1240LU25Q0070 Attachment 3 Project Specifications.docx
DOCX document 281 KB Posted
- Solicitation number
- 1240LU25Q0070
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Project Manual for the Bitterroot Facility Painting Projects located in Stevensville and Darby, Montana, prepared for the U.S. Forest Service. The project involves comprehensive painting work for three ranger stations: Stevensville Ranger Station, Darby Ranger Station, and West Fork Ranger Station. The painting specifications cover exterior surfaces including doors, door frames, trim, fascia, siding, handrails, and posts, with specific requirements for surface preparation, paint systems, and application techniques.
The project manual includes detailed technical specifications across multiple divisions, focusing on General Requirements (Division 01), Existing Conditions (Division 02), Thermal and Moisture Protection (Division 07), and Finishes (Division 09). The painting specifications prescribe premium grade paint systems, primarily using Sherwin-Williams products, with specific protocols for surface preparation, primer application, and finish coats. The Contracting Officer Representative is Shawn Boelman from the Bitterroot National Forest, and the project is scheduled for completion by June 1, 2025. The manual provides comprehensive guidelines for contractors, including requirements for product submittals, quality control, waste management, and project closeout procedures.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL FOR:
BITTERROOT FACILITY PAINTING PROJECTS
Stevensville, MT 59870 Darby, MT 59829
Date: June 1, 2025
BID SPECIFICATIONS
PROJECT INFORMATION SHEET
BRF FACILITY PAINTING PROJECTS
PROJECT LOCATION
Stevensville Ranger Station 88 Main Street Stevensville, MT 59808
Darby Ranger Station 712 N. Main Street Darby, MT 59829
West Fork Ranger Station 6735 West Fork Road Darby, MT 59829
CONTRACTING OFFICER REPRESENTATIVE:
U.S. Forest Service Shawn Boelman Bitterroot NF – Facilities Engineer shawn.boelman@usda.gov
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 2500 SUBSTITUTION PROCEDURES
01 3000 ADMINISTRATIVE REQUIREMENTS
01 4000 QUALITY REQUIREMENTS
01 5000 TEMPORARY FACILITIES AND CONTROLS
01 5713 TEMPORARY EROSION AND SEDIMENT CONTROL
01 6000 PRODUCT REQUIREMENTS
01 7000 EXECUTION AND CLOSEOUT REQUIREMENTS
01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 7800 CLOSEOUT SUBMITTALS
DIVISION 02 - EXISTING CONDITIONS
02 4100 DEMOLITION
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 9200 JOINT SEALANTS
DIVISION 09 - FINISHES
09 9123 EXTERIOR PAINTING
TOC Page 1 of 1
SECTION 01 2500 SUBSTITUTION PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Section includes administrative and procedural requirements for substitutions.
1.02 DEFINITIONS
A. Substitutions: Changes proposed by contractor in products, materials, equipment and methods of construction from those required by the contract documents.
1.03 SUBMITTAL
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Substitution Requests: Submit electronic copy of request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and drawing numbers and titles.
1. Documentation: Show compliance with requirements for substitution and the following , as applicable:
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.
b. Coordination information, including a list of changes or modifications needed to other parts of the work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities or proposed substitution with those of the work specified. Include annotated copy of applicable specification section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, substantial design characteristics, warranties and specific features and requirements indicated. Indicate deviations, if any, from work specified.
d. Product data, including drawings and descriptions of products an fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable and requested.
g. List of similar installations for completed project names and addresses and names and addresses of Architects and Owners.
h. Material test reports from qualified testing agency indicating and interpreting tst results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for project, from ICC-ES.
j. Detailed comparison of Contractor's construction schedule using proposed substitution from products specified in work, including effect overall contract time. If specified product or methods of construction cannot be provided within the contract time, include letter from manufacturer, or manufacturer's letterhead, stating receipt of purchase order, lack of availbility, or delay in delivery.
k. Cost information, including a proposal change, if any, in contract sum.
l. Contractors certification that proposed substitution complies with requirements in the contract documents except as indicated in substitution request, is compatible with related materials, and is appropriate fo applications indicated.
m. Contractor waiver rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
1.04 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests of recommended by manufacturer.
B.
