This document is an Independent Government Estimate (IGE) Schedule of Items for a GAOA Facility Painting project at Bitterroot National Forest. The solicitation involves exterior painting for multiple facilities, including base items for three locations (Stevensville RD Bunkhouse, Stevensville RD Office, and West Fork RD Residence #3) and seven optional items such as Darby RD Office, Visitor Center, and various shops and buildings. The anticipated delivery date is 30-Sep-26, with the period of performance from 05/01/2026 to 09/30/2026.
The procurement is anticipated to be awarded as a firm fixed-price contract, with the Contracting Officer having the option to exercise additional line items within 90 days of award. The solicitation has undergone multiple amendments, extending the end date and providing additional specifications, with the most recent amendment (Amendment 0003) adding revised attachments and a Q&A document. The project is being conducted by the Department of Agriculture Forest Service, specifically targeting facility improvements at the Bitterroot National Forest location.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
INSTRUCTIONS: HOW TO USE THIS FORM
| Independent Government Estimate (IGE) |
| No specific format is required for an IGE; however this must be an independent estimate and not a reiteration of a contractor quote. The selected format should generally be in the same level of detail and manner that the Schedule of Items pricing we request from contractors. The estimate should state any underlying assumptions or rationale used in formulating the estimate. Initially the CO will use the IGE to determine the estimated value of the procurement and to identify the appropriate procurement thresholds applicable to the solicitation. Later the IGE is compared to prices received to evaluate an offeror’s understanding of the government requirements and in supporting a price reasonableness determination. |
EXPLANATION OF TABS
| Stand Alone IGE: | Use if the below do not apply to your requirement. |
| Stand Alone IGE w/options: | Use if you have a requirement where you know you have an ongoing/recurring need year after year. |
| IDIQ: | Use if you have a need that is reoccurring or multi-year requirement. |
| Task Order: | Use if you want to issue a order against an existing contract or agreement. |
CONTRACT (NO OPTIONS)
SCHEDULE OF ITEMS
BITTERROOT NATIONAL FOREST
PROJECT TITLE: BRF PAINTING PROJECTS WORKPLAN ACQUISITION PLAN/REQUISITION NO: WPAP# 713477
| Anticipated Delivery Date (Required for Supply and Construction) | 30-Sep-26 | ||||
| SCHEDULE OF ITEMS | |||||
| ITEM | |||||
| NUMBER | DESCRIPTION | PAY UNIT | EST QTY | UNIT PRICE | TOTAL PRICE |
| BASE ITEMS | |||||
| 0001 | Exterior Painting - Stevensville RD Bunkhouse | LS | 1 | ||
| 0002 | Exterior Painting - Stevensville RD Office | LS | 1 | ||
| 0003 | Exterior Painting - West Fork RD Residence #3 | LS | 1 |
| OPTIONAL ITEMS | |||
| 1001 | Exterior Painting - Darby RD Office | LS | 1 |
| 1002 | Exterior Painting - Darby RD Visitor Center Historical ** | LS | 1 |
| 1003 | Exterior Painting - Stevensville RD Shop | LS | 1 |
| 1004 | Exterior Painting - Darby RD Shop | LS | 1 |
| 1005 | Exterior Painting - Darby RD Fire Cache | LS | 1 |
| 1006 | Exterior Painting - Darby RD Tree Cooler | LS | 1 |
| 1007 | Exterior Painting - Darby RD Barn Historical ** | LS | 1 |
| BASE ITEMS TOTAL | |
| OPTIONAL ITEMS TOTAL | |
| TOTAL | |
| LS-Lump Sum |
Award anticipated to be a firm fixed price contract.
| ** This is a historical facility. The paint shall be applied so that brush strokes remain. |
| The Government may require the delivery of the numbered line item, identified in the Schedule as an optional item, in the quantity and at the price stated in the Schedule. |
| The Contracting Officer may exercise the optional items by written notice to the Contractor within 90 days. |
File details come from the government source that posted it. Updated .