Statement of Work Summary: Longleaf Timber Stand Improvement

This is a Statement of Work (SOW) for timber stand improvement services in the Ocala National Forest, covering approximately 1,575 acres across Lake, Putnam, and Marion Counties in Florida, with optional expansion up to 250 additional acres. The contractor must provide all labor, equipment, tools, transportation, and supervision to cut small oaks and sand pines in recently planted longleaf pine plantations using brush cutters, chainsaws, or other approved tools. No government-furnished equipment or materials are provided. The work spans 31 identified forest compartments/stands ranging from 8 to 152 acres each, with both sand pine and oaks designated for cutting in all areas.

Technical specifications require the contractor to completely sever designated trees at the base with stump heights not exceeding 3 inches, retain all longleaf pines, cut all sand pines and oaks smaller than 3 inches diameter at breast height (dbh), and leave oaks uncut if not within 20 feet of pines. The contractor must designate a non-working, English-speaking supervisor for each crew and provide sufficient staff and equipment to treat approximately 15 acres per day. All crew members must use OSHA-required personal protective equipment including chainsaws/brush cutters, eye protection, gloves, chaps, hearing protection, long pants, and non-skid boots, and carry first aid kits. The contractor must minimize soil disturbance, avoid unnecessary erosion, protect existing trails and roads by keeping them free of slash and debris, and complete corrective work before proceeding to the next area. Measurement is based on GPS-determined acreage, with payment calculated as actual acres completed and accepted multiplied by the contract unit price. Negligent cutting of protected trees incurs a $5 penalty per tree.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Longleaf Timber Stand

Improvement

DIVISION 100 – GENERAL SPECIFICATIONS

110. General Contractor shall provide all labor, equipment, tools, transportation, and supervision to cut small oaks and pines in recently planted longleaf pine plantations on approximately 1,575 acres with optional areas added NTE 250 acres. Work includes cutting designated trees using brush cutters, chainsaws, or other approved tools. No government-furnished equipment or materials will be provided unless otherwise stated.

The Contracting Officer may substitute similar work areas within the Ranger District if original areas become unsuitable or unavailable.

120. Description and Location All work areas are within the Ocala National Forest (Lake, Putnam, and Marion Counties).

Boundaries are marked by fire lines, roads, flagging and on a geo-reference map. These stands are of mixed age and vary in vegetation density.

Comp/STD Acres Sand pine to cut Oaks to cut

43/09 17 X X 43/10 20 X X 43/22 12 X X 43/30 17 X X 43/37 79 X X

104/38 30 X X 224/06 87 X X 259/06 13 X X 259/07 30 X X 259/14 59 X X 260/14 152 X X 262/08 94 X X 266/14 17 X X 266/15 30 X X 266/19 16 X X 266/34 8 X X 268/18 25 X X 268/20 48 X X 268/29 20 X X 289/11 54 X X 289/14 90 X X 289/15 133 X X 289/21 52 X X

289/35 88 X X 290/04 94 X X 297/09 60 X X 297/10 33 X X 297/14 104 X X 297/16 41 X X 297/29 52 X X

Total Acres: 1,575 dbh = diameter at breast height (4.5 feet above ground).

130. Government-Furnished Property None.

140. Supervision Contractor must designate a non-working, English-speaking supervisor for each crew.

Written designation must define authority and establish supervisory order if multiple supervisors are listed.

DIVISION 200 – TECHNICAL SPECIFICATIONS

210. Technical Instructions

• Follow species-cutting requirements in Section 120.

• Completely sever all designated pines and oaks at the base; no hung or wedged trees allowed.

• Stump height shall not exceed 3 inches.

• All longleaf pines will be retained.

• All sand pine and oak < 3 inches dbh must be cut.

• Oaks to be cut may be left uncut if they are not close (within 20 feet) to any pines.

• Do not cut large oaks or flagged trees.

• Accidental cutting of protected trees will be evaluated. Negligent cutting will incur a $5 penalty per tree.

220. Equipment and Personnel Requirements

• Contractor shall provide enough staff/equipment to treat ~15 acres/day.

• A competent foreman is required.

• All crew members must use required PPE per OSHA.

Required equipment:

• Chainsaws/brush cutters with full PPE (eye protection, gloves, chaps, hearing protection, long pants, non-skid boots).

• First aid kits.

230. Erosion Control Work must minimize soil disturbance and avoid unnecessary erosion.

240. Protection of Improvements Contractor shall protect trails, roads, fences, monuments, and other improvements. Roads and trails must remain free of slash and debris. Unauthorized trails do not require clearing.

250. Access Some units require 4WD due to sandy, high-centered roads. Unauthorized travel ways may only be used with COR approval.

DIVISION 300 – INSPECTION AND ACCEPTANCE

Notify the COR/Inspector upon completion of each area. Any required corrective work must be completed before moving to the next area.

DIVISION 400 – MEASUREMENT AND PAYMENT

410. Measurement Acreage determined using GPS.

420. Payment Payment based on actual acres completed and accepted multiplied by the contract unit price.

Statement of Work
Longleaf Timber Stand Improvement
DIVISION 100 – GENERAL SPECIFICATIONS
110. General
120. Description and Location
Total Acres: 1,575
130. Government-Furnished Property
140. Supervision
DIVISION 200 – TECHNICAL SPECIFICATIONS
210. Technical Instructions
220. Equipment and Personnel Requirements
230. Erosion Control
240. Protection of Improvements
250. Access
DIVISION 300 – INSPECTION AND ACCEPTANCE
DIVISION 400 – MEASUREMENT AND PAYMENT
410. Measurement
420. Payment

File details come from the government source that posted it. Updated .