shall be based upon the full completion of the Work. Government requires all work to be completed prior to accepting the Contractor’s request to perform Substantial Completion Inspection.
5. SURVEY, DESIGN and BUILD
The D/B contractor shall conduct an onsite survey to design the above-mentioned requirements, inventory existing materials; determine what must be demolished such as cracked mud mats. The D/B contractor shall then proceed with updating the design drawings and specifications for the project. Upon submission by the Designer of Record (DOR) of signed and sealed 100-percent design drawings and specifications for a discrete segment of work, and upon Government review and approval of that segment, the Government may authorize the Design-Build Contractor to proceed with mobilization and construction activities for the approved segment prior to completion of the remaining design work. The D/B contractor shall continue with their effort to complete the final design build drawings and specifications as per the project schedule.
Construction is permitted 7 days a week during daylight hours to expedite project completion. The site will be secured with construction fencing like the current installation. Site will be cleaned daily from debris.
Third party testing and/or inspections are required for the following items:
• Rebar and forms prior to concrete pouring
• Concrete slump tests
• Weld joints
• Lead abatement of moat railing include air tests and final wipe clearance tests
• Bollard foundation footings
6. CODES AND STANDARDS
Comply with applicable Federal, District of Columbia, WMATA, and authority-having-jurisdiction requirements in effect on the date established by the contract. Where listed requirements conflict, notify the CO and DOR- before proceeding. Do not apply a “most stringent” rule without evaluating compatibility, jurisdiction, and design intent.
Minimum Referenced Criteria:
33 U.S.C.1251 Federal Water Pollution Control Act. Clean Water Act 1972
Architectural Barriers Act Accessibility Standards International Building Code (IBC 2024) International Fire Code (IFC 2024) International Green Construction Code (IGCC 2018) International Mechanical Code (IMC 2024) International Plumbing Code (IPC 2024) International Property Maintenance Code (IPMC 2018) International Code Council Performance Code (ICCPC -2021) International Existing Building Code (IEBC 2018) National Fire Protection Association (NFPA) 70: National Electrical (2023) The Risk Management Process: An Interagency Security Committee Standard (2013)
The Secretary of the Interior’s Standards for the Treatment of Historic Properties with Guidelines for Preserving, Rehabilitating, Restoring and Reconstruction of Historic Buildings (2017)
United States General Services Administration P100 (2024)
Washington Metropolitan Area Transit Authority (WMATA) Office of Joint Development and Adjacent Construction (JDAC):
• Adjacent Construction Project Manual (2015)
• Adjacent Construction Project Flowchart (2019)
• Typical WMATA Design & Coordination Checklist
• Site Specific Work Plan (SSSWP) Template
All Other Codes and Standards indicated and/or specified in the drawings and specifications. If there are any conflicts, the most stringent applies. Use the latest edition of the codes and standards mentioned above.
7. QUALITY ASSURANCE and QUALITY CONTROL
D/B contractor shall coordinate inspections, tests, punch list, and final inspection through the COR. DOR of the D/B contractor shall be the QC chief.
The D/B contractor shall have a quality assurance and quality control (QAQC) team to ensure the work meet the requirements of the documents and its own design documents. The Design-Build Contractor's Architect/Engineer (A/E) Designer of Record shall participate in and support all Quality Assurance/Quality Control (QA/QC) activities as a member of the QA/QC team.
Submit a Safety Plan for review and approval by the government.
8. COORDINATION
Coordinate construction schedules and construction operations with the Contracting Officer's Representative (COR). All changes and matters related to costs and times must be approved by the Contracting Officer prior to actual purchasing and installation.
9. PERIOD OF PERFORMANCE
The Period of Performance for design and construction is eleven and one-half months from the date of issuance of the Notice to Proceed (NTP).
10. DELIVERY
The D/B contractor shall coordinate material delivery and on-site storage with USDA.
