12456818R0012 HVAC Replacement & Energy Upgrades Phase II-V PNW Corvallis, OR

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES SCHEDULE OF ITEMS

SCHEDULE OF ITEMS

Corvallis HVAC Replacement Phase II-V Benton County, Oregon

ITEM

NUMBER

DESCRIPTION

METHOD OF MEAS.

UNIT

QTY.

PRICE

TOTAL

BASE ITEMS

BI 1

Mobilization
LSQ
LS
1

BI 2

Phase 2 Central Wing HVAC
LSQ
LS
1

BI 3

Phase 2A Central Wing HVAC (3rd Floor)
LSQ
LS
1

Base Total:

ADDITIVE ITEMS

AI 1

Phase 3 West Wing HVAC
LSQ
LS
1

AI 2

Phase 3A West Wing HVAC (3rd Floor)
LSQ
LS
1

AI 3

Phase 4 West Wing Fan Coil Units Replacement
LSQ
LS
1

AI 4

Phase 4A Central & West Wing Windows
LSQ
LS
1

AI 5

Phase 5 Process Chilled Water
LSQ
LS
1

AI 6

Phase 5A West Wing MAU & Exhaust Fan
LSQ
LS
1

Additive Items Total:

Total Bid:
$

The Government Plans to award the Base Bid and then based on the availability of funds award as many of the additive items as possible.

OFFEROR

DUNS Number

EMAIL

The estimated start work date is October 15, 2018.

For additional information, please contact Takele Woldu at 828-257-4205 or twoldu@fs.fed.us

Offerors shall submit pricing for all items listed in the Schedule of Items. Offers that do not contain pricing for all items listed in the Schedule of Items, will not be considered for award.

NOTES:

1.) Offerors are urged to inspect work site before submitting a proposal. See Section L for organized site visit information.

2.) A bid bond of 20 percent of the total offer including additive items is required. A payment bond (100 percent) and a performance bond (100 percent) will be required after award.

3.) Offerors MUST be active in the SYSTEM FOR AWARD MANAGEMENT (SAM) data base – See FAR 52.204-7 and Annual Representations and Certifications Applications – See FAR clause 52.204-8. These are now consolidated at the following site: https://www.sam.gov/portal/public/SAM/

4.) ELECTRONIC OFFERS ARE ACCEPTED.

5.) Facsimile proposals will be NOT be accepted.

6.) This is not a public bid opening. All offers submitted are considered confidential. The name of the contractor and the amount of the contract will be disclosed only after an award has been made.

7.) RETURN PACKAGE: To be considered for award the offeror must follow the directions in Section L.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 SCOPE OF CONTRACT

Work for this project consists of HVAC system and building automation system replacement and energy upgrades at the Corvallis Forestry Sciences Laboratory. Elements of work include replacement and integration of the Building Automation System (BAS); replacement of mechanical equipment, ducting, and piping including fan coil units, air handling units, exhaust fans, heat recovery units, chilled water, steam and heating water system devices; window replacement; associated testing, adjusting, balancing, and commissioning; and associated architectural and structural components . See Attachment 1 for Specifications and Drawings.

C-2 PROJECT LOCATION

Corvallis Forestry Scinces Laboratory, 3200 SW Jefferson Way, Corvallis, Oregon, 97331

MAGNITUDE OF THE PROJECT- FAR 36.204

(c) Between $5,000,000 – $10,000,000

C-3 SPECIFICATIONS

SEE ATTACHMENT 1 - SPECIFICATION Project Manual Volume 1 document - 240 Pages

AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL

SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS FPMR PART 101-29 (FAR 52.211-1) (AUG 1998)

(a) The GSA Index of Federal Specifications, Standards and Commercial Item Description, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to--

GSA Federal Supply Service Specifications Section, Suite 8100 470 East L'Enfant Plaza SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978.

