This document is a Questions and Answers file for Request for Quotation (RFQ) 1240BF27Q0002 for Misty Barge Dry Dock services issued by Highmark Marine Group (a federal agency or government entity). The solicitation concerns hauling out, drydocking, and performing hull work and coatings on a 60-foot-long, 26-foot-wide barge with an approximate weight of 90 long tons, constructed in 1979. The contract is lump-sum firm-fixed-price with an anticipated award date of November 10, 2026, and a period of performance from November 10, 2026, through April 1, 2027, with relaunch as the completion objective. The Government will arrange and pay for towing to and from the contractor's facility, which must be located in Southeast Alaska. Moorage days following relaunch (up to two weeks) are included in the base price (CLIN 0001).
The five contract line items (CLINs) include: CLIN 0001 for haul-out, lay days, and weather protection; CLIN 0002 for exterior hull painting and spot repairs (estimated 200 square feet) with specified coating systems for underwater body, freeboard, and other areas; CLIN 0003 for exterior deck and appurtenances painting; CLIN 0004 for interior hull painting in a specified 13-foot by 24-foot by 6.5-foot-high center compartment (after potable water tank removal); and CLIN 0005 for bilge tank cleaning including fuel tanks (estimated 500 gallons at half-full on arrival), three 500-gallon potable water tanks (shock chlorination at 200 ppm for 24 hours required), and sewage/aeration tank pumping. Key work scope includes preparation to SSPC-SP 10 (near-white blast cleaning) for damaged areas, installation of eight 24-pound bolt-on zinc anodes on existing hull studs, replacement of two 90-foot lengths of one-inch hot-dip-galvanized stud-link anchor chain, installation of a new 750-pound Danforth-type hot-dip-galvanized anchor, fabrication and installation of a double anchor stand on the aft deck, refurbishment of four 30-ton manual winches and associated boom/mast equipment with offsite work permitted, and replacement or repair of deck hatch gaskets with government-witnessed hose and light testing. Specified coating products include Amercoat 240LT epoxy primer, Amercoat ABC 3 marine antifoulant for underwater surfaces, and Amershield aliphatic polyurethane for topcoats, with substitutions reviewed after award. No page limits apply to technical capability documentation of past similar haul-outs; qualifications or resumes for the Contract Manager and Quality Control Representative need not be provided, only identification of individuals to the Government. Partial payments are allowed as each CLIN is completed and accepted. The Government will not provide sales tax exemption documentation; offerors must incorporate any applicable state or local taxes into pricing. Government inspections will be on-site for critical hold points (block setup, haul-out, tank inspections) and should not affect schedule. A Quality Control Plan must be provided by the contractor after award. Marine Chemist certification for hot work and confined space entry is the contractor's responsibility and must be included in CLIN prices; the fuel tanks contain only #2 diesel and will not be emptied before tow. FAR 52.217-8 option language is included for schedule extension only (not pricing increases) if performance cannot be completed within the base performance period.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 1
1240BF27Q0002, Misty Barge Dry Dock
A. Solicitation, Submission, and Schedule
1. Schedule of Items workbook. The price workbook (C04-1240BX27Q0002-Scedule-of-Items- Offer.xlsx) contains a second, hidden tab, "Sheet1," with unrelated pricing (custodial cleaning CLINs and Contract Manpower Reporting). The file name also reads 1240BX27Q0002 rather than 1240BF27Q0002. Please confirm:
a. Only the BID SUMMARY SHEET tab is to be completed, and the hidden "Sheet1" tab is not to be completed and may be disregarded or deleted.
a. Government Response: The hidden sheet is not to be used and maybe discarded.
b. The blank line below CLIN 0005 may be used for unit prices or other pricing information, or should be left blank.
a. Government Response: The space below CLIN 0005 is to be left blank.
Reference: Schedule of Items workbook
2. Notice of award and the 30-day barge acceptance notice. SF 1449 shows a period of performance of November 10, 2026 to April 1, 2027, and PWS 1.4 shows date of award to April 1, 2027. PWS 3.2.3 requires a minimum 30-day notice of when the barge will be accepted at drydock.
