1240LU25R0016-0001 Revised Attachment 1 SOI GAOA Sula Housing Water System BNF.docx
DOCX document 26 KB Posted
- Solicitation number
- 1240LU25R0016
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Schedule of Items (SOI) for the GAOA Sula Housing Water System Improvements project in Ravalli County, Montana, issued by the Department of Agriculture Forest Service. The solicitation (1240LU25R0016) covers comprehensive water system infrastructure upgrades at the Sula Ranger Station, including construction surveying, site preparation, demolition of an existing pump house, and installation of new water system components.
The project scope involves multiple key construction elements: building a new wood-framed pump house, installing 1,100 linear feet of 2" HDPE water line, rehabilitating an existing water supply well, implementing electrical controls, and performing site restoration. The solicitation includes 21 distinct pay items with estimated quantities and unit pricing, ranging from excavation and embankment to valve installations and surface restoration. A site visit is scheduled for July 9th at the Sula Ranger Station, with questions due by July 15th, 2025. The project appears to be funded under the Great American Outdoors Act (GAOA) and focuses on critical infrastructure improvements for the Bitterroot National Forest housing and district water system.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART 1 – THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES
Sula Ranger Station Water System Improvements Ravalli County, Montana
B-1 Schedule of Items
| Pay Item |
| Description |
| Meth of |
Meas.
Unit
Estimated Qty
Unit Price Total
BASE PROPOSAL
| 010250 |
| Construction Surveying and Staking |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 012910 |
| Mobilization |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 015100 |
| Erosion Control |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 024100 |
| Demolition (Existing Pump House) |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 133422 |
| Pump House Foundation & Utility Preparation |
| AQ |
| EA |
| 1 |
| $________ |
| $________ |
| 133423 |
| Wood Framed Pump House |
| AQ |
| EA |
| 1 |
| $________ |
| $________ |
| 221000.1 |
| 2” Galvanized Water Line |
| AQ |
| LF |
| 10 |
| $________ |
| $________ |
| 221000.2 |
| Plumbing Appurtenances Inside Pump House |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 260500 |
| Electrical Controls – Transducer, Conduit, Etc. |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 310000.1 |
| Excavation |
| AQ |
| CY |
| 5 |
| $________ |
| $________ |
| 310000.2 |
| Embankment |
| AQ |
| CY |
| 5 |
| $________ |
| $________ |
| 311000.1 |
| Site Clearing |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 311000.2 |
| Remove, Salvage, And Replace Gravel Surface |
| AQ |
| CY |
| 4 |
| $________ |
| $________ |
| 321123 |
| ¾” Minus Aggregate Base Course, Gravel (6” Thick) |
| AQ |
| CY |
| 2 |
| $________ |
| $________ |
| 321216 |
| Asphalt Concrete Pavement (3” Thick) |
| AQ |
| SY |
| 7 |
| $________ |
| $________ |
| 329000 |
| Surface Restoration |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 330110.91 |
| Rehabilitation of Existing Water Supply Well |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
| 331000.1 |
| 2” HDPE DR11 Water Line |
| AQ |
| LF |
| 1100 |
| $________ |
| $________ |
| 331000.2 |
| 2” Ball Valve – Storage tank Drain Line |
| AQ |
| EA |
| 1 |
| $________ |
| $________ |
| 331000.3 |
| 6” Gate Valve -Storage Tank Distribution Line |
| AQ |
| EA |
| 1 |
| $________ |
| $________ |
| 331000.4 |
| 2” Fittings (Bends) |
| AQ |
| EA |
| 10 |
| $________ |
| $________ |
| 331000.5 |
| Connect 2” HDPE to Proposed Pump House |
| AQ |
| LF |
| 1 |
| $________ |
| $________ |
| 331000.6 |
| Connect to Existing Storage Tank |
| LSQ |
| LS |
| 1 |
| $________ |
| $________ |
TOTAL BASE PROPOSAL
* Designated Method of Measurement DQ – Designed Quantities; AQ – Actual Quantities, LSQ – Lump Sum Quantities;
B-1 Notes
1. Bidder must bid on all items. Round to nearest cent.
2. Item 133423 was changed from a precast concrete pump house to a wood framed pump house. Requirements of the wood framed pump house are outlined in Section C Statement of Work.
3. In the event of an error in extending bid prices, unit prices will govern unless otherwise determined by the Contracting Officer in accordance with applicable regulations.
4. Offers for quantities less than those listed in the numbered items may be rejected.
5. Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include payment bond under Item 01 Mobilization.
6. The Government reserves the right to request additional information as required to fully understand the Contractor’s pricing structure and determine its reasonableness.
7. Contingency costs are not permissible in accordance with FAR 31.205-7. Unforeseen conditions are addressed under the following FAR clauses: 52.236-2 and 52.243-4 (see Section I).