This document is a Request for Proposal (RFP) for the GAOA Historic Guinavah-Malibu Campground and Amphitheatre Reconstruction project in the Uinta-Wasatch-Cache National Forest, Cache County, Utah. The solicitation, issued by the USDA Forest Service, seeks a contractor to reconstruct the campground with multiple bid options, including base bid work such as constructing a new entrance road, right turn lane, removing existing infrastructure, and building a site sign. Optional work includes west and east side campground development, asphalt paving, pavilion construction, amphitheater restoration, and an interpretive trail.

The solicitation (RFP 1240LS25R0002) is a total small business set-aside with an estimated project value between $1,000,000 and $5,000,000. Proposals are due by August 28, 2025, at 1:00 p.m. Mountain Time, to be submitted via email. The contract requires completion within 365 calendar days of award, with an anticipated start date in Fall 2025/Spring 2026. Contractors must provide performance and payment bonds, and proposals will be evaluated using a tradeoff process that considers technical factors and price, with non-price factors being more important. The government intends to award the contract without discussions but reserves the right to conduct further negotiations if necessary.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

60OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

RFP 1240LS25R0002

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

07/26/2025

PAGE OF

PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

1141513

6. PROJECT NO.

7. ISSUED BY CODE 40LS 8. ADDRESS OFFER TO

USDA - Forest Service Procurement and Property Services (PPS) Contracting Service Area (CSA) #7 1749 West 500 South Salt Lake City, UT 84104 christine.m.hansen@usda.gov

9. FOR INFORMATION

CALL:

a. NAME Chris Hansen

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(385) 509-1895

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

GAOA Historic Guinavah-Malibu Campground and Amphitheatre Reconstruction Logan Ranger District

Uinta-Wasatch-Cache National Forest Cache County, Utah

The Government estimates the project magnitude to be between $1,000,000 and $5,000,000.

Proposals are due by Thursday, August 28, 2025 at 1:00 p.m. (Mountain Time) Local Time.

Proposal shall be emailed to:

Chris Hansen, CO christine.m.hansen@usda.gov It is the offeror’s responsibility to ensure that their proposal is received by the due date and time Faxed responses WILL NOT be accepted.

KEEP TECHNICAL AND PRICING PROPOSALS AS SEPARATE DOCUMENTS

Questions regarding this solicitation are due in writing to the CO, by Wednesday, August 13, 2025 at 1:00 PM (Mountain Time) Local Time

11. The Contractor shall begin performance within 10 calendar days and complete it within 365 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section F, Clause 52.211-

10) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT

BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12b.)

YES NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Emailed offers specified in Item 8 are due by 1:00 pm local time on Thursday, August 28, 2025.

b. An offer guarantee is, is not required (in the amount of 20 percent of the bid price) if quote exceeds $150,000.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA mailto:christine.m.hansen@usda.gov mailto:christine.m.hansen@usda.gov

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN

IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 84N8 27. PAYMENT WILL BE MADE BY

All invoices will be processed using the Department of Treasury’s Invoice Processing Platform (IPP), visit http://www.ipp.gov to learn more. Contractors must follow the instructions on how to register and submit invoices via IPP.

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award,

(b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON

AUTHORIZED TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85) FAR (48 CFR) 53.236-1(e) http://www.ipp.gov/

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 SITE INFORMATION & LIMITATIONS

C.5 TRAFFIC CONTROL AND SIGNAGE

C.6 EARTHWORK DISTURBANCE PERMITS

C.7 WORK CAMPS, STAGING, STORAGE AREAS

C.8 INSPECTION OF WORKSITE

C.9 START DATE

C.10 CONTRACT TIME

C.11 TECHNICAL SPECIFICATIONS

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 OTHER REQUIREMENTS

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS OR

RESPONDENTS

K.1 PROVISIONS

K.2 OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS

L.1 PROVISIONS

L.2 INSTRUCTIONS

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROVISIONS

M.2 PROPOSAL EVALUATION

M.3 TECHNICAL EVALUATION FACTORS

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

USDA Forest Service

SCHEDULE OF ITEMS

GAOA 4BK Historic Guinavah-Malibu CCC Campground & Amphitheatre Reconstruction Final

NUMBER

DESCRIPTION

METHOD

OF MEAS

UNIT

QUANTITY

PRICE

TOTAL

Base Bid

010250

Construction Staking

LSQ

LS

Lump Sum

011900

Mobilization

000501

Rehab Historic Toilet/ Storage Buildings

022340-1

Removal and Disposal of Existing Structures (site furnishings: fire rings, picnic tables, etc.)