(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

(End of provision) AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (FAR 52.211-3) (JUN 1988)

The specifications cited in this solicitation may be obtained from:

Specification Address

ASTM StandardsAmerican Society for Testing and Materials
1916 Race Street
Philadelphia, PA 19103
(215) 199-5462

AASHTO Standards American Association of State Highway and Transportation Officials 341 National Press Building Washington, D.C. 20024

The request should identify the solicitation number and the specification requested by date, title, and number, as cited in the solicitation.

C-4 SUBMITTALS

Submittals shall include the following unless otherwise required in the specification:

1. Date and revision dates.

2. Project name and contract number.

3. Names of Contractor, subcontractor, supplier, and manufacturer.

4. Specifications section number.

5. Field dimensions and relation to adjacent structures.

6. Applicable standards such as ASTM or Federal Specifications.

7. Contractor's stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents. Provide all submittals within 14 calendar days of contract award unless otherwise required by the specification.

C-5 PRODUCT SAMPLES AND/OR SUBMITTALS

The following product samples and/or submittals are required for this project:

The all submittals other than color or physical materials for this project will be handle by an electonic submittal process. “Submittal Exchange” will be used to track and approve submittals, shop drawings, and material certification. Apon award of the contract and receiving contact information including email address the electronic submittal program will be established.

C-6 ORDER OF PRECEDENCE--CONSTRUCTION

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

1. The Schedule (excluding the specifications), i.e., Sections A, B, D, E, F, G, and H.

2. Representations and other instructions, i.e., Sections K, L, and M.
3. Contract clauses, i.e., Section I.

4. Other documents, exhibits, and attachments (excluding plans or drawings), i.e., Section J.

5. Special Project Specifications.

6. Standard Specifications, i.e., Section C (including FAR clauses).
7. (a) Drawings, figured dimensions over scaled dimensions.

(b) Drawings, large scale contract drawings over small scale contract drawings.

(c) Schedules on contract drawings over any conflicting notations on contract drawings.

8. Shop drawings.

AGAR 452.211-72 STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)

The Attachments listed in Section J are hereby made a part of this solicitation and any resultant contract.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

E-1 INSPECTION AND TESTING PERFORMED BY GOVERNMENT

The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.

E-2 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

FAR 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not --

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may --

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of Clause)

AGAR 452.246-70 INSPECTION AND ACCEPTANCE (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at the project site.

SECTION F--DELIVERIES OR PERFORMANCE 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984)

F-1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 730 calendar days after issuance of a Notice to Proceed for phases II through V see timeline below:

Only Phase 2 is awarded- 380 days

Only Phase 2 and AI 1- 500 days

Only Phase 2 and AI 1 & 2- 560 days

Only Phase 2 and AI 1, 2, and 3- 680 days

Only Phase 2 and AI 1, 2, 3, and 4- 710 days

Only Phase 2 and AI 1, 2, 3, 4, and 5- 730 days (End of Clause)

F-2 PROJECT COORDINATION/OTHER WORK IN THE AREA

The project site will need to remain open during the duration of the work, contractor will be expected to coordinate with District staff to a reasonable extent, see Drawings and Specifications for further information.

F-3 52.211-12 Liquidated Damages—Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $274.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of Clause)

F-4 52.236-1 Performance of Work by the Contractor (Apr 1984) The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15% percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

SECTION G--CONTRACT ADMINISTRATION DATA

G-1 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE

The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held after the date of contract award. The conference will be held at the Corvallis Science Research Lab at later date TBD.

(End of Clause)

G-2 INVOICING

All Invoices must be submitted through the Department of Treasury's Invoice Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in the previous communications from USDA and Treasury. All invoices are to be submitted via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm

Contractor is required to submit as an attachment in IPP for their invoice a cost breakdown for the invoice being submitted.

Contractor is required to forward Payrolls, via email, to the COR prior to submission of the invoice in IPP.