With quotations due October 30, the earliest the barge could be accepted after award is likely mid- December 2026 or later. Please confirm:
a. The anticipated award date, period of performance start date, and contract end date.
a. Government Response: The government anticipates an award no later than 10
November 2026 with a period of performance to start on 10 November 2026/date of award. This start date allows the contractor to begin any performance needed prior to receiving the barge, to include preparing sites, ordering supplies etc.
b. Whether the 30-day notice may be given in the quotation (as a proposed acceptance window) or must be given after award, and from what date the 30 days is counted.
a. Government Response: This 30 day notice is to engage with contracting group to award the towing contract and notify the contractor once award is made. Yes, mid- December is a good estimate.
c. The Government's anticipated towing window and towing contractor, if known.
a. Government Response: Towing window is currently through Nov 30, 2026 with
Cascade Towing. Timelines can be revised based on dry dock availability, but winter weather could cause delays.
d. Whether the April 1, 2027 completion date applies to relaunch, or to tow-away from the contractor's facility.
a. Government Response: The government objective is to be relaunched by 01 April 2027.
e. Whether the period of performance and lay days will be adjusted if the barge's arrival is delayed by weather or towing availability outside the contractor's control.
a. Government Response: Yes, if weather or other unforeseen circumstances happen, extension to performance dates will be considered.
Reference: SF 1449; PWS 1.4, 3.2.3
3. SF 1449 Delivery date. SF 1449 lists "Delivery: 09/01/2026," which is before the solicitation issue date. Please confirm this date does not apply.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 2
Reference: SF 1449, page 1
a. Government Response: Government system issue printing the form. Disregard 09/01/2026.
4. Towing scope. PWS 1.1 describes the contract as covering "towing, drydock, and hull work," while PWS 1.3 and 3.2.3 state the Government will tow the barge. Please confirm that towing to and from the contractor's facility is excluded from the contractor's price, and that the Government's towing contractor is responsible for the return tow.
Reference: PWS 1.1, 1.3, 3.2.3
a. Government Response: Towing to and from the contractor’s facility is excluded from the contractor’s price. However, dry dock facility is limited to being located within Southeast Alaska.
5. Moorage after relaunch. If the return tow does not occur immediately after relaunch, how long should offerors expect to moor the barge, and should moorage days be included in the CLIN 0001 price or handled separately?
Reference: PWS 3.1.8, 3.2
a. Government Response: Moorage days shall be included in the CLIN 1001, added with amendment 00002. Pre-coordination with government/towing contractor shall occur to minimize the number of moorage days up to 2 weeks.
6. Option to extend services. Evaluation and Basis for Award, Factor 3 – Price, paragraph (c) states the Government will evaluate the FAR 52.217-8 option by adding one half of the base price to the total price, and that offerors shall not include pricing for the option period. Please confirm how this evaluation applies to a lump-sum drydock requirement, and how additional lay days and dockage would be priced if the option is exercised.
Reference: FAR 52.217-8; Evaluation and Basis for Award, Factor 3(c)
a. Government Response: Clause 52.217-8 is needed in case all performance cannot be met during the awards period of performance. Under this type of service contract, it will not be used to increase pricing but only extend performance if needed.
7. Technical Capability content. Please confirm any page limits, what documentation is acceptable to "demonstrate past haul outs of similar size" (for example, photos, lift records, or customer references), and how many past haul outs of similar size must be demonstrated. Please also confirm whether qualifications or resumes for the Contract Manager and Quality Control Representative (PWS 1.10) are required in the quotation.
Reference: 52.212-1(j); PWS 1.10, 3.2.1Moorage Fee
a. Government Response: No page limits to documentation of past haul outs of similar size. Government does not require resumes or qualification listings only that the individual(s) be identified to the government.
B. Vessel Data and Records
8. Hull dimensions. PWS 3.1.1 lists the hull as 61' x 26' x 6'-6". The Docking Plan (Appendix 2, ASD0301-80101) lists length overall 60'-0", breadth 26'-0", depth molded 6'-6" at centerline and 6'- 0" at side. Please confirm:
a. Which dimensions govern.
b. Whether the 28'-2" overall height is measured from the bottom of the hull or from the deck.
c. The width of the barracks and the roof eave overhang beyond the hull at the sides and ends.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 3
Reference: PWS 3.1.1; Appendix 2 Docking Plan
a. Government Response: Hull length is 60’. The 28’-2” overall height is measured from the bottom of the hull. The roof eave does not overhang beyond the hull of the barge on any of the sides or ends.
