This is a Schedule of Items for a federal fixed-price construction contract for the GAOA South Zone Fence Replacement project, dated 3/16/26. The document outlines base items and option items for fence removal, construction, and installation services across multiple sites managed by what appears to be a federal land management agency.

The base items include mobilization for the entire project and twelve fence-related tasks across various named locations: Oowah Lake (8,000 linear feet of barbed wire fence removal and construction), Buckeye (8,498 linear feet of wood post and rail fence installation), Warner Wood (5,528 linear feet of wood post and rail fence construction), Warner Barbed Wire (3,516 linear feet of barbed wire conversion), Mason Draw (3,465 linear feet of barbed wire fence removal and construction), Devils Canyon Barb (9,392 linear feet of barbed wire fence removal and construction), Devils Canyon Wood (710 linear feet of wood post and rail fence removal and construction), Buckboard (5,631 linear feet of barbed wire fence removal and construction), Nizhoni Barb (200 linear feet of barbed wire fence removal and construction), Nizhoni Wood (2,735 linear feet of wood post and rail fence removal and construction), Monticello Lake (7,853 linear feet of barbed wire fence removal and construction), Porcupine Rim (3,740 linear feet of barbed wire fence removal and construction), and Great Wall of Buckeye (3,700 posts for broken and rotten post replacement on existing wood fence). The contract uses unit pricing with "CQ" (Contractor Quote) as the method of measure for all line items. Six option items are available: Pack Creek (7,705 linear feet), Gooseberry (8,213 linear feet), Indian Creek (5,808 linear feet), Orange Olsen (3,168 linear feet), Potters Pond (2,290 linear feet), and Mammoth (2,946 linear feet), all involving barbed wire fence or wood post and rail fence work. All items are priced on a linear foot or per-post basis with unit prices to be provided by bidders. The schedule notes require a bid guarantee, specify that bond premium payments must be included in the mobilization line item rather than added to the contract price, and stipulate that any option item awards will be made with the initial award.

View the file

Other files for this federal contract opportunity

Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Description Unit of Measure Method of Measure QTY Unit Price Total Price

BASE ITEMS

Warner Barbed Wire Convert 3516 ft of Barbed Wire to Lay Down Linear Foot

CQ 3516

Linear Foot CQ

Nizhoni Barb Remove and Construct 200 ft of Barbed Wire Fence. Linear Foot CQ 200

Devils Canyon Wood Remove and Construct 710 ft Wood Post and Rail Fence 710

Mammoth

3168CQLinear FootRemove and Construct Barbed Wire FenceOrange Olsen

Potters Pond Remove and Install Wooden Post and Rail Fence Linear Foot CQ 2290

Indian Creek

OPTION QUOTE PRICE

TOTAL PRICE

(Base + Options)

2946CQLinear Foot

BASE QUOTE PRICE

Remove and Install Wooden Post and Rail Fence

Remove and Install Wooden Post and Rail Fence Linear Foot CQ 5808

8213CQLinear FootRemove and Construct Barbed Wire Fence

7705CQ

OPTION ITEMS

Nizhoni Wood

Buckboard 5631

Gooseberry

Pack Creek Remove and Construct Barbed Wire Fence Linear Foot

Porcupine Rim

Great Wall of Buckeye

Remove and Construct Barbed wire fence

Replace Broken and Rotten posts for 22423 ft of existing wood fence, apprx 3700 posts

Monticello Lake

Linear Foot

Linear Foot

Linear Foot

Linear Foot

Each 3700CQ (Post)

CQ

CQ

CQ

CQ

Schedule of Items 3/16/26 GAOA South Zone Fence Replacment

Oowah Lake

Buckeye

Warner Wood

CQ 8498

Remove and Construct Barbed Wire Fence Linear Foot CQ 8000

Remove and Install Wood post and rail fence

Remove and Construct 5528 ft Wood Post and Rail Fence.

Mobilization Mobilization for entire project

Linear Foot

Linear Foot CQ 5528

LS LS LS

Schedule Notes:

1. Any award of Option Items will be done with initial award.

2. Payment for bond premiums will be required in accordance with FAR 52.228-15. In accordance with FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Base Item – Mobilization.

3. A bid guarantee is required for this solicitation. See FAR 52.228-1 Bid Guarantee (SEP 1996) on page 18 of Attachment 1. Solicitation Terms and Conditions

Devils Canyon Barb Remove and Construct 9392 ft of Barbed Wire Fence.

Remove and Construct Barb wire fence

Remove and Consturct 2735 ft Wood Post and Rail Fence

Remove and Construct Barbed Wire Fence

Mason Draw Remove and Construct Barbed Wire Fence Linear Foot CQ 3465

Linear Foot CQ

Sheet1

File details come from the government source that posted it. Updated .