01 3200_Construction Progress Documentation.pdf

PDF 389 KB Posted

Attached to
Bessey Nursery Construction Correction & Completion Federal contract opportunity
Solicitation number
1240LT24R0012
Issued by
Department of Agriculture Forest Service

About this file

This document contains construction progress documentation specifications for a federal construction contract. The specifications require the contractor to submit for approval a cost loaded project schedule within 60 days of the notice to award using the critical path method. The schedule must show activities, milestones, durations, procurement details, and be updated monthly to reflect progress. Updates are due weekly before progress meetings and must indicate actual completions and any changes. The schedule will determine monthly payments and failure to meet the specifications may result in payment withholds until compliance.

View the file

Other files for this federal contract opportunity

Other files attached to Bessey Nursery Construction Correction & Completion, newest first.
File Type Posted
Generator Propane Line Redline.pdf PDF
01 4000 Quality Requirements (Supplement).pdf PDF
Bessey Pumphouse Arch Specs.pdf PDF
Irrigation System AsBuiltNotes.pdf PDF
Q and A_Second Round.docx DOCX document
BesseyPumphouseArchDrawings.pdf PDF
sign in sheet for site visit.pdf PDF
1240LT24R0012_Amendment 1.pdf PDF
Bessey_RevisedSectionC.3_03072024.docx DOCX document
Bessey_RevisedSectionL.1_452.215-71_b_TechProposalInstructions_03072024.docx DOCX document
Bessey Pre Bid Q And A.docx DOCX document
Bessey_RevisedSectionJ2_03072024.docx DOCX document
Bessey_RevisedSectionB1ScheduleOfItems_03072024.docx DOCX document
1240LT24R0012.pdf PDF
J-6. Supplemental Pumphouse & Waterline Drawings.zip ZIP file
J.1 Wage Rate Decision.pdf PDF
J-5. Amendment & Modifications.zip ZIP file
J-4.Original Specifications & Drawings.zip ZIP file
J.2 Schedule Item Work Descriptions.pdf PDF
J..7 Determination of Responsibility.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

2. Daily construction reports.

3. Field condition reports.

B. See Division 1 Section "Price and Payment Procedures" for submitting the Schedule of Values.

1.2 SUBMITTALS

1.3 COORDINATION

A. Contractor's Cost Loaded Construction Schedule: Submit one electronic copy of initial schedule.

1. Include type of schedule (Initial or Updated) and date on label.

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Cost Loaded Construction Schedule with the list of subcontracts, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 – PRODUCTS (Not Used)

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 2

PART 3 - EXECUTION

3.1 REPORTS

3.2 PROJECT SCHEDULE GENERAL REQUIREMENTS

B. Not used.

B. Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).

C. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 60 days of date established for the Notice of Award.

3.3 BASIS FOR PAYMENT AND COST LOADING SCHEDULE

B. The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN or Bid Schedule Item must equal the value of the CLIN or Bid Schedule Item.

C. Activity cost loading must be reasonable and without front-end loading. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

D. Failure to meet the requirements of this specification may result in the disapproval of the

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 3

preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met. In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.4 PROJECT SCHEDULE DETAILED REQUIREMENTS

B. Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

1. Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

2. Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

C. Contract Milestones and Constraints: Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited. Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

1. The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

2. The last activity in the schedule must be a finish milestone titled "End Project." Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.

The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3. Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

4. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 4

a. Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

b. Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.5 SCHEDULE UPDATES

B. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate Actual Completion percentage for each activity.

4. Schedule updates and agreement to schedule item percentages complete will precede applications for partial payment.

C. Distribution: Distribute copies of approved schedule to Contracting Officer, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices.

2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.