Contractor is required to forward daily diaries for each day worked on the project to the COR with the payrolls.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H-1 AVAILABILITY AND USE OF UTILITY SERVICES (FAR 52.236-14) (APR 1984)

(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.

(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

Utilities AvailableRate to be ChargedRestrictions on Use
Electric Power No Chargefor construction
Water No Chargefor construction
Sanitary facilities No Chargefor construction

(End of clause)

H-2 LANDSCAPE PRESERVATION

(a) Prior to excavation, the Contractor shall remove the organic surface layer of soil, including grass and small plants within the clearing limits, stockpile separately and redistribute these materials over the finished slopes on the project as directed by the Contracting Officer. The conserved organic soil layer will be approximately 6” in thickness in all locations where practical and shall be removed with a smooth-edged excavator bucket or other similar tool that is capable of separating the upper organic layer of soil from the lower soil. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. The Contractor shall confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states. If a spill of petroleum product should occur in water, the Contractor shall take immediate action to clean up or contain the spill, then immediately notify the Engineer and the Oregon Emergency Response System (OERS), telephone 1-800-452-0311 or 1-503-378-4124, and then immediately notify the Contracting Officer.

Contractor shall have a SPILL RESPONSE KIT on the project whenever equipment is operating. The spill kit shall be sufficient to absorb 34 gallons of oil, designed to float on the surface, while absorbing oil and repelling water. The KIT shall meet or exceed the physical properties of “New Pig Products Spill Kit #408”.

Oil absorbing mats are required under all stationary equipment, or equipment being serviced within the Forest Boundary to prevent leaking or spilled petroleum base products from contaminating soil and water resources. Such material will be furnished by Contactor and approved by Contracting Officer.

Servicing of all equipment shall be done only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Equipment shall be furnished on a fully operational basis, of modern design and in good operating condition with no fuel or oil leaks. Repairs and move-in/move-out are the Contractor’s responsibility. All equipment shall be power washed and shall be clean prior to entering Forest Service Land.

(c) No objectionable material shall be allowed to enter any stream, river, lake, or other body of water. Material which falls in these areas shall be retrieved and disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the project limits shall be repaired as directed by the Contracting Officer.

(d) The Contractor shall not operate equipment or otherwise disturb the natural vegetation and soil beyond the areas flagged on the ground or beyond two feet from edge of walkways, top of cuts, or toe of fills.

(e) The Contractor will make every reasonable attempt to preserve the scenic and natural environment along this construction project.

H-3 VALUE ENGINEERING

Value engineering change proposals which change the service or function of a facility or produce irreconcilable conflicts with management objectives will not be considered.

The following work is excluded from consideration under the Value Engineering clause:

None

H-4 PRODUCT SUBSTITUTION

Any modification of items, designs, materials, products or equipment (including Government-Furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

H-5 SANITATION REQUIREMENTS

Unless substitute measures or equipment are authorized in writing by the Contracting Officer, protection of air and water quality will include the use of approved chemical toilets by all persons engaged in road construction or in removing timber under this contract while they are within the boundaries of the Forest. Such facilities shall be furnished by Contractor in quantities and at locations approved by the Engineer. No habitation or overnight dwelling by employees of Contractor will be permitted on National Forest land without advance written approval from the Contracting Officer.

H-6 FINAL CLEANUP

Contractor shall remove and dispose all of its own trash and refuse from the contract area. Material to be removed includes, but is not limited to refuse such as tin cans, aluminum foil, glass, paper, garbage, grease cartridges, etc. All debris shall be disposed of off National Forest Land and in accordance with Federal, State, and Local disposal requirements.

H-7 PROTECTION OF CULTURAL RESOURCES

Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1979 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by Forest Service. Forest Service may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object which is or may be entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas or objects by either party shall be promptly reported to the other party.

Contractor shall protect all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destruction, obliteration, removal or damage during Contractor's Operations. In accordance with 36 CFR 296.14(c), Contractor shall bear costs of restoration, provided that such payment shall not relieve Contractor from civil or criminal remedies otherwise provided by law.

