This is Amendment 0005 to solicitation 1240LT26Q0016, issued by USDA Forest Service CSA Intermountain 8 on February 20, 2026, with an effective date of April 20, 2026. The amendment modifies the solicitation for the Manti-La Sal National Forest GAOA South Zone Fence Replacement project.
The amendment makes four substantive changes to the original solicitation: (1) removal of the Great Wall of Buckeye site from base items due to funding limitations, with all references to this site throughout attachments deemed not part of any resulting contract; (2) change of SOW paragraph 1.7 START DATE to May 18, 2026; (3) modification of SOW paragraph 1.8 CONTRACT TIME to 344 calendar days, with the Period of Performance remaining 05/18/2026 to 04/26/2027; and (4) extension of the response deadline to May 1, 2026 at 12:00 PM MT. The Contracting Officer is Brian J. Wharton, the Contract Specialist is Tony Taylor (tony.taylor@usda.gov), and the Contracting Officer's Representative is Jared McCourt. Offerors must acknowledge receipt of this amendment prior to the response deadline to avoid rejection of their offers.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240LT26Q0016
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40LT
OGDEN UT 84401-2310
324 25TH ST
USDA-FS CSA INTERMOUNTAIN 8
GAOA04/20/20260005
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/20/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Manti-La Sal National Forest
GAOA South Zone Fence Replacement
Amendment 0005 - This amendment makes the following changes:
- Due to funding limitations, the Great Wall of Buckeye site is removed from the base items on the SOI. Any reference to this site throughout any attachments is hereby deemed not a part of any resulting contract.
- SOW paragraph 1.7 START DATE is changed to May 18, 2026.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
BRIAN J. WHARTON
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
1240LT26Q0016/0005
- SOW paragraph 1.8 CONTRACT TIME is changed to
344 Calendar Days; the POP end date remains
4/26/2027.
- The response date is changed to May 1, 2026.
The time remains 12:00 PM MT.
No, other changes are made.
Period of Performance: 05/18/2026 to 04/26/2027
COR - Jared McCourt
Contract Specialist - Tony Taylor -tony.taylor@usda.gov
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
| 2026-04-20T11:08:43-0600 | |
| BRIAN WHARTON |
File details come from the government source that posted it. Updated .