024102-1

Removal and Disposal of Existing Structures and Obstructions

101110-1

Single-Panel Bulletin Board with Roof

AQ

EA

101110-2

Double-Panel Bulletin Board with Roof

101400-1

Signs - Regulatory & Directional (Aluminum)

101415-1

Major Site I.D. Sign (Sign and Stone Base)

101415-2

Minor Site I.D. Sign (Sign on Double Post)

129700 Fee Tube Relocation AQ EA 1

221100-1

Water Pipeline, 2-Inch HDPE, 160 PSI, Heat Fusion Joints, Including Trench, Pipe Zone & Bedding

DQ

LF

221100-2

Daylight Drains

221100-3

Pump Out Drains

221102-1

Curb Valve and Box - 2" Metal

221102-2

Curb Valve and Box - 4" Metal

260500-1

Electrical Site Demolition

260500-2

Electrical Site Distribution System

260500-4a

Electrical System, Storage Building (West)

311000

Clearing and Grubbing

321200-1

Hot Mix Asphalt Paving for Right Turn Lane and Entrance Road, Including Tack Coat and Saw Cuts

Ton

312010

Select Borrow - Commercial Source

CY

2,300

312100-1

Project Site Preparation and Grading (Roads and Parking Areas)

321204-3

Crushed Aggregate Base - Grading C (For Under Asphalt Pavement)

1,070

321204-2

Crushed Aggregate Surfacing - Grading G (For

Paths)

322205-1

Barrier Rocks

322622-1

Concrete Curbstops (6-foot)

322640-1

Pavement Marking - 4-inch Wide Line Striping (Reflectorized White)

322640-2

Pavement Marking - 8-inch Wide Line Striping

322640-3

Pavement Marking - Accessible Parking Symbol (Reflectorized White on Blue Background)

322706

ASPHALT PAVEMENT PULVERIZATION

SY

16,224

323116

Road Closure Gate - 32 Foot (Double 16' Gate)

329206 Seeding

LSQ LS

Total Base Bid:

NUMBER Option: West Side

OF MEAS UNIT QUANTITY PRICE TOTAL

022340-1

Removal and Disposal of Existing Structures (site furnishings: fire rings, picnic tables, etc.)

Removal and Disposal of Existing Structures and

026460

Concrete Dumpster Pads with Screen Walls

129400-1

Family Unit - Single (Includes Aggregate Surface Pad and Site Furnishings)

129400-2

Family Unit - Double (Includes Aggregate

129400-4

Unit Markers

132700-1

Precast Concrete Vault Restrooms (Double- Vault)

221105-1

Hydrant - Type A with Aggregate Pad

221105-2

Hydrant - Type C with Aggregate Pad

221310

Sewage Holding Tank- 2000 Gal. Including Sewerline and Trailer Hookup

221300-3

Cleanout

231126

Exterior Propane Gas System (Host Unit) - 120 Gallon Tank and 3/4-Inch PE Piping to Unit

260500-6

Electrical System, Restroom

3,878

Crushed Aggregate Base - Grading C (For Under

1,678

322100

Tent Pad Size 16' by 16'

322622-2

Concrete Curbstops (8-foot)

329206

Seeding

332228-3

Culvert - 24-inch Galv. Steel Corrugated Metal Pipe (16 Gage, 2 2/3"x1/2" Corrugations)

Total "Option: West Side":

NUMBER Option: East Side

000501

Rehab Historic Toilet/ Storage Buildings

Removal and Disposal of Existing Structures and

026460

Concrete Dumpster Pads with Screen Walls

101110-1

Single-Panel Bulletin Board with Roof

101415-2

Minor Site I.D. Sign (Sign on Double Post)

129400-1

Family Unit - Single (Includes Aggregate

129400-4

Unit Markers

129410

Group Sites - (40 PAOT Group Sites includes Concrete Pad, Aggregate Base and Site Furnishings)

132700-1

Precast Concrete Vault Restrooms (Double- Vault)