Wheeled or track-laying equipment shall not be operated within such areas except on roads. Unless agreed otherwise, trees will not be felled into such areas.

H-8 METHODS OF MEASUREMENT

One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:

(a) Designed Quantities (DQ). These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

(1) As a result of changes in the work authorized by the Contracting Officer.

(2) As a result of the Contracting Officer determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

(3) As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to construction.

(c) Actual Quantities (AQ). These quantities are determined from measurement of completed work.

(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract including necessary materials, equipment, and labor to complete the job. They will not be measured.

H-9 STATE ELECTRICAL INSPECTION AND COUNTY BUILDING PERMITS

The Contractor shall arrange for and provide the State Electrical inspection. When requesting the inspection inform the Building Permit Department of the federal limitation described below. The Contractor shall not obtain any building permits or inspections other than the State Electrical inspection.

Federal law validated by the State Attorney General, Oregon Department of Justice verify that the Federal Government and its Contractors may be exempted from State/Local Building Permits and Fees for projects located on Federal Installations including all federal lands. Contractor State Licenses will not be jeopardized by following this requirement to avoid the State/County permit system. This applies to the prime Contractor and all subcontractors.

AGAR 452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel: a Manager or Superintendent that will be the primary point of contact for this contract.

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

(End of clause)

AGAR 452.228-71 INSURANCE COVERAGE (NOV 1996)

Pursuant to FAR clause 52.228-5, insurance - Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

PART II--CONTRACT CLAUSES SECTION I--CONTRACT CLAUSES

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

(End of clause)

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1
Definitions (NOV 2013)
52.203-3
Gratuities (APR 1984)
52.203-5
Covenant Against Contingent Fees (MAY 2014)
52.203-6
Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7
Anti-Kickback Procedures (MAY 2014)
52.203-8
Cancellation, Rescission, and Recovery of Funds for Illegal

or Improper Activity (MAY 2014)

52.203-10
Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014)
52.203-12
Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)
52.203-17
Contractor Employee Whistleblower Rights and Requirement to Inform

Employees of Whistleblower Rights (APR 2014)

52.204-4
Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |

(MAY 2011)

52.204-10
Reporting Executive Compensation and First-Tier Subcontract Awards

(OCT 2015)

52.204-13
System for Award Management Maintenance (JULY 2013)
52.204-14
Service Contract Reporting Requirements (JAN 2014)
52.204-18
Commercial and Government Entity Code Maintenance (JUL 2016)
52.209-6
Protecting the Government's Interest when Subcontracting

with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)

52.209-9
Updates of Publicly Available Information Regarding Responsibility Matters

(JULY 2013)

52.209-10
Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)
52.215-2
Audit and Records -- Negotiation (OCT 2010)
52.219-6
Notice of Total Small Business Set-Aside (NOV 2011)
52.219-14
Limitations on Subcontracting (NOV 2011)
52.219-28
Post-Award Small Business Program Rerepresentation (JULY 2013)
52.222-3
Convict Labor (JUNE 2003)
52.222-4
Contract Work Hours and Safety Standards Act -- Overtime Compensation

(MAY 2014)

52.222-6
Construction Wage Rate Requirements (MAY 2014)
52.222-7
Withholding of Funds (MAY 2014)
52.222-8
Payrolls and Basic Records (MAY 2014)
52.222-9
Apprentices and Trainees (JULY 2005)
52.222-10
Compliance with Copeland Act Requirements (FEB 1988)
52.222-11
Subcontracts (Labor Standards) (MAY 2014)
52.222-12
Contract Termination - Debarment (MAY 2014)
52.222-13
Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14
Disputes Concerning Labor Standards (FEB 1988)
52.222-15
Certification of Eligibility (MAY 2014)
52.222-21
Prohibition of Segregated Facilities (APR 2015)
52.222-26
Equal Opportunity (APR 2015)
52.222-27
Affirmative Action Compliance Requirements for Construction (APR 2015)
52.222-35
Equal Opportunity for Veterans (OCT 2015)
52.222-36
Equal Opportunity for Workers with Disabilities (JULY 2014)
52.222-37
Employment Reports on Veterans (FEB 2016)
52.222-40
Notification of Employees Rights Under the National Labor Relations Act