PART 2 PRODUCTS
2.01 PRODUCT
A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 15 day prior to time required for preparation and review of related Submittal.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied.
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Requested substitution will not adversely affect Contractor's construction schedule.
c. Requested substitution has received necessary approvals of authorities having jurisdiction.
d. Requested substitution is compatible with other portions of the work.
e. Requested substitution has been coordinated with other portions of the work.
f. Requested substitution provides specific warranty.
g. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
h. Requested substitution will provide identical visual effect to specified products in every regard.
2. Substitution for Convenience: Not Allowed.
PART 3 - NOT USED
END OF SECTION
Bitterroot Facilities Painting Projects 01 2500 - 1 Substitution Procedures
SECTION 01 3000 ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Electronic document submittal.
B. General administrative requirements.
C. Electronic document submittal service.
D. Preconstruction meeting.
E. Progress meetings.
F. Construction progress schedule.
G. Contractor's daily reports.
H. Progress photographs.
I. Submittals for review, information, and project closeout.
J. Submittal procedures.
1.02 GENERAL ADMINISTRATIVE REQUIREMENTS
A. Comply with requirements of Section 01 7000 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.
B. Make the following types of submittals to Contracting Officer:
1. Requests for Interpretation (RFI).
2. Requests for substitution.
3. Shop drawings, product data, and samples.
4. Test and inspection reports.
5. Design data.
6. Manufacturer's instructions and field reports.
7. Applications for payment and change order requests.
8. Progress schedules.
9. Coordination drawings.
10. Correction Punch List and Final Correction Punch List for Substantial Completion.
11. Closeout submittals. PART 2 PRODUCTS - NOT USED PART 3 EXECUTION
3.01 ELECTRONIC DOCUMENT SUBMITTAL
A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF) format.
1. Besides submittals for review, information, and closeout, this procedure applies to requests for information (RFI's) progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, and any other document any participant wishes to make part of the project record.
3.02 PRECONSTRUCTION MEETING
A. Attendance Required:
1. Owner.
2. Contracting Officer.
3. Contractor.
B. Agenda:
1. Execution of Forest Service-Contractor Agreement.
2. Submission of executed bonds and insurance certificates.
Bitterroot Facilities Painting Projects 01 3000 - 1 Administrative Requirements
3. Distribution of Contract Documents.
4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.
5. Designation of personnel representing the parties to Contract, [ ] and Contracting Officer.
6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
7. Scheduling.
C. Record minutes and distribute copies within two days after meeting to participants, with two copies to Owner, participants, and those affected by decisions made.
D. Contractor will record minutes and distribute copies within seven days after meeting to participates, with one copy to Owner, participants, and those affected by decisions made.
3.03 PROGRESS MEETINGS
A. Schedule and administer meetings throughout progress of the work at maximum bi-monthly intervals.
B. Attendance Required:
1. Contractor.
2. Owner.
3. Contractor's superintendent.
4. [ ].
C. Agenda:
1. Review minutes of previous meetings.
2. Review of work progress.
3. Field observations, problems, and decisions.
4. Identification of problems that impede, or will impede, planned progress.
5. Review of submittals schedule and status of submittals.
6. Maintenance of progress schedule.
7. Corrective measures to regain projected schedules.
8. Planned progress during succeeding work period.
9. Maintenance of quality and work standards.
10. Effect of proposed changes on progress schedule and coordination.
11. Other business relating to work.
D. Contractor will record minutes and distribute copies within seven days after meeting to participates, with one copy to Owner, participants, and those affected by decisions made.
E. Contractor will record minutes and distribute copies within seven days after meeting to participates, with one copy to Owner, participants, and those affected by decisions made.
3.04 CONSTRUCTION PROGRESS SCHEDULE
A. If preliminary schedule requires revision after review, submit revised schedule within 10 days.
B. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.
C. Within 10 days after joint review, submit complete schedule.
D. Submit updated schedule with each Application for Payment.
3.05 SUBMITTALS FOR REVIEW
A. When the following are specified in individual sections, submit them for review:
1. Product data.
2. Shop drawings.
3. Samples for selection.
4. Samples for verification.
B. Submit to Contracting Officer for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.
C. Samples will be reviewed for aesthetic, color, or finish selection.
D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 7800 - Closeout Submittals.