221105-1

Hydrant - Type A with Aggregate Pad

221105-2

Hydrant - Type C with Aggregate Pad

221310

Sewage Holding Tank- 2000 Gal. Including Sewerline and Trailer Hookup

221300-3

Cleanout

231126

Exterior Propane Gas System (Host Unit) - 120 Gallon Tank and 3/4-Inch PE Piping to Unit

260500-4b

Electrical System, Storage Building (East)

260500-6

Electrical System, Restroom

1,325

322100

Tent Pad Size 16' by 16'

323116

Road Closure Gate - 32 Foot (Double 16' Gate)

329206 Seeding

LSQ LS

Total "Option: West Side":

NUMBER Option: Asphalt Pavement

321200-1

Hot Mix Asphalt Paving for Campground Loop Road, and Parking, Including Tack Coat and Saw Cuts (Campground only)

1,497

321200-2

Hot Mix Asphalt Paving for Spurs, Including Tack Coat and Saw Cuts (Campground only)

321200-2

Hot Mix Asphalt Paving for Roads, and Parking, Including Tack Coat and Saw Cuts (Day Use and Amphitheater)

1,370

322640-1

Pavement Marking - 4-inch Wide Line Striping

4,000

322640-3

Pavement Marking - Accessible Parking Symbol (Reflectorized White on Blue Background)

AQ EA

Total "Option: Asphalt Pavement":

NUMBER Option: Pavilions

133442-1

Shelter - Group Site, Includes Concrete Footing, Half Wall (with fireplace or half wall)

133442-2

Shelter - Group Site, Includes Concrete Footing, without extra rock work (fireplace and half wall)

260500-5a

Electrical System, Pavilion (Typical)

260500-5b Electrical System, Pavilion (Amphitheater)

LSQ EA

Total "Option: Pavilions":

NUMBER Option: Amphitheater

260500-3

Electrical Amphitheater and Trail Distribution System

136100

Amphitheater Renovation

Ampitheater path)

DQ CY

Total "Option: Amphitheater":

NUMBER Option: Interpretive Trail with Bulletin

Boards

Interpretive Trail)

101110-1 Single-Panel Bulletin Board with Roof

Total "Option: Interpretive Trail with Bulletin Boards":

Total Base:

Total All Options:

Grand Total (Base and All Options):

The Government may/may not award all line items. The Government also reserves the right to make award of the base award line items and then add optional award items to the contract within 60 days of Notice to Proceed. Optional items may not be awarded in the same order as listed in the Schedule of Items.

Name of Company (Please Print):

Unique Entity ID (UEI) from SAM.gov:

Printed Name of Company Representative:

Signature of Company Representative:

Phone Number:

Email Address:

Date:

B.2 SCHEDULE NOTES

The offeror shall insert a price in each line item opposite each pay line items listed in the Schedule. A price shall not be tendered for any item not listed. All other items not listed are indirect to one of the above items.

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 011900 Mobilization. Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.

Respond to all items. Proposalss shall be rounded to the nearest dollar.

Solicitation No: 1240LS25R0002 Project Name: GAOA Guinavah-Malibu CG Reconstruction

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

A. The Guinavah-Malibu Campground was constructed in the area of a CCC Camp. The current campground was constructed in the 1960’s and is need of major renovations to bring the campground and the amenities up to current standards. The Guinavah- Malibu site includes a campground, group sites, trailhead, day-use area with picnic sites and a historical amphitheater. Special care to protect and retain existing CCC Historical features throughout the site is required. The work associated with this project includes:

B. Contract Base Bid and Option Item Descriptions

1. Base:

a. Constructing a new entrance road and central intersection, with Trailhead Parking, pull-out and kiosk

b. Construct Right Turn Lane on US HWY 89.

c. Obliterating All existing roads that are to be removed throughout campground.

d. Removal All existing site furnishings (tables, concrete slabs, fire rings, water hydrants) throughout campground.

e. Removal of 1 Slump Block toilet building.

f. Construct Major Site Sign (Sign and Stone Base) off HWY 89.

2. West Side Bid Option:

a. Constructing a new campground "loop", including new road, spurs, restrooms, family units and site furniture.

b. Realigning existing roads and intersections.

c. Installing new road signs and campsite unit numbers

d. Install CXT Toilets

3. East Side Bid Option:

a. Constructing a new road and parking areas. Surfaces will be a mix of aggregate types.

b. Install new bulletin boards.

c. Constructing a new walk-in camping, a pathway system, signs, and site furniture.

d. Install CXT Toilets

4. Asphalt Pavement Option:

a. Place 3” asphalt pavement on Roads, Parking Areas, and Spurs.