(DEC 2010)

52.222-50
Combating Trafficking in Persons (MAR 2015)
52.222-54
Employment Eligibility Verification (OCT 2015)
52.222-55
Minimum Wages Under Executive Order 13658 (DEC 2015)

52.223-6 52.223-12 Drug-Free Workplace (MAY 2001) Refrigeration Equipment & Air Conditioners (MAY 1995)

52.223-11
Ozone-Depleting Substances and High Global Warming Potential

Hydrofluorocarbons (JUN 2016)

52.223-15
Energy Efficiency in Energy-Consuming Products (DEC 2007)
52.223-17
Affirmative Procurement of EPA-Designated Items in Service and Construction

Contracts (MAY 2008)

52.223-18
Encouraging Contractor Policies to Ban Test Messaging While Driving

(AUG 2011)

52.223-21
Foams (JUN 2016)
52.225-13
Restrictions on Certain Foreign Purchases (JUN 2008)
52.227-1
Authorization and Consent (DEC 2007)
52.227-2
Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)
52.227-4
Patent Indemnity -- Construction Contracts (DEC 2007)
52.228-2
Additional Bond Security (OCT 1997)
52.228-5
Insurance - Work on a Government Installation (JUN 1997)
52.228-11
Pledges of Assets (JAN 2012)
52.228-12
Prospective Subcontractor Requests for Bonds (MAY 2014)
52.228-14
Irrevocable Letter of Credit (NOV 2014)
52.228-15
Performance and Payment Bonds – Construction (OCT 2010)
52.229-2
North Carolina State and Local Sales and Use Tax (Apr 1984)
52.229-3
Federal, State, and Local Taxes (FEB 2013)
52.232-5
Payments Under Fixed-Price Construction Contracts (MAY 2014)
52.232-17
Interest (MAY 2014)
52.232-23
Assignment of Claims (MAY 2014)
52.232-27
Prompt Payment for Construction Contracts (MAY 2014)
52.232-33
Payment by Electronic Funds Transfer – System for Award Management

(JULY 2013)

52.232-39
Unenforceability of Unauthorized Obligations (JUNE 2013)
52.232-40
Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)
52.233-1
Disputes (MAY 2014)
52.233-3
Protest After Award (AUG 1996)
52.233-4
Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2
Differing Site Conditions (APR 1984)
52.236-3
Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5
Material and Workmanship (APR 1984)
52.236-6
Superintendence by the Contractor (APR 1984)
52.236-7
Permits and Responsibilities (NOV 1991)
52.236-8
Other Contracts (APR 1984)
52.236-9
Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984)

52.236-10
Operations and Storage Areas (APR 1984)
52.236-11
Use and Possession Prior to Completion (APR 1984)
52.236-12
Cleaning Up (APR 1984)
52.236-13
Accident Prevention (NOV 1991)

Alternate I (NOV 1991)

52.236-14
Availability and Use of Utility Services (APR 1984)
52.236-15
Schedules for Construction Contracts (APR 1984)

Alternate I (APR 1984)

52.236-17
Layout of Work (APR 1984)
52.236-21
Specifications and Drawings for Construction (FEB 1997)
52.236-26
Preconstruction Conference (FEB 1995)
52.242-13
Bankruptcy (JULY 1995)
52.243-4
Changes (JUNE 2007)
52.244-6
Subcontracts for Commercial Items (FEB 2016)
52.245-1
Government Property (APR 2012)
52.245-9
Use and Charges (APR 2012)
52.246-21
Warranty of Construction (MAR 1994)
52.248-3
Value Engineering – Construction (OCT 2015)
52.249-2
Termination for Convenience of the Government (Fixed-Price) (APR 2012)--

