This document appears to be a map and associated details for a federal contract opportunity related to the Saguache Park Phase III Tank Install project.

The key details are:

  • The project involves the replacement of 2 livestock watering tanks on the Continental Divide Pipeline with tire tanks, and the redevelopment of the Horse Canyon Line which includes two spring redevelopments, approximately 7,000 ft of buried pipe, two tire tank installations, and a storage tank installation.
  • The contract period of performance is from 06/01/2024 to 10/01/2024.
  • The competitive range for the contract is between $10,000 - $50,000.
  • The technical point of contact is Margaret (Meg) Shelley, Rangeland Management Specialist.
  • A pre-bid site visit meeting will be held on 04/16/2024 at 9:00am MST via Teams/Zoom.
  • The solicitation number is 1240LT24R0033 and the opportunity type is a Solicitation.
  • The agency involved is the Department of Agriculture Forest Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P

P

Sources: Esri, HERE, Garmin, Intermap, increment P Corp., GEBCO, USGS, FAO, NPS, NRCAN, GeoBase, IGN, Kadaster NL, Ordnance Survey, Esri Japan, METI, Esri China (Hong Kong), (c) OpenStreetMap contributors, and the GIS User Community

Creede

Saguache

La GaritaThe USDA Forest Service makes no warranty, expressed or implied, including the warranties of merchantability and fitness for a particular purpose, nor assumes any legal liability or responsibility for the accuracy, reliability, completeness or utility of

Saguache Park Water Development Map Phase III Legend Type

Above Ground Above ground Option 1 Option 2

ContractPoints Type P Spring " Storage

Tank HorseCanyonGDE-AboveGroundPipeline

0.7 0 0.70.35 MilesM Shelley RMS Date: 9/22/2023

Redevelop Spring -106.755639 38.071512

Redevelop Spring -106.755866 38.070446

Install Tank -106.754341 38.066417

Install Tank -106.755696 38.063342

Install StorageTank -106.755678 38.059091

Replace Tank -106.729364 38.043874

Replace Tank -106.722872 38.039187

Install Tank -106.753141 38.067618

Install Tank -106.751787 38.063779

Install StorageTank -106.751003 38.059132

Note: This map shows two pipeline routes. Option 1 oir option 2 will be selected prior to contract work begining