5. Pavilions Option:

a. Erect pavilions at group sites.

b. Construct Group Sites with site furnishings

6. Amphitheater Restoration Option:

a. Removal of existing amphitheater seating planks and posts.

b. Installing new wood plan benches and supports,

c. Constructing accessible pathway

d. Constructing new wood stairs

e. Installing pathway lighting

f. Construct pavilion with site furnishings

7. Interpretive Trail with Bulletin Boards Option:

a. Construct Interpretive Trail with Single-Panel Bulletin Boards with a roof.

C. Quantities associated with these options are identified in the Schedule of Items.

C.2 PROJECT LOCATION

The project is located on the Uinta-Wasatch-Cache National Forest on the Logan Ranger District, Cache County, Utah. The site is accessed via US Highway 89 and is located approximately 5 miles East of Logan, Utah. The campground is on the south side of the highway.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

In accordance with FAR 36.204, the estimated magnitude of construction for this project is between $1,000,000 and $5,000,000.

C.4 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.

2. Contractor shall provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.

3. All construction equipment shall be pressure-washed before entering National Forest System lands. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

4. Water is not available at the site for construction purposes.

5. Power may be available upon request.

6. Toilet facilities are not available at the site.

C.5 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Utah Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items. The contractor is responsible for obtaining a Right of Way (ROW) Encroachment permit through Utah Department of Transportation (UDOT) for all work to be performed within the UDOT ROW which may include the removal of some trees near US-89.

Coordination and any permits from Rocky Mountain Power shall be the responsibility of the contractor.

C.6 EARTHWORK DISTUBANCE PERMITS

The contractor shall be responsible for obtaining a Utah Pollution Discharge Elimination Systems permit for the project and is responsible for adhering to best management practices throughout construction. No work is anticipated to be performed in riparian areas or wetlands.

C.7 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the COR. The Contractor must request in writing for approval from the COR to stage work trailers on site.

B. Overnight camping may be allowed on site with prior approval.

C.8 INSPECTION OF WORKSITE

The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

C.9 START DATE

A. Fall 2025/Spring 2026

C.10 CONTRACT TIME

365 Calendar days for the base and all awarded option items

C.11 TECHNICAL SPECIFICATIONS

The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental, and no additional compensation will be made.

Section 000501 - Rehab Historic Toilet/ Storage Buildings Section 010250 - Construction Staking Section 011250 - Measurement And Payment Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 017320 - Selective Demolition Section 022340 - Obliteration Of Old Roadways And Parking Spurs Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 024102 - Removal And Disposal Of Structures And Obstructions Section 024134 - Lead Waste Practices And Disposal Section 026460 - Dumpster Pad And Screen Wall Enclosures Section 033000 - Cast-In-Place Concrete Section 033020 - Concrete From Packaged Dry Mix For Minor Structures Section 044313.16 - Adhered Stone Masonry Veneer Section 048100 - Unit Masonry Assemblies Section 048101 - Prefabricated Firebox And Chimney Assemblies Section 049020 - Stone Restoration And Cleaning Section 061000 - Rough Carpentry Section 061600 - Sheathing Section 070150.19 - Preparation For Reroofing Section 073113 - Asphalt Shingles Section 073129 - Wood Shingles Section 076200 - Sheet Metal Flashing And Trim Section 079200 - Joint Sealants Section 090190.52 - Maintenance Repainting Section 092900 - Gypsum Board Section 099123 - Interior Painting Section 099300 - Preparation And Application Of Transparent Finishes For Shingles Section 099600 - High-Performance Coatings Section 101110 - Bulletin Boards Section 101400 - Signs Section 101415 - Site Identification Sign Fabrication (Wood) Section 129400 - Family Unit And Site Furnishings Section 129410 - Site Furnishings At Group Sites Section 129700 - Fee Tube Section 132700 - Precast Concrete Vault Restrooms