Alternate I (SEP 1996)

52.249-10
Default (Fixed-Price Construction) (APR 1984)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70
Reimbursement for Bond Premiums – Fixed-Price Construction Contracts

(NOV 1996)

452.236-71
Prohibition Against the Use of Lead-Paint (NOV 1996)
452.236-72
Use of Premises (NOV 1996)
452.236-73
Archeological or Historic Sites (FEB 1988)
452.236-74
Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76
Samples and Certificates (FEB 1988)
452.236-77
Emergency Response (NOV 1996)

52.217-7 -- Option for Increased Quantity -- Separately Priced Line Item. (Mar 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within [insert in the clause the period of time in which the Contracting Officer has to exercise the option]. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of Clause)

I-2 PAYMENT FOR MATERIALS DELIVERED OFF THE SITE

As provided in FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, material acquired for incorporation into the project, and stored off site by the Contractor, may, at the option of the Contracting Officer, be included in progress payments. Prior to payment, such material will be subject to Government inspection and must be stored separately from other materials, and be identified as, "PROPERTY OF THE UNITED STATES, Project Name and Contract Number." In addition, the Contractor shall furnish the Government with a right of ingress and egress to the property together with right of removal.

I-3 PAYMENTS FOR INCIDENTAL ITEMS

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered incidental to and included in the payment for items shown.

I-4 PUBLIC OFFICIALS NOT PERSONALLY LIABLE

There shall be no personal liability upon the Government or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.

I-5 RETURN OF PERFORMANCE AND PAYMENT BONDS

Performance and payment security furnished under this contract must be retained by the Government for a minimum of one year after acceptance of all work under the contract. Performance and payment security other than corporate or individual surety bonds will be returned to the Contractor one year after completion of work if no claims against these bonds have been filed at that time.

I-6 PAYMENT FOR PERFORMANCE AND PAYMENT SECURITY EXPENSES

It is mutually agreed that the premium costs for performance bonds, payment bonds and alternative payment protections furnished for this contract are included in the total amount bid for other items and that any payment to the Contractor for the cost of bonds made in accordance with FAR 52.232-5 refers only to corporate sureties listed in the current Department of Treasury Circular 570 and no advance payment will be made for bond premiums where other than corporate surety bonds are furnished. Bond premiums as used in this paragraph and FAR 52.232-5 shall include any Small Business Administration fees paid in connection with SBA guaranteed corporate surety bonds.

I-7 WARRANTY OF CONSTRUCTION FAR 52.246-21 (Mar 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of-

(1) The Contractor's failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall-

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

(End of clause) Alternate I (Apr 1984). If the Government specifies in the contract the use of any equipment by "brand name and model," the contracting officer may add a paragraph substantially the same as the following paragraph (k) to the basic clause:

(k) Defects in design or manufacture of equipment specified by the Government on a "brand name and model" basis, shall not be included in this warranty. In this event, the Contractor shall require any subcontractors, manufacturers, or suppliers thereof to execute their warranties, in writing, directly to the Government.

(End of clause)

52.204-19 - INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)

The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEPT 2013)

(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United States Department of Agriculture (USDA)-designated items unless—

(1) The product cannot be acquired—

(i) Competitively within a time frame providing for compliance with the contract performance schedule;

(ii) Meeting contract performance requirements; or

(iii) At a reasonable price.

(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:

(3)

(i) Spacecraft system and launch support equipment.

(ii) Military equipment, i.e., a product or system designed or procured for combat or combat- related missions.

(b) Information about this requirement and these products is available at http://www.biopreferred.gov.

(c) In the performance of this contract, the Contractor shall—

(1) Report to http://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and

(2) Submit this report no later than—

(i) October 31 of each year during contract performance; and

(ii) At the end of contract performance.

(End of clause)

52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material. “Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material…