11. DISPOSAL OF REMOVED MATERIALS, EQUIPMENT AND DEBRIS
The D/B contractor shall be responsible for the off-site disposal of all removed materials per applicable Federal, State, and local environmental disposal laws and regulations. The contractor shall ensure that the workplace is cleaned at the end of each workday.
12. SAFETY AND FIRE PREVENTION
The D/B contractor shall observe all normal rules governing safety on construction projects and shall comply with all Federal, State, Local, and USDA regulations/requirements.
13. SECURITY REQUIREMENTS
The contractor shall comply with USDA security regulations for identification access passes for all workers. The contractor should apply well in advance for anyone requiring building access as the
USDA badging process is cumbersome and time consuming. Including fingerprinting, it may take a couple of months. Submit all necessary paperwork including PII documents to the COR.
14. DESIGN SUBMITTALS REQUIREMENTS for LOT 9
Three copies each:
o 35% Design Package ½ size drawings, specifications, product catalog.
o 65% Design Package ½ size drawings, specifications, products catalog.
o 100% ½ size drawings, specifications, products catalog.
o Final Design Package ½ size drawings, specs, final QC plan, final safety plan, product catalogs.
o Electronic copies of submittals.
15. CONSTRUCTION SUBMITTALS
The D/B contractor to submit four (4) hard copies of each of the following submittals:
1. See DOR specification section 013300-submittal procedures.
2. O/M Manuals
3. Project close-out package including the test results, warranty certificates, and contact info.
See DOR’s specification section 017700 Closeout Procedures.
The D/B contractor shall provide above referenced engineer approved shop drawings to Government for final review and prior to start of any construction (besides O/M manuals and project close-out package).
The government review time for each submission shall be no longer than fourteen (14) days.
16. WARRANTY AND PROJECT CLOSEOUT PACKAGE
The D/B contractor shall warranty materials and labor for a period of at least 12 months, or as per the manufacturer’s warranty period, or as specified, whichever is greater from the signed date indicating satisfactory completion of the contract including punch list items. The D/B shall be responsible for costs from the hardware and/or software support services from vendors and/or manufacturers if they are required to be part of the above warranty period.
Provide a two-year warranty and two-year preventive maintenance contract for the moveable / hydraulic bollards at project completion.
The D/B contractor shall provide two (2) copies of O/M manuals (binders and electronic copy on thumb drives) with warranty information and contact phone numbers.
17. AS-BUILT DRAWINGS
The D/B contractor shall provide three (3) copies of completed ½ size as-built drawings and two (2) electronic copies (pdf and AutoCAD/Revit) on thumb drives to the Government prior to project closeout.
18. SPECIAL CONSIDERATIONS
The Architects and Engineers of the design/build team shall be registered in the District of Columbia and all final design documents shall be stamped by a professional engineer licensed in the District of Columbia. The construction contractor shall have a valid general contractor’s license in DC. The D/B contractor shall attend pre-construction, weekly or as determined necessary meetings with CO, COR, and others. The contractor will lead and schedule project meetings as well as prepare and distribute written minutes of the meetings to all interested parties.
| 4. PROJECT DESCRIPTION |
| 5. SURVEY, DESIGN and BUILD |
| 6. CODES AND STANDARDS |
| Minimum Referenced Criteria: |
| 33 U.S.C.1251 Federal Water Pollution Control Act. Clean Water Act 1972 |
| 7. QUALITY ASSURANCE and QUALITY CONTROL |
| 8. COORDINATION |
| 9. PERIOD OF PERFORMANCE |
| 10. DELIVERY |
| 11. DISPOSAL OF REMOVED MATERIALS, EQUIPMENT AND DEBRIS |
| 12. SAFETY AND FIRE PREVENTION |
| 13. SECURITY REQUIREMENTS |
| Three copies each: |
| 15. CONSTRUCTION SUBMITTALS |
| 16. WARRANTY AND PROJECT CLOSEOUT PACKAGE |
| 17. AS-BUILT DRAWINGS |
| 18. SPECIAL CONSIDERATIONS |