Suggested Timline_ 02-14-20.xlsx
XLSX spreadsheet 12 KB Posted
- Solicitation number
- 1243ZP20Q0008
- Issued by
-
Department of Agriculture Forest Service
About this file
This document outlines a federal contract opportunity for design services. The USDA Forest Service El Yunque National Forest is soliciting proposals for a 110-day contract to design the reconstruction of the Big Tree Trail and La Mina Trail and associated bridges in Puerto Rico. The estimated construction cost is between $900,000 and $1,300,000. The work will include drawings, specifications, cost estimates, and final design plans stamped by a Professional Engineer licensed in Puerto Rico. The NAICS code is 541330 for engineering services. The solicitation is anticipated to be issued on or around January 6, 2020. A non-mandatory site showing will be held on January 8 and 9 with limited space for 40 people per day at the Palo Colorado Recreation Site parking lot. Interested parties must bring their own PPE for the site visit.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 La Mina and Big Tree Trail Assessment, Trail Bridges and Structures assessment, and A-E Repair and Re-Construction Design Project
SUGGESTED TIMELINE
| Work Activity (Task Description) | Responsible Party | Duration | Start | Finish |
| Contract - Award Date | (Gov't) | 03/09/2020, Mon | 03/09/2020, Mon | |
| Pre-Work Meeting (via phone) | (Gov't)(Contractor) | 03/11/2020, Wed | 03/11/2020, Wed | |
| Issue Notice to Proceed | (Gov't) | 03/11/2020, Wed | 03/11/2020, Wed | |
| Deliverable Due: 30% Submittal | (Contractor) | 61 day(s) | 03/11/2020, Wed | 05/11/2020, Mon |
| Response Due: 30% Submittal | (Gov't) | 14 day(s) | 05/11/2020, Mon | 05/25/2020, Mon |
| Deliverable Due: 60% Submittal | (Contractor) | 45 day(s) | 05/25/2020, Mon | 07/09/2020, Thu |
| Response Due: 60% Submittal | (Gov't) | 7 day(s) | 07/09/2020, Thu | 07/16/2020, Thu |
| Deliverable Due: 90% Submittal | (Contractor) | 14 day(s) | 07/16/2020, Thu | 07/30/2020, Thu |
| Response Due: 90% Submittal | (Gov't) | 7 day(s) | 07/30/2020, Thu | 08/06/2020, Thu |
| Deliverable Due: 100% Submittal | (Contractor) | 7 day(s) | 08/06/2020, Thu | 08/13/2020, Thu |
| Total: | 155 days |
| **Refer to Section 2.7 - Deliverables of the Statement of Work for the 30%, 60%, 90% and 100% submittal requirements. |
| **The A-E shall confirm if the timeline is reasonable or propose a new timeline based on the requirements of the Deliveries or Performance |