3.06 SUBMITTALS FOR INFORMATION
A. When the following are specified in individual sections, submit them for information:
1. Design data.
2. Certificates.
3. Test reports.
4. Inspection reports.
5. Manufacturer's instructions.
6. Manufacturer's field reports.
7. Other types indicated.
B. Submit for Contracting Officers's knowledge as contract administrator or for Owner.
3.07 SUBMITTALS FOR PROJECT CLOSEOUT
A. Submit Correction Punch List for Substantial Completion.
B. Submit Final Correction Punch List for Substantial Completion.
C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 7800 - Closeout Submittals:
1. Project record documents.
2. Operation and maintenance data.
3. Warranties.
4. Bonds.
5. Other types as indicated.
D. Submit for Owner's benefit during and after project completion.
3.10 SUBMITTAL PROCEDURES
A. Shop Drawing Procedure:
1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting the Contract Documents and coordinating related work.
2. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.
B. Transmit each submittal with a copy of approved submittal form.
C. Transmit each submittal with approved form.
D. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.
E. Identify Project, Contractor, Sub-Contractor or supplier, pertinent drawings and detail number, and specification section number, as appropriate on each copy.
F. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and contract documents.
G. Schedule submittals to expedite the project, and coordinate submission of related items.
H. For each submittal for review, allow 15 days excluding delivery time to and from the contractor.
I. Identify variations from contract documents and product or system limitations that may be detrimental to successful performance of the complete work.
J. Provide space for Contractor and Mosaic Architecture review stamps.
K. When revised for resubmission, identify all changes made since previous submission.
L. Distribute reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.
M. Submittals not requested will not be recognized or processed.
END OF SECTION
SECTION 01 4000 QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. References and standards.
B. Testing and inspection agencies and services.
C. Control of installation.
D. Mock-ups.
E. Tolerances.
1.02 REFERENCE STANDARDS
A. ASTM C1021 - Standard Practice for Laboratories Engaged in Testing of Building Sealants 2008 (Reapproved 2019).
B. ASTM C1077 - Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation 2017.
C. ASTM C1093 - Standard Practice for Accreditation of Testing Agencies for Masonry 2019.
D. ASTM D3740 - Standard Practice for Minimum Requirements for Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction 2019.
E. ASTM E329 - Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection 2021.
F. ASTM E543 - Standard Specification for Agencies Performing Nondestructive Testing 2021.
G. IAS AC89 - Accreditation Criteria for Testing Laboratories 2020.
1.03 REFERENCES AND STANDARDS
A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.
B. Comply with reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.
C. Obtain copies of standards where required by product specification sections.
D. Maintain copy at project site during submittals, planning, and progress of the specific work, until Substantial Completion.
E. Should specified reference standards conflict with Contract Documents, request clarification from Contracting Of before proceeding.
1.04 TESTING AND INSPECTION AGENCIES AND SERVICES
A. Owner will employ and pay for services of an independent testing agency to perform other specified testing.
1. Provide all structural code required testing.
2. Soils testing in accordance with Geo-tech report.
B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.
PART 2 PRODUCTS - NOT USED PART 3 EXECUTION
3.01 CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.
B. Comply with manufacturers' instructions, including each step in sequence.
Bitterroot Facilities Painting Projects 01 4000 - 1 Quality Requirements
C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Contracting Officer before proceeding.
D. Comply with specified standards as minimum quality for the work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Have work performed by persons qualified to produce required and specified quality.
F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.
G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.
3.02 MOCK-UPS
A. Tests shall be performed under provisions identified in this section and identified in the respective product specification sections.
B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.
C. Contracting Officer will use accepted mock-ups as a comparison standard for the remaining Work.
D. Where mock-up has been accepted by Contracting Officer and is specified in product specification sections to be removed, protect mock-up throughout construction, remove mock- up and clear area when directed to do so by Contracting Officer.
3.03 TOLERANCES
A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.
B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from Contracting Officer before proceeding.