Section 133442 - Pre-Manufactured Shelter Section 133450 - Precast Vault Toilet Installation Section 136100 - Amphitheater Rennovation Section 221100 - Water Distribution Systems Section 221102 - Curb Valves And Boxes Section 221105 - Water Hydrants Section 221310 - Sewage Holding Tank Section 231126 - Facility Liquefied-Petroleum Gas Piping Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 262726 - Wiring Devices Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 312010 - Select Borrow Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 322100 - Tent Pads Section 322205 - Barrier Rocks Section 322622 - Precast Concrete Curb Stops Section 322640 - Pavement Marking Section 322706 - Asphalt Pavement Pulverizing Section 323116 - Gates For Roads Section 329206 - Seeding Section 332228 - Culvert Pipe And Pipe Arches

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

FAR 52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

FAR 52.211-13 Time Extensions (SEP 2000) FAR 52.236-15 Schedules for Construction Contracts (APR 1984) FAR 52.242-14 Suspension of Work (APR 1984)

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

AGAR 452.204-70 Modification for Contract Closeout

A post award conference with the successful offeror may be required. It will be scheduled and held within 10 days after the date of the contract award. The conference will be held via conference call.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 OTHER REQUIREMENTS

Minimum Insurance Coverage Requirements Pursuant to FAR clause FAR 52.228-5, Insurance-Work on a Government Installation paragraph (a), Contractors shall present evidence and maintain, as a minimum, the amounts of insurance coverage indicated below:

(1) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes.

If occupational diseases are not compensable under those statutes, they must be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 must be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(2) General Liability. The Contractor must have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(3) Automobile Liability. The Contractor must have automobile liability insurance written on a comprehensive form of policy. The policy must provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States must provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(4) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor must have aircraft public and passenger liability insurance. Coverage must be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury must be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR): https://www.acquisition.gov/browse/index/far (Clauses are located at FAR part 52 and begin with 52)

Department of Agriculture Acquisition Regulation (AGAR):https://www.acquisition.gov/agar (Clauses are located at AGAR part 452 and begin with 452)

Deviations to clauses may be viewed at: USDA FAR Class Deviations

FAR 52.202-1 Definitions (JUN 2020) FAR 52.203-3 Gratuities (APR 1984) FAR 52.203-5 Covenant against Contingent Fees (MAY 2014) FAR 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) FAR 52.203-7 Anti-Kickback Procedures (JUN 2020) FAR 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper

Activity (MAY 2014) FAR 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) FAR 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower

Guidance to contractor employees) FAR 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) FAR 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(JUN 2020)

FAR 52.204-13 System for Award Management Maintenance (OCT 2018) FAR 52.204-14 Service Contract Reporting Requirements (OCT 2016) FAR 52.204-19 Incorporation by Reference of Representations and Certifications (DEC

2014) FAR 52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) FAR 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (NOV 2021) FAR 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) FAR 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition (Dec

2023) FAR 52.209-6 Protecting the Government's Interest when Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment, or Voluntarily Excluded (JAN 2025) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/far/part-52 https://www.acquisition.gov/agar https://www.acquisition.gov/agar/part-452-solicitation-provisions-and-contract-clauses https://www.usda.gov/about-usda/general-information/staff-offices/departmental-administration/office-contracting-and-procurement-ocp/usda-far-class-deviations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

FAR 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018)

FAR 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

FAR 52.215-2 Audit and Records -- Negotiation (JUN 2020) FAR 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) FAR 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) FAR 52.219-8 Utilization of Small Business Concerns (JAN 2025) FAR 52.219-10 Incentive Subcontracting Program (OCT 2014) FAR 52.219-16 Liquidated Damages --Subcontracting Plan (SEP 2021) FAR 52.222-3 Convict Labor (JUN 2003) FAR 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation

(MAY 2018)

FAR 52.222-6 Construction Wage Rate Requirement (AUG 2018) FAR 52.222-7 Withholding of Funds (MAY 2014) FAR 52.222-8 Payrolls and Basic Records (JUL 2021) FAR 52.222-9 Apprentices and Trainees (JUL 2005) (DEVIATION FEB 2025) FAR 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) FAR 52.222-11 Subcontracts (Labor Standards) (MAY 2014) FAR 52.222-12 Contract Termination - Debarment (MAY 2014) FAR 52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (MAY 2014) FAR 52.222-14 Disputes Concerning Labor Standards (FEB 1988) FAR 52.222-15 Certification of Eligibility (MAY 2014) FAR 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or

Separately Specified Pricing Method) (AUG 2018) FAR 52.222-35 Equal Opportunity for Veterans (JUN 2020) FAR 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) FAR 52.222-37 Employment Reports on Veterans (JUN 2020) FAR 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC

2010) FAR 52.222-50 Combating Trafficking in Persons (NOV 2021) FAR 52.222-54 Employment Eligibility Verification (JAN 2025) FAR 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026

(JAN 2022)

FAR 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) FAR 52.223-2 Reporting of Biobased Products Under Service and Construction

Contracts (MAY 2024) (DEVIATION FEB 2025) FAR 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2024) FAR 52.223-23 Sustainable Products & Services (MAY 2024) (DEVIATION FEB 2025) FAR 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) FAR 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic

Enterprises (JUN 2000) FAR 52.226-7 Drug-Free Workplace (MAY 2024) FAR 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving

(MAY 2024)

FAR 52.227-1 Authorization and Consent (JUN 2020) FAR 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN

2020) FAR 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)

FAR 52.228-2 Additional Bond Security (OCT 1997) FAR 52.228-5 Insurance – Work on a Government Installation (JAN 1997) FAR 52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION MAY 2023) FAR 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) FAR 52.228-14 Irrevocable Letter of Credit (NOV 2014) FAR 52.228-15 Performance and Payment Bonds -- Construction (JUN 2020)

(DEVIATION MAY 2023)

FAR 52.229-3 Federal, State, and Local Taxes (FEB 2013) FAR 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) FAR 52.232-17 Interest (MAY 2014) FAR 52.232-23 Assignment of Claims (MAY 2014) FAR 52.232-24 Prohibition of Assignment of Claims (MAY 2014) FAR 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) FAR 52.232-33 Payment by Electronic Funds Transfer – System for Award Management

(OCT 2018)

FAR 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) FAR 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR

2023) FAR 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) FAR 52.233-3 Protest after Award (AUG 1996) FAR 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) FAR 52.236-2 Differing Site Conditions (APR 1984) FAR 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) FAR 52.236-5 Material and Workmanship (APR 1984) FAR 52.236-6 Superintendence by the Contractor (APR 1984) FAR 52.236-7 Permits and Responsibilities (NOV 1991) FAR 52.236-8 Other Contracts (APR 1984) FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) FAR 52.236-10 Operations and Storage Areas (APR 1984) FAR 52.236-11 Use and Possession Prior to Completion (APR 1984) FAR 52.236-12 Cleaning Up (APR 1984) FAR 52.236-13 Accident Prevention (NOV 1991) FAR 52.236-17 Layout of Work (APR 1984) FAR 52.236-21 Specifications and Drawings for Construction (FEB 1997) Alternate II (APR 1984) FAR 52.236-26 Preconstruction Conference (FEB 1995) FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by

American Security Drone Act-Covered Foreign Entities (NOV 2024) FAR 52.242-13 Bankruptcy (JUL 1995) FAR 52.243-4 Changes (JUN 2007) FAR 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN

2025) (DEVIATION FEB 2025)

FAR 52.246-21 Warranty of Construction (MAR 1994) FAR 52.248-3 Value Engineering – Construction (OCT 2020) FAR 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR

2012)-Alternate I (SEP 1996) FAR 52.249-10 Default (Fixed-Price Construction) (APR 1984) FAR 52.253-1 Computer Generated Forms (JAN 1991) AGAR 452.236-70 Emergency Response, Fire Suppression, and Liability https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf

FAR 52.217-7 Option for Increased quantity – Separately Priced Line Item (MAR 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 60 days of Notice to Proceed.

(End of clause)

FAR 52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph

(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-25#FAR_25_105

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.

Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. Chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 https://www.acquisition.gov/far/part-12#FAR_12_505 factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]

(End of clause)

FAR 52.252-6 Authorized Deviations in Clauses (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Agriculture Acquisition Regulation (48 CFR

4) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

(End of clause)

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

Attachment 1-Specifications and Submittals (318 pages) Attachment 2-Drawings (83 pages) Attachment 3-Wage Determination-Highway-Cache County-UT20250105 (7 pages)

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER

STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

FAR 52.204-29 Federal Acquisition Supply Chain Security Act Orders—Representation and Disclosures (Dec 2023) FAR 52.236-28 Preparation of Proposals – Construction (OCT 1997)

FAR 52.204-8 Annual Representations and Certifications (JAN 2025) (DEVIATION

FEB 2025)

(a) (1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.

(2) The small business size standard is small.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .