Att. 1 Schedule of Items 250611.docx
DOCX document 23 KB Posted
- Solicitation number
- 12445525R0011
- Issued by
-
Department of Agriculture Forest Service
About this file
The attached document is a Schedule of Items for the GAOA SUF Bunkhouse Replacement project at Seagull Guard Station in Superior National Forest, Cook County, Minnesota. The schedule outlines eight distinct line items covering the full project scope, including mobilization, general requirements, sitework (demolition and earthwork), utilities, building foundation, prefabricated bunkhouse construction, on-site MEP work, and an optional RV hookup installation. The project has a completion date of 09/30/2025, with line items structured as lump sum (LS) quantities, though specific pricing details are not populated in this document.
The schedule corresponds to a U.S. Forest Service small business set-aside solicitation (No. 12445525R0011) for replacing an existing bunkhouse with a new 2,360 square foot, 12-person crew quarters facility located at 11456 Gunflint Trail in Grand Marais, Minnesota. The project is estimated between $1-5 million, with a performance period from September 1, 2025 to September 30, 2026. Contractors must maintain active SAM registration, provide a 20% bid guarantee, and attend a mandatory pre-bid conference on July 30, 2025, with proposal submissions due by August 21, 2025.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
GAOA SUF Bunkhouse Replacement at Seagull Guard Station Seagull Guard Station Superior National Forest Cook County, Minnesota
Completion Date: 09/30/2025
| Item |
| Supplies/Services |
| Qty |
| Unit of Issue |
| Unit Price |
| Total Price |
| 0001 |
| MOBILIZATION |
| 1 |
| LS |
| $ |
| $ |
| 0002 |
| GENERAL REQUIREMENTS |
| 1 |
| LS |
| $ |
| $ |
| 0003 |
| SITEWORK – DEMO & EARTHWORK |
| 1 |
| LS |
| $ |
| $ |
| 0004 |
| SITEWORK - UTILITIES |
| 1 |
| LS |
| $ |
| $ |
| 0005 |
| BUILDING FOUNDATION & ONSITE WORK |
| 1 |
| LS |
| $ |
| $ |
| 0006 |
| PREFABRICATED / SITE-BUILT BUNKHOUSE BUILDING |
| 1 |
| LS |
| $ |
| $ |
| 0007 |
| ON-SITE MEP RELATED TO BUILDING |
| 1 |
| LS |
| $ |
| $ |
| 0008 |
| GOV. OPTION: RV HOOKUPS - |
ELEC, WATER, SEWER
| 1 |
| LS |
| $ |
| $ |
| Total |
| $ |
Unit abbreviations are defined as: LS – Lump Sum.