C. Adjust products to appropriate dimensions; position before securing products in place.
3.04 TESTING AND INSPECTION
A. Testing Agency Duties:
1. Provide qualified personnel at site. Cooperate with Contracting Officer and Contractor in performance of services.
2. Perform specified sampling and testing of products in accordance with specified standards.
3. Ascertain compliance of materials and mixes with requirements of Contract Documents.
4. Promptly notify Contracting Officer and Contractor of observed irregularities or non- compliance of Work or products.
5. Perform additional tests and inspections required by Contracting Officer.
6. Submit reports of all tests/inspections specified.
B. Limits on Testing/Inspection Agency Authority:
1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.
2. Agency may not approve or accept any portion of the Work.
3. Agency may not assume any duties of Contractor.
4. Agency has no authority to stop the Work.
C. Contractor Responsibilities:
1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.
2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.
3. Provide incidental labor and facilities:
a. To provide access to Work to be tested/inspected.
b. To obtain and handle samples at the site or at source of Products to be tested/inspected.
c. To facilitate tests/inspections.
d. To provide storage and curing of test samples.
4. Notify Contracting Officer and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.
5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.
6. Arrange with Owner's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.
D. Re-testing required because of non-compliance with specified requirements shall be performed by the same agency on instructions by Contracting Officer.
E. Re-testing required because of non-compliance with specified requirements shall be paid for by Contractor.
3.05 DEFECT ASSESSMENT
A. Replace Work or portions of the Work not complying with specified requirements.
B. If, in the opinion of Contracting Officer, it is not practical to remove and replace the work, Contracting Officer will direct an appropriate remedy or adjust payment.
END OF SECTION
Bitterroot Facilities Painting Projects 01 5000 - 1 Temporary Facilities and Controls
SECTION 01 6000 PRODUCT REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General product requirements.
B. Transportation, handling, storage and protection.
C. Product option requirements.
D. Substitution limitations.
E. Maintenance materials, including extra materials, spare parts, tools, and software.
1.02 SUBMITTALS
A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.
B. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
C. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.
1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.
1.03 QUALITY ASSURANCE
A. Source Limitations: To the fullest extent possible, provide products of the same kind and from a single source.
B. Compatibility of Options: When the contractor is given the option of selecting between two or more products for use on the project, the product selected shall be compatible with products previously selected, even if previously selected products were also options.
C. Nameplates: Except for the required labels and operating data, do not attach or imprint manufacturer's or producers nameplates or trademarks on exposed surfaces of products which will be exposed to view in occupied spaces or on the exterior.
1. Labels: Locate required product labels and stamps on concealed surface or where required for observation after installation, on an acceptable surface that is not conspicuous.
2. Equipment Nameplates: Provide a permanent nameplate on each item of service connected or power operated equipment. Locate on an easily accessible surface which is inconspicuous in occupied space. The nameplates shall contain, as applicable, the following information and other essential operating data:
a. Name of product and manufacturer.
b. Model and serial number.
c. Capacity.
d. Speed.
e. Rating.
1.04 PRODUCT, DELIVERY, STORAGE AND HANDLING
A. Should space on site be adequate for storage of equipment and materials to be incorporated in the work, the contractor and all sub-contractor will be required to provide off-site storage for such materials and equipment.
1. Locations and facilities for off-site storage shall be identified for the CO.
2. Off-Site storage shall be governed by requirements of Article 9.3.2 of the General Conditions.
B. Deliver, store and handle products in accordance with the manufacturer's recommendations, using means and methods that will prevent damage, deterioration and loss, including theft.
Bitterroot Facilities Painting Projects 01 6000 - 1 Product Requirements
1. Schedule delivery to minimize long-term storage at the site and to prevent overcrowding of construction spaces.
2. Coordinate delivery and installation time to ensure minimum holding time of items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft and other losses.
3. Deliver products to the site in the manufacturer's original sealed container and other packaging system, complete the labels and instructions for handling, storing, unpacking, protecting and installing.
4. Inspect products upon delivery to ensure compliance with the construction documents and to ensure that products are undamaged and properly protected.
5. Store products in a manner that will facilitate inspection and measurement of quantity or counting of units.
6. Store heavy materials away from the project structure in a manner that will not endanger the supporting construction.
7. Store products subject to damage by the elements above ground, under cover in a weather tight enclosure with ventilation adequate to prevent condensation.
PART 2 PRODUCTS
2.01 NEW PRODUCTS
A. Provide new products unless specifically required or permitted by Contract Documents.
B. Use of products having any of the following characteristics is not permitted:
1. Made using or containing CFC's or HCFC's.
2. Made of wood from newly cut old growth timber.
3. Containing lead, cadmium, or asbestos.
C. Where other criteria are met, Contractor shall give preference to products that:
1. If used on interior, have lower emissions.
2. If wet-applied, have lower VOC content.
3. Have longer documented life span under normal use.
4. Are made of recycled materials.
2.02 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.
B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.
C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions: Submit a request for substitution for any manufacturer not named.
2.03 MAINTENANCE MATERIALS
A. Furnish extra materials, spare parts, tools, and software of types and in quantities specified in individual specification sections.
B. Deliver to Project site; obtain receipt prior to final payment.
PART 3 EXECUTION
3.01 SUBSTITUTION LIMITATIONS
A. See Section 01 2500 - Substitution Procedures.
3.02 TRANSPORTATION AND HANDLING
A. Package products for shipment in manner to prevent damage; for equipment, package to avoid loss of factory calibration.
B. If special precautions are required, attach instructions prominently and legibly on outside of packaging.
C. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.
D. Transport and handle products in accordance with manufacturer's instructions.
E. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas.
F. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.
G. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage, and to minimize handling.
H. Arrange for the return of packing materials, such as wood pallets, where economically feasible.
3.03 STORAGE AND PROTECTION
A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication. See Section 01 7419.
B. Store and protect products in accordance with manufacturers' instructions.
C. Store with seals and labels intact and legible.
D. Store sensitive products in weathertight, climate-controlled enclosures in an environment favorable to product.
E. For exterior storage of fabricated products, place on sloped supports above ground.
F. Protect products from damage or deterioration due to construction operations, weather, precipitation, humidity, temperature, sunlight and ultraviolet light, dirt, dust, and other contaminants.
G. Comply with manufacturer's warranty conditions, if any.
H. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.
I. Prevent contact with material that may cause corrosion, discoloration, or staining.
J. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.
K. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.
END OF SECTION
SECTION 01 7000
EXECUTION AND CLOSEOUT REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Examination, preparation, and general installation procedures.
B. Requirements for alterations work, including selective demolition.
C. Pre-installation meetings.
D. Cutting and patching.
E. Surveying for laying out the work.
F. Cleaning and protection.
G. Demonstration and instruction of Owner personnel.
H. Closeout procedures, including Contractor's Correction Punch List, except payment procedures.
I. General requirements for maintenance service.
1.02 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Cutting and Patching: Submit written request in advance of cutting or alteration that affects:
1. Structural integrity of any element of Project.
2. Integrity of weather exposed or moisture resistant element.
3. Efficiency, maintenance, or safety of any operational element.
4. Visual qualities of sight exposed elements.
5. Work of Owner or separate Contractor.
1.03 PROJECT CONDITIONS
A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.
B. Protect site from puddling or running water. Provide water barriers as required to protect site from soil erosion.
C. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.
D. Dust Control: Execute work by methods to minimize raising dust from construction operations. Provide positive means to prevent air-borne dust from dispersing into atmosphere and over adjacent property.
E. Erosion and Sediment Control: Plan and execute work by methods to control surface drainage from cuts and fills, from borrow and waste disposal areas. Prevent erosion and sedimentation.
1. Minimize amount of bare soil exposed at one time.
2. Provide temporary measures such as berms, dikes, and drains, to prevent water flow.
3. Construct fill and waste areas by selective placement to avoid erosive surface silts or clays.
4. Periodically inspect earthwork to detect evidence of erosion and sedimentation; promptly apply corrective measures.
F. Noise Control: Provide methods, means, and facilities to minimize noise produced by construction operations.
1.04 COORDINATION
A. Coordinate scheduling, submittals, and work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.
B. Notify affected utility companies and comply with their requirements.
Bitterroot Facilities Painting Projects Execution and Closeout Requirements 01 7000 - 1
C. Verify that utility requirements and characteristics of new operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.
D. Coordinate space requirements, supports, and installation of mechanical and electrical work that are indicated diagrammatically on drawings. Follow routing indicated for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
E. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.
F. Coordinate completion and clean-up of work of separate sections.
G. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Owner's activities.
PART 2 PRODUCTS
2.01 PATCHING MATERIALS
A. New Materials: As specified in product sections; match existing products and work for patching and extending work.
B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.
C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01 6000 - Product Requirements.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work. Start of work means acceptance of existing conditions.
B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached.
C. Examine and verify specific conditions described in individual specification sections.
D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication.
E. Verify that utility services are available, of the correct characteristics, and in the correct locations.
F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions.
3.02 PREPARATION
A. Clean substrate surfaces prior to applying next material or substance.
B. Seal cracks or openings of substrate prior to applying next material or substance.
C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.
3.03 LAYING OUT THE WORK
A. Verify locations of survey control points prior to starting work.
B. Promptly notify Contracting Officer of any discrepancies discovered.
C. Protect survey control points prior to starting site work; preserve permanent reference points during construction.
D. Promptly report to Contracting Officer the loss or destruction of any reference point or relocation required because of changes in grades or other reasons.
E. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Contracting Officer.
F. Utilize recognized engineering survey practices.
G. Establish a minimum of two permanent bench marks on site, referenced to established control points. Record locations, with horizontal and vertical data, on project record documents.
H. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar appropriate means:
1. Site improvements including pavements; stakes for grading, fill and topsoil placement; utility locations, slopes, and invert elevations.
2. Grid or axis for structures.
3. Building foundation, column locations, ground floor elevations.
I. Periodically verify layouts by same means.
J. Maintain a complete and accurate log of control and survey work as it progresses.
3.04 GENERAL INSTALLATION REQUIREMENTS
A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement.
B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated.
C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated.
D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated.
E. Make neat transitions between different surfaces, maintaining texture and appearance.
3.05 ALTERATIONS
A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only.
1. Verify that construction and utility arrangements are as indicated.
2. Report discrepancies to Contracting Officer before disturbing existing installation.
3. Beginning of alterations work constitutes acceptance of existing conditions.
B. Remove existing work as indicated and as required to accomplish new work.
1. Remove items indicated on drawings.
2. Relocate items indicated on drawings.
3. Where new surface finishes are to be applied to existing work, perform removals, patch, and prepare existing surfaces as required to receive new finish; remove existing finish if necessary for successful application of new finish.
4. Where new surface finishes are not specified or indicated, patch holes and damaged surfaces to match adjacent finished surfaces as closely as possible.
C. Services (Including but not limited to HVAC, Plumbing, Fire Protection, Electrical, Telecommunications, and [ ]): Remove, relocate, and extend existing systems to accommodate new construction.
1. Maintain existing active systems that are to remain in operation; maintain access to equipment and operational components; if necessary, modify installation to allow access or provide access panel.
2. Where existing active systems serve occupied facilities but are to be replaced with new services, maintain existing systems in service until new systems are complete and ready for service.
a. Disable existing systems only to make switchovers and connections; minimize duration of outages.
b. Provide temporary connections as required to maintain existing systems in service.
3. Verify that abandoned services serve only abandoned facilities.
4. Remove abandoned pipe, ducts, conduits, and equipment , including those above accessible ceilings; remove back to source of supply where possible, otherwise cap stub and tag with identification; patch holes left by removal using materials specified for new construction.
D. Protect existing work to remain.
1. Prevent movement of structure; provide shoring and bracing if necessary.
2. Perform cutting to accomplish removals neatly and as specified for cutting new work.
3. Repair adjacent construction and finishes damaged during removal work.
E. Adapt existing work to fit new work: Make as neat and smooth transition as possible.
F. Patching: Where the existing surface is not indicated to be refinished, patch to match the surface finish that existed prior to cutting. Where the surface is indicated to be refinished, patch so that the substrate is ready for the new finish.
G. Refinish existing surfaces as indicated:
1. Where rooms or spaces are indicated to be refinished, refinish all visible existing surfaces to remain to the specified condition for each material, with a neat transition to adjacent finishes.
2. If mechanical or electrical work is exposed accidentally during the work, re-cover and refinish to match.
H. Clean existing systems and equipment.
I. Remove demolition debris and abandoned items from alterations areas and dispose of off-site; do not burn or bury.
J. Do not begin new construction in alterations areas before demolition is complete.
K. Comply with all other applicable requirements of this section.
3.06 CUTTING AND PATCHING
A. Whenever possible, execute the work by methods that avoid cutting or patching.
B. See Alterations article above for additional requirements.
C. Perform whatever cutting and patching is necessary to:
1. Complete the work.
2. Fit products together to integrate with other work.
3. Provide openings for penetration of mechanical, electrical, and other services.
4. Match work that has been cut to adjacent work.
5. Repair areas adjacent to cuts to required condition.
6. Repair new work damaged by subsequent work.
7. Remove samples of installed work for testing when requested.
8. Remove and replace defective and non-complying work.
D. Execute work by methods that avoid damage to other work and that will provide appropriate surfaces to receive patching and finishing. In existing work, minimize damage and restore to original condition.
E. Employ original installer to perform cutting for weather exposed and moisture resistant elements, and sight exposed surfaces.
F. Cut rigid materials using masonry saw or core drill. Pneumatic tools not allowed without prior approval.
G. Restore work with new products in accordance with requirements of Contract Documents.
H. Fit work air tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.
I. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material in accordance with Section 07 8400, to full thickness of the penetrated element.
J. Patching:
1. Finish patched surfaces to match finish that existed prior to patching. On continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit.
2. Match color, texture, and appearance.
3. Repair patched surfaces that are damaged, lifted, discolored, or showing other imperfections due to patching work. If defects are due to condition of substrate, repair substrate prior to repairing finish.
3.07 PROGRESS CLEANING
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.
B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.
C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.
D. Collect and remove waste materials, debris, and trash/rubbish from site periodically and dispose off-site; do not burn or bury.
3.08 PROTECTION OF INSTALLED WORK
A. Protect installed work from damage by construction operations.
B. Provide special protection where specified in individual specification sections.
C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.
D. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.
E. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.
F. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.
G. Remove protective coverings when no longer needed; reuse or recycle coverings if possible.
3.09 DEMONSTRATION AND INSTRUCTION
A. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time, at equipment location.
B. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.
C. Provide a qualified person who is knowledgeable about the Project to perform demonstration and instruction of Owner's personnel.
3.10 ADJUSTING
A. Adjust operating products and equipment to ensure smooth and unhindered operation.
3.11 FINAL CLEANING
A. Use cleaning materials that are nonhazardous.
B. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
C. Remove all labels that are not permanent. Do not paint or otherwise cover fire test labels or nameplates on mechanical and electrical equipment.
D. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
E. Clean filters of operating equipment.
F. Clean debris from roofs, gutters, downspouts, scuppers, overflow drains, area drains, and drainage systems.
G. Clean site; sweep paved areas, rake clean landscaped surfaces.
H. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site; dispose of in legal manner; do not burn or bury.
3.12 CLOSEOUT PROCEDURES
A. Make submittals that are required by governing or other authorities.
B. Accompany Project Coordinator on preliminary inspection to determine items to be listed for completion or correction in the Contractor's Correction Punch List for Contractor's Notice of Substantial Completion.
C. Notify Contracting Officer when work is considered ready for Contracting Officer's Substantial Completion inspection.
D. Submit written certification containing Contractor's Correction Punch List, that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Contracting Officer's Substantial Completion inspection.
E. Conduct Substantial Completion inspection and create Final Correction Punch List containing Contracting Officer's and Contractor's comprehensive list of items identified to be completed or corrected and submit to Contracting Officer.
F. Correct items of work listed in Final Correction Punch List and comply with requirements for access to Owner-occupied areas.
G. Notify Contracting Officer when work is considered finally complete and ready for Contracting Officer's Substantial Completion final inspection.
H. Complete items of work determined by Contracting Officer listed in executed Certificate of Substantial Completion.
3.13 MAINTENANCE
A. Provide service and maintenance of components indicated in specification sections.
B. Maintenance Period: As indicated in specification sections or, if not indicated, not less than one year from the Date of Substantial Completion or the length of the specified warranty, whichever is longer.
C. Examine system components at a frequency consistent with reliable operation. Clean, adjust, and lubricate as required.
D. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by the manufacturer of the original component.
E. Maintenance service shall not be assigned or transferred to any agent or subcontractor without prior written consent of the Owner.
END OF SECTION
SECTION 01 7419
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 GENERAL
1.01 WASTE MANAGEMENT REQUIREMENTS
A. Owner requires that this project generate the least amount of trash and waste possible.
B. Employ processes that ensure the generation of as little waste as possible due to error, poor planning, breakage, mishandling, contamination, or other factors.
C. Minimize trash/waste disposal in landfills; reuse, salvage, or recycle as much waste as economically feasible.
D. Required Recycling, Salvage, and Reuse: The following may not be disposed of in landfills or by incineration:
1. Aluminum and plastic beverage containers.
2. Corrugated cardboard.
3. Wood pallets.
4. Clean dimensional wood.
5. Metals, including packaging banding, metal studs, sheet metal, structural steel, piping, reinforcing bars, door frames, and other items made of steel, iron, galvanized steel, stainless steel, aluminum, copper, zinc, lead, brass, and bronze.
E. Contractor shall develop and follow a Waste Management Plan designed to implement these requirements.
F. Methods of trash/waste disposal that are not acceptable are:
1. Burning on the project site.
2. Burying on the project site.
3. Dumping or burying on other property, public or private.
4. Other illegal dumping or burying.
G. Regulatory Requirements: Contractor is responsible for knowing and complying with regulatory requirements, including but not limited to Federal, state and local requirements, pertaining to legal disposal of all construction and demolition waste materials.
1.02 DEFINITIONS
A. Clean: Untreated and unpainted; not contaminated with oils, solvents, caulk, or the like.
B. Construction and Demolition Waste: Solid wastes typically including building materials, packaging, trash, debris, and rubble resulting from construction, remodeling, repair and demolition operations.
C. Hazardous: Exhibiting the characteristics of hazardous substances, i.e., ignitibility, corrosivity, toxicity or reactivity.
D. Nonhazardous: Exhibiting none of the characteristics of hazardous substances, i.e., ignitibility, corrosivity, toxicity, or reactivity.
E. Nontoxic: Neither immediately poisonous to humans nor poisonous after a long period of exposure.
F. Recyclable: The ability of a product or material to be recovered at the end of its life cycle and remanufactured into a new product for reuse by others.
G. Recycle: To remove a waste material from the project site to another site for remanufacture into a new product for reuse by others.
H. Recycling: The process of sorting, cleansing, treating and reconstituting solid waste and other discarded materials for the purpose of using the altered form. Recycling does not include burning, incinerating, or thermally destroying waste.
I. Return: To give back reusable items or unused products to vendors for credit.
J. Reuse: To reuse a construction waste material in some manner on the project site.
Bitterroot Facilities Painting Projects Construction Waste Management and Disposal 01 7419 - 1
K. Salvage: To remove a waste material from the project site to another site for resale or reuse by others.
L. Sediment: Soil and other debris that has been eroded and transported by storm or well production run-off water.
M. Source Separation: The act of keeping different types of waste materials separate beginning from the first time they become waste.
N. Toxic: Poisonous to humans either immediately or after a long period of exposure.
O. Trash: Any product or material unable to be reused, returned, recycled, or salvaged.
P. Waste: Extra material or material that has reached the end of its useful life in its intended use. Waste includes salvageable, returnable, recyclable, and reusable material.
PART 2 - NOT USED PART 3 EXECUTION
3.01 WASTE MANAGEMENT PLAN IMPLEMENTATION
A. Manager: Designate an on-site person or persons responsible for instructing workers and overseeing and documenting results of the Waste Management Plan.
B. Instruction: Provide on-site instruction of appropriate separation, handling, and recycling, salvage, reuse, and return methods to be used by all parties at the appropriate stages of the project.
C. Meetings: Discuss trash/waste management goals and issues at project meetings.
1. Prebid meeting.
2. Preconstruction meeting.
3. Regular job-site meetings.
D. Facilities: Provide specific facilities for separation and storage of materials for recycling, salvage, reuse, return, and trash disposal, for use by all contractors and installers.
1. Provide containers as required.
2. Provide adequate space for pick-up and delivery and convenience to subcontractors.
3. Keep recycling and trash/waste bin areas neat and clean and clearly marked in order to avoid contamination of materials.
E. Hazardous Wastes: Separate, store, and dispose of hazardous wastes according to…