This is a Statement of Work for the Lake Sherwood GAOA Phase 3 project located near Neola, West Virginia. The project addresses repairs to an aging dump station and associated sewer line infrastructure, along with installation of new signage.
The scope consists of six deliverables: (1) Mobilization including demobilization, erosion and sediment control, and utility locating and preservation; (2) Traffic Control to protect workers and road users during sewer line replacement and dump station upgrades; (3) Sewer Line Replacement involving removal of the old line and installation of a new 2-inch line from the lift station to the main line, including new double cleanouts and combination valves, with pressure testing required prior to acceptance; (4) Dump Station Upgrades requiring removal and replacement of water towers, water lines, sanitary hatch, and dump station pad, with new and affected water lines pressure tested to 50 psi, chlorinated, and flushed; (5) Supply of Sign Materials to be placed in the warehouse area at Lake Sherwood in a location approved by the Contracting Officer's Representative (COR); and (6) Installation of Signs for the Dump Station involving removal of existing signs and posts, backfilling with soil, and installation of new signs and posts in COR-approved locations. All work must be performed in accordance with specified sections of the contract documents.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work – Lake Sherwood GAOA Phase 3 Project Lake Sherwood GAOA Phase 3
General Information
1.0 Scope of Work
The bid consists of mobilization, traffic control, sewer line replacement, dump station upgrades, supplying sign materials and installing the signs at the dump station. All operations at the Lake Sherwood Recreation Area near Neola, WV.
2.0 Background
The Lake Sherwood dump station and associated sewer line is old and in need of repairs. New signs are also needed.
3.0 Deliverables / Schedule See
the table below.
Base Bid
Item No.
Deliverable Specification Sections Objective
Mobilization
All Sections
Mobilization, demobilization, all erosion and sediment control, and all items not incidental to or under another item. Telephone, water, electrical, and sewer utilities are in the area. The contractor is responsible for locating and preserving all existing utilities, including repair or replacement of lines damaged from contract operations.
Traffic Control
011000, 012200, 013300, 017100, 017419, 321216
Perform all necessary traffic control to protect workers and road users during contract operations.
Traffic control shall be in place during all operations for the sewer line replacement and dump station upgrades.
Sewer Line Replacement
017100, 017419, 024119, 221313, 312000, 321216, 329000, 401, 415, 702, 703, 704, Perform all necessary work to replace the sewer line from the dump station to the main line in accordance with the contract documents. The replacement shall include but is not limited to unhooking the old line and installing a new 2" line from near the lift station to hook into the main line on the other side of the paved road. New double cleanouts and combination valves will also be installed. Saw cutting asphalt and trenching across the road with an associated asphalt utility patch is incidental to this item. The new sewer line shall be pressure tested prior to acceptance.
Dump Station Upgrades
017100, 017419, 024119, 033000, 033020, 220523.12, 221313, 312000, 329000, 331415
Perform all necessary work to remove and replace the water towers, associated water lines, sanitary hatch, dump station pad, and associated items in accordance with the contract documents. New and affected water lines shall be pressure tested to 50psi, chlorinated, and flushed prior to acceptance per specifications.
Supply Sign Materials
011000, 012200, 013300, 017100, 017419
Provide new signs and associated hardware for the dump station per the schedule provided in the plans.
Place the materials in the warehouse area at Lake Sherwood in a location approved by the COR.
Install Signs for Dump Station
Remove Existing signs and posts. Backfill holes with soil. Install new signs and posts at the dump station in accordance with the contract documents. Install posts in and signs in locations approved by the COR.
017100, 017419, 024119, 033000, 033020, 312000, 329000