Section F_ Deliveries of Performance.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
USDA Forest Service El Yunque National Forest La Mina and Big Tree Recreation Trail and Bridge Design Services
Solicitation number
1243ZP20Q0008
Issued by

About this file

This document outlines a federal contract opportunity with the USDA Forest Service for trail and bridge design services. The contract is a 100% small business set-aside with an estimated value between $900,000 and $1,300,000. The selected contractor will provide design and construction documents for reconstruction of the Big Tree and La Mina recreation trails and associated bridges in El Yunque National Forest, Puerto Rico. Deliverables include drawings, specifications, cost estimates, and other documents stamped by a licensed Professional Engineer. The period of performance is 110 days, with 30%, 60%, 90%, and 100% design submittals required. The solicitation is expected to be issued on or around January 6, 2020. Non-mandatory site showings will be held on January 8 and 9, 2020 for up to 40 people per date, with attendees required to bring personal protective equipment.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Contract No. 12******
La Mina and Big Tree Trail Assessment, Trail Bridges and Structures assessment, and A-E Repair and Re-Construction Design Project

SUGGESTED TIMELINE

Work Activity (Task Description)Responsible PartyDurationStartFinish
Contract - Award Date(Gov't)02/24/2020, Mon02/24/2020, Mon
Pre-Work Meeting (via phone)(Gov't)(Contractor)02/26/2020, Wed02/26/2020, Wed
Issue Notice to Proceed(Gov't)02/26/2020, Wed02/26/2020, Wed
Deliverable Due: 30% Submittal(Contractor)30 day(s)02/26/2020, Wed03/27/2020, Fri
Response Due: 30% Submittal(Gov't)14 day(s)03/27/2020, Fri04/10/2020, Fri
Deliverable Due: 60% Submittal(Contractor)31 day(s)04/10/2020, Fri05/11/2020, Mon
Response Due: 60% Submittal(Gov't)7 day(s)05/11/2020, Mon05/18/2020, Mon
Deliverable Due: 90% Submittal(Contractor)14 day(s)05/18/2020, Mon06/01/2020, Mon
Response Due: 90% Submittal(Gov't)7 day(s)06/01/2020, Mon06/08/2020, Mon
Deliverable Due: 100% Submittal(Contractor)7 day(s)06/08/2020, Mon06/15/2020, Mon
Total:110 days

*Refer to Section 2.6 - 2.9 of the Statement of Work for the 30%, 60%, 90% and 100% submittal requirements.