Schedule of Items
Sula Ranger Station Water System Improvements
Bitterroot National Forest
| Item No. |
| Item Description |
| Method |
| Units |
| Quantity |
| Unit Cost |
| Total Cost |
| 0001 |
| 010250 |
| Construction Surveying and Staking |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0002 |
| 012910 |
| Mobilization |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0003 |
| 015100 |
| Erosion Control |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0004 |
| 024100 |
| Demolition (Existing Pump House) |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0005 |
| 133422 |
| Pump House Foundation & Utility Preparation |
| AQ |
| EA |
| 1 |
| $ |
| $ |
| 0006 |
| 133423 |
| Construct Wood Framed Pump House |
| AQ |
| EA |
| 1 |
| $ |
| $ |
| 0007 |
| 221000.1 |
| 2" Galvanized Water Line |
| AQ |
| LF |
| 10 |
| $ |
| $ |
| 0008 |
| 221000.2 |
| Plumbing Appurtenances Inside Pump House |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0009 |
| 260500 |
| Electrical Controls - Transducer, Conduit, etc. |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0010 |
| 310000.1 |
| Excavation |
| AQ |
| CY |
| 5 |
| $ |
| $ |
| 0011 |
| 310000.2 |
| Embankment |
| AQ |
| CY |
| 5 |
| $ |
| $ |
| 0012 |
| 311000.1 |
| Site Clearing |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0013 |
| 311000.2 |
| Remove, Salvage, and Replace Gravel Surface |
| AQ |
| CY |
| 4 |
| $ |
| $ |
| 0014 |
| 321123 |
| 3/4" Minus Aggregate base Course, Gravel (6" Thick) |
| AQ |
| CY |
| 2 |
| $ |
| $ |
| 0015 |
| 321216 |
| Asphalt Concrete Pavement (3" Thick) |
| AQ |
| SY |
| 7 |
| $ |
| $ |
| 0016 |
| 329000 |
| Surface Restoration |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0017 |
| 330110.91 |
| Rehabilitation of Existing Water Supply Well |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
| 0018 |
| 331000.1 |
| 2" HDPE DR11 Water Line |
| AQ |
| LF |
| 1100 |
| $ |
| $ |
| 0019 |
| 331000.2 |
| 2" Ball Valve - Storage Tank Drain Line |
| AQ |
| EA |
| 1 |
| $ |
| $ |
| 0020 |
| 331000.3 |
| 6" Gate Valve - Storage Tank Distribution Line |
| AQ |
| EA |
| 1 |
| $ |
| $ |
| 0021 |
| 331000.4 |
| 2" Fittings (Bends) |
| AQ |
| EA |
| 10 |
| $ |
| $ |
| 0022 |
| 331000.5 |
| Connect 2" HDPE To Proposed Pump House |
| AQ |
| LF |
| 1 |
| $ |
| $ |
| 0023 |
| 331000.6 |
| Connect to Existing Storage Tank |
| LSQ |
| LS |
| 1 |
| $ |
| $ |
CY=Cubic Yard EA=Each LS-Lump Sum LF-Linear Foot SY-Square Yard
SCHEDULE NOTES
a) One award will be made from this solicitation; contractors must submit pricing for all items.
b) In the event of an error in extending the item prices, unit prices will govern, unless otherwise determined by the Contracting Officer, in accordance with applicable regulations.
c) Offers for quantities less than those listed in the numbered items may be rejected.
d) Payment for bond premiums in accordance with FAR 52.232-5. Payments under Fixed-Price Construction Contracts shall not be in addition to the contract price but can be included under Mobilization.
e) The pay items in the Schedule of Items may have suffixes that do not appear on the pay items in the specifications. The suffixes pertain only to sizes, classes, and/or types indicated in the item ‘Descriptions,’ and are used by the Government for computer tabulation of price schedules. For the abbreviations in the schedule descriptions, see Special Project Specification, SPS 101 (07/07/1997).
f) One contract will be awarded to the responsive and responsible proposer offering the best value to the Government.
g) The successful Contractor must be registered in the System for Award Management (SAM) data base before an award is issued.
h) This is a Request for Proposal (RFP); no public opening will be held. Results will not be made public prior to the award. Proposals submitted in response to this RFP will not be returned and will be retained by the U.S. Forest Service for official record purposes. This RFP does not commit the Government to pay any costs incurred in the preparation or the submission of a proposal, or to make any award.
i) Proposals received after the stated closing date and time for submission will be deemed late and will not be considered for the award. Contractors are urged to thoroughly read the RFP and to review all attachments prior to preparing and submitting a proposal.