9. Barge weight and weight condition. Please confirm:
a. The basis of the approximately 90 long ton weight (survey, displacement calculation, or recorded lift weight).
b. Expected levels in the fuel, potable water, and sewage tanks on arrival, and whether furnishings and stores will remain aboard.
c. Any known weight distribution or longitudinal center of gravity, and the locations of heavy items such as the generators, battery bank, tanks, and aerobic treatment unit.
Reference: PWS 3.1.1
a. Government Response: The 90 Long ton was recorded lift weight. The fuel tanks are anticipated to be about half full, potable water will likely be full, and sewage tanks are unknown. Weight distribution is unknown. The generators and battery banks are located on the aft compartment per appendix 2, page 2 of the solicitation.
10. Previous drydock records. Paragraph 2.02 of Appendix 1 requires new coatings to be compatible with the existing coatings. Please provide any available records from the barge's most recent drydock, including:
a. Coating products applied, number of coats, dry film thicknesses, and areas coated, for both the exterior (PPG) and interior (Devoe) systems.
b. The facility used, the lift method, sling or strap locations, and the blocking arrangement.
c. Any ultrasonic thickness gauging results and condition reports.
Reference: Appendix 1, 2.02; Appendix 3, Photo 02
a. Government Response: The most recent drydock was completed in 2022 by Superior Marine using a travel lift. Coating applied to the exterior is as described in Appendix 1, Table 1.
11. Pre-towing inspection. PWS 3.1.4 requires the post-work survey to verify that systems and equipment are in the same or better condition than documented during the pre-towing inspection.
Please confirm who performs the pre-towing inspection, and whether a copy of the report and photos will be provided to the contractor before haul-out.
Reference: PWS 3.1.4
a. Government Response: Since the contractor is not performing the towing, there should be a post-towing inspection report with pictures prior to haul out, performed by the dry dock contractor with government representative. Submit this report to COR prior to haul out.
12. Barge condition and utilities during the work. Please confirm:
a. Whether the barracks will be unoccupied and cleared of personal property during the contract.
b. How the contractor will be given access (keys, codes) to the barracks and bilge.
c. Whether the barge must be kept heated during the lay period.
d. The shore power connection requirements (voltage, amperage, and plug type), and whether the contractor may operate the barge generators.
Reference: PWS 3.1, 3.1.6, 3.1.7
a. Government Response: The barracks will be unoccupied. The personal property in the house such as furniture, linens, cookware, etc will all stay in the barge. The barge will be
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 4 unlocked for contractor use and key provided for bilge. The barge will be winterized with antifreeze and water drained from the house, and therefore heat will not be required during lay period. However, the bilge will still contain water and wastewater in the tanks which could freeze. Contractor shall drain these tanks prior to a hard freeze to prevent damage.
13. Hazardous materials testing. PWS paragraph 3.1.1 states there is no known asbestos or lead in the hull and places testing of removed materials on the contractor. Given the barge's 1979 construction date, older antifoulant layers may contain tributyltin (TBT) or other regulated materials.
Please provide any existing test results for lead, TBT, or other hazardous materials in the existing coatings, and confirm whether abatement and disposal of any regulated material found during the work will be handled as over-and-above work under PWS paragraph 1.16.
Reference: PWS 1.16, 3.1.1
a. Government Response: There haven’t been any positive test results for lead, TBT or other hazardous materials in the existing coatings. The exterior coatings have all been sandblasted down to bare metal within the last 5 years. Any abatement of confirmed hazardous materials will be considered over and above work. Contractor shall notify COR immediately.
C. CLIN 0001 – Haul Out, Lay Days, and Weather Protection
14. Hoist holes. Appendix 3, Photo 03 (page 2, top left) shows the back side of the hoist holes, captioned "Back side of hoist holds missed in previous drydock work to be prepared and painted."
The Navigation Lighting Arrangement (Appendix 2, Sheet ASD0301-42201) shows three openings in the starboard hull side (port side not shown). Please confirm:
a. How many hoist holes are to be prepared and painted, and where they are located.
b. Whether the hoist holes are designed lifting points, whether they have a rated capacity, and whether they were used during the most recent haul-out.
Reference: Appendix 3, Photo 03; Appendix 2
a. Government Response: There are 3 on each side of the barge visible on second picture of Appendix 3. Unknown whether they are lifting points or have a rated capacity. Unknown whether used in more recent haul-out.
15. Blocking. Please confirm whether the 2004 Docking Plan (Appendix 2, ASD0301-80101) is the current blocking reference, whether there have been any structural modifications to the hull since 2004, and whether the Government has any restrictions on block locations beyond those in PWS 3.2.4.
Reference: PWS 3.2.2, 3.2.4; Appendix 2
a. Government Response: There haven’t been any other structural modifications to the hull since 2004.
16. Weather protection extent. PWS 3.1.6 requires the barge to be protected from rain, snow, and wind for the duration of drydocking, with all exterior blasting and painting sheltered. Please confirm:
a. Whether a full enclosure of the entire barge, including the barracks, is required for the full lay period, or whether enclosures over only active blast and paint areas meet the requirement.
b. Whether heat and dehumidification are required throughout, or only as needed to meet the coating manufacturer's application and cure conditions.
Reference: PWS 3.1.6
a. Government Response: Only weather protection for the active blast and painting areas to meet coating manufacturer’s requirements is needed.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 5
D. Coatings – General (applies to CLINs 0002–0004)
17. Surface preparation standard. The rows "Hull Waterline to Keel (Underwater Body)," "Gunwale Waterline to Deck (Freeboard)," and "Interior Bilge Hull" call for damaged areas to be blasted "to near white (SSPC-SP6)." SSPC-SP 6 is Commercial Blast Cleaning; SSPC-SP 10 is Near-White Blast Cleaning. Which standard is intended?
Reference: Appendix 1, Table 1
a. Government Response: This should be SSPC-SP 10, blast to near white.
18. Sweep blast standard. The Underwater Body and Freeboard rows call for "pressure wash and sand sweep entire surface" with no standard given. Please confirm sand sweeping is to be performed to SSPC-SP 7 (Brush-Off Blast Cleaning).
Reference: Appendix 1, Table 1
a. Government Response: Yes, SSPC-SP 7 standard would be appropriate.
19. Antifoulant removal on surfaces above the waterline. The Freeboard, Outside Deck, and Outside Deck Appurtenances rows call for pressure washing "to remove all loose AF paint."
Antifoulant should not be present on these surfaces. Please confirm the intent is to remove all loose or failing paint of any type from these surfaces.
Reference: Appendix 1, Table 1
a. Government Response: Yes, the intent is to remove all loose or failing paint from these surfaces.
20. Primer for spot repairs. The Underwater Body and Freeboard rows call for 1 coat of Dimetcote at 4 mils DFT on blasted repair areas. Dimetcote is an inorganic zinc silicate primer and is not suitable for spot repairs, as it does not feather or bond reliably to existing organic coatings. Please confirm that an organic zinc-rich epoxy primer, applied at the manufacturer's recommended DFT, is acceptable in place of Dimetcote for spot repairs in these areas as an approved equal under paragraph 2.01.
Reference: Appendix 1, 2.01, Table 1
a. Government Response: Yes, substitutions will be reviewed after award.
21. New steel. Appendix 1, Table 1 covers maintenance of existing coated surfaces only. Please confirm:
a. The surface preparation and coating system for new steel installed under this contract (double anchor stand, anode pads or studs, and any steel repairs).
b. Whether the new 750-pound anchor and the existing anchors and chain are to be coated after cleaning or left uncoated.
Reference: PWS 3.3.2, 3.4.8; Appendix 1, Table 1
a. Government Response: Please refer to Appendix 1, Table 1 for the coating required for damaged areas depending on location for new steel. Contractor may submit alternative proposal for consideration after award. The new anchor shall be Hot-Dip Galvanized.
The existing anchors and chain to remain are to be left uncoated after cleaning. Also include two HDG 90 foot lengths of 1 inch stud link chain and connecting hardware to replace two of the degraded existing lengths of chain.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 6
E. CLIN 0002 – Exterior Hull Painting and Repairs
22. Underwater body coating sequence. The Underwater Body row lists, for repair areas, 1 coat of Dimetcote at 4 mils, 2 coats of Amercoat 240LT at 8 mils each, 1 coat of "Black 214" antifoulant, and 2 coats of Amercoat ABC 3 at 5 mils each, and separately lists "2 coats of antifoulant" over the remaining surface. Please confirm:
a. The full coat sequence for spot repair areas.
b. Whether the entire underwater body receives 2 full coats of antifoulant after sweep blasting, and whether those 2 coats are the Amercoat ABC 3 coats or an additional product.
c. The full product name for "Black 214."
d. Paragraph 3.04 calls for two stripe coats of antifoulant on all welds and edges. Please confirm whether stripe coats are to be the anticorrosive (Amercoat 240LT) applied before the antifoulant, and whether they apply only to the underwater body.
Reference: Appendix 1, 3.04, Table 1
a. Government Response:
Spot Repair sequence for Underbody coating per Appendix 1, Table 1:
This is the treatment for everywhere else on the Underwater Body that does not need spot repair:
Yes, the entire underwater body receives 2 full coats of Amercoat ABC 3 marine antifoulant.
Black 214 = Amercoat 214 black Yes, the two stripe coats shall be the Amercoat 240LT applied before the antifoulant.
Yes, this applies only to the underwater body.
23. Spot repair quantity. The Underwater Body and Freeboard rows call for spot repairs of damaged and rusted areas but give no estimated quantity. As a firm-fixed-price lump sum, this leaves no common basis for pricing. Please provide an estimated square footage of spot repair for the underwater body and for the freeboard to be included in the lump-sum price, and confirm that offerors may provide a unit price per square foot to adjust for actual quantities found after the hull is pressure washed and inspected.
Reference: Appendix 1, 3.03, Table 1
a. Government Response: Estimated quantity of 200 sf. Yes, offerors may provide a unit price per square foot to adjust for actual quantities found after cleaning and inspection.
24. Limit of "minor" repairs. PWS 3.3.1 calls for minor spot repairs to rub spots and other minor trauma. Please confirm that steel repairs (for example, set-in plating, cracked welds, or plate renewal) found during inspection will be handled as over-and-above work under PWS 1.16, and
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 7 state the expected turnaround time for Government authorization. Blasted steel awaiting authorization cannot be primed and will flash-rust; please confirm that any re-blasting required due to authorization delays will also be handled as over-and-above work.
Reference: PWS 1.16, 3.3.1
a. Government Response: Yes, those steel repairs are considered greater than minor repairs and would qualify as over and above work. Expected turnaround time can vary – please keep in close contact with COR for any expedited needs. Yes, any government delays would be handled as over and above work.
25. Antifoulant above the waterline. The second Freeboard line calls for "2 coats of antifoulant; Color:
BLACK." Antifoulant is not appropriate above the waterline. Please confirm the intended freeboard finish is Amershield aliphatic polyurethane, black, at 5 mils DFT, as shown in the first Freeboard line.
Reference: Appendix 1, Table 1
a. Government Response: Yes.
26. Topcoat extent. Please confirm whether the entire freeboard is to receive a full coat of Amershield after spot repairs, or whether the topcoat is applied to spot-repaired areas only. Spot-topcoating black polyurethane typically results in a visibly mismatched finish.
Reference: Appendix 1, Table 1
a. Government Response: Full coat of Amershield to entire freeboard is intended.
27. Barge name. Please provide the letter height, font, color, and method (paint or vinyl) for the barge name, and confirm whether any other markings (official number, hailing port, draft marks) are to be repainted.
Reference: PWS 3.3.1.1
a. Government Response: Barge name height/color should be similar to existing. Barge name shall be vinyl. No other markings are anticipated.
28. Zinc anodes. The Docking Plan shows six hanging zinc anodes (ZHS-23) and notes they are to be pulled out of the water before docking. The Docking Plan's List of Materials shows only six studs (Part 1) for the hanging anode connections, so installing eight bolt-on anodes will require new pads or studs at a minimum. PWS 3.3.2 calls for removing the existing anodes and installing eight 24-pound bolt-on anodes, four per side, and the Performance Requirement Measures say "remove hanging zincs and install 8 bolt-on zincs." Please confirm:
a. Whether the hull has existing studs or pads for bolt-on anodes. If not, whether fabricating and welding new anode pads or studs is in scope, and the required locations and height relative to the waterline.
b. The required anode alloy and specification (for example, zinc to MIL-DTL-18001) and part number, if any.
c. Whether the Government or towing contractor will pull the hanging anodes before the tow, and what should be done with the removed anodes and hardware.
Reference: PWS 3.3.2, Section 5; Appendix 2 Docking Plan
a. Government Response: The barge does not have hanging anodes anymore. PWS 3.3.2 is accurate. Performance measures, task 2 should remove the word “hanging”. The hull has existing studs for bolt on zinc anodes similar to existing. The Docking Plan notes are not accurate. The Docking plan was for reference for the plan and layout of the barge.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 8
F. CLIN 0003 – Exterior Deck and Appurtenances
29. Deck and appurtenance quantities. Please provide the approximate total deck area to receive the full coat system, the deck area under or immediately adjacent to the barracks that is excluded, and a list of the appurtenances to be coated (railings, bitts, cleats, hatch coamings, and similar), including the length and material of the deck railing.
Reference: PWS 3.4.1, 3.4.2; Appendix 1, Table 1
a. Government Response: The building is 40’x20’. Please refer to the attached asbuilt drawings and house drawings for quantity takeoffs. Appurtenances are defined by 3.4.2.
Include all previously painted deck appurtenances including vents, cleats, winches, hatches, handrails, pad eyes for aft ramp, mooring bit, deck posts, propane bracket, deck penetrations, etc.
30. Preparation standard for damaged areas. The Outside Deck row allows needle gun, bristle blaster, or spot sandblasting for damaged areas but gives no cleanliness standard. Please confirm damaged areas are to be prepared to SSPC-SP 11 (Power Tool Cleaning to Bare Metal), or to SSPC-SP 10 (Near-White Metal Blast Cleaning), or to another standard.
Reference: Appendix 1, Table 1
a. Government Response: Cleaning to SSPC-SP 11 Power Tool Cleaning to Bare Metal is acceptable.
31. Coat sequence for damaged areas. Please confirm whether damaged areas prepared to bare metal receive a spot prime coat (product and DFT) before the full coat of Amercoat 240LT, or whether the single full coat of Amercoat 240LT at 8 mils DFT is applied directly over bare metal.
Reference: Appendix 1, Table 1
a. Government Response: Damaged areas are to receive a spot prime coat of Dimetcote at 4 mils DFT before 2 coats of Amercoat 240LT at 8 Mil DFT each as stated in Appendix 1, Table 1.
32. Nonskid application. The Outside Deck row calls for "1 full coat of Amercoat 240 LT at 8 Mil DFT" with the finish "Broadcast copper slag into Amercoat 240 LT and seal with top coat of Dark Gray Amershield Aliphatic polyurethane; 5 mil DFT. Color: Match Existing." Please confirm the following:
a. Is the copper slag broadcast into the single full coat of Amercoat 240LT, or into a separate second coat of 240LT applied over the first?
b. Is nonskid required over the entire deck, or only walkways and work areas? If only certain areas, please identify them.
c. What copper slag grit size and broadcast rate are required?
d. The finish color is listed as both "Dark Gray" and "Match Existing." Please confirm which governs.
Reference: Appendix 1, Table 1
a. Government Response: Copper slag broadcast into the single full coat of Amercoat.
Nonskid is required only on walking surfaces on deck. Match existing.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 9
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 10
33. Bitts and bollards. Appendix 3, Photos 06 and 07 (page 2, middle right and bottom left) show rub damage at the deck bitts; Photo 07 is captioned "Rub area to be addressed in drydock." Please confirm the bitts are coated with the Outside Deck Appurtenances system (haze gray Amercoat 240LT and dark gray Amershield) and priced under CLIN 0003.
Reference: Appendix 3, Photos 06–07; Appendix 1, Table 1
a. Government Response: Correct.
34. Hatches. PWS 3.4.3 calls for replacing, adjusting, or reinstalling gaskets as needed for a tight seal.
Please confirm:
a. The number and location of deck hatches.
b. The make, model, or style of each hatch (for example, flush or raised, bolted or dogged) and the clear opening dimensions.
c. The gasket material and profile, and whether replacement gaskets are to be furnished by the contractor.
d. The test the Government will use to accept a "tight seal" (for example, chalk test, hose test, or light test), and whether the Government will witness the test.
Reference: PWS 3.4.2, 3.4.3
a. Government Response: There are two deck hatches. One on the forward and one on the aft. Please refer to pictures and asbuilts. All materials to be furnished by the contractor. A tight seal shall be witnessed by government using a hose and light test.
35. 30-ton winches. PWS 3.4.4 identifies four 30-ton Wintech manual winches but gives no model.
Please confirm:
a. The model and serial number of each winch, and whether parts manuals or drawings are available.
b. Whether OEM replacement parts are required, or whether equivalent bearings and seals are acceptable.
c. The wire rope construction (for example, 6x19 IWRC galvanized) and the maximum length of deteriorated cable that may be cut out. If a cable is found unserviceable, confirm whether new cable will be handled as over-and-above work.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 11
d. Whether a proof-load test or certificate is required for the new swaged eyes.
e. Whether winch refurbishment may be performed off the barge at the contractor's shop or by a subcontractor.
Reference: PWS 3.4.4
a. Government Response: Model and serial are unknown. Please refer to asbuilts.
Equivalent bearings and seals are acceptable. Yes, new cable would be handled as over and above work. No proof load test is required. Winch refurbishment should be performed off the barge per PWS 3.4.1.
36. Boom winches. PWS 3.4.6 identifies both the 5-ton and the 2-ton boom winches as "Wintech, model HM8." Please confirm whether the 2-ton winch is a different brand or model from the 5-ton winch, and provide the model for each.
Reference: PWS 3.4.6
a. Government Response: As far as the government knows, they are the same.
37. Boom and mast/crane. Please provide the make, model, and rated capacity of the boom and mast system. Please also confirm whether a load test or certification is required after reassembly, and that "disassemble all parts" covers sheaves, pins, and running gear, not removal of the mast structure. Please confirm that repairs found during inspection will be handled as over-and-above work.
Reference: PWS 3.4.5
a. Government Response: Unknown. Load test and cert are not required. Removal of the mast structure is not required. Any repairs required during inspection will be handled as over and above work.
38. Capstan. Please provide the make, model, and power source (electric, hydraulic, or manual) of the capstan.
Reference: PWS 3.4.7
a. Government Response: Disregard requirement for capstans. No capstans on barge.
Replace with testing Automatic Bilge Dewatering System (pages 78-80) of Misty Combined Stamped asbuilts from 2005 when last major work was done. Report findings to COR.
39. Anchors. PWS 3.4.8.5 calls for a 750-pound anchor "similar in style to the 1000 lb anchors," in ZG20-400 cast steel with mill certificate. Please confirm:
a. The type and make of the existing 1000-pound anchors (for example, stockless, Danforth or fluke, or Navy), and whether the new 750-pound anchor must be the same type.
b. Whether an equivalent cast steel grade (for example, ASTM A27 or ASTM A216 WCB) with mill certificate is acceptable in place of ZG20-400, and whether classification-society certification is required.
c. Whether the existing 250-pound anchor's chain and connecting hardware are to be reused with the new 750-pound anchor. If the chain or shackles are undersized, confirm whether replacement will be handled as over-and-above work.
d. What should be done with the 250-pound anchor: returned to the Government or disposed of by the contractor.
Reference: PWS 3.4.8
a. Government Response: The existing anchor is a Danforth anchor and new anchor should be the same type. A substitution can be proposed after award. The connecting
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 12 hardware and chain should be replaced as described in question 21. Disposed anchor shall be disposed of by the contractor.
40. Double anchor stand. PWS 3.4.8.6 calls for a double anchor stand on the aft deck, similar to Appendix 3 Photos 25 and 26. Please confirm:
a. Which anchors are stored on the new stand, and which return to their original locations.
b. Whether the stand is to be welded to the deck. If so, confirm that hot work on the aft deck above the aft compartment (generators and battery bank) is acceptable with appropriate fire watch and gas-free certification.
c. Any available dimensions for the reference stand, and whether Government approval of shop drawings is required before fabrication.
Reference: PWS 3.4.8.6, 3.4.8.7, Section 5
a. Government Response: The two largest anchors (1000 lb and 750 lb) shall be stored on the stand. Yes, stand shall be welded to the deck. Yes, with appropriate fire water and gas-free cert. No dimensions are available, but provide rough sketch prior to fabrication for government approval.
G. CLIN 0004 – Interior Hull Painting
41. Amershield DFT. The Interior Bilge Hull row calls for Amershield aliphatic polyurethane at 8 mils DFT. The Amershield product data sheet (PPG, dated November 10, 2020) lists a maximum of 6 mils DFT per coat; application at 8 mils risks premature coating failure. If Amershield is retained (see Question 42), please confirm whether it should be applied at 5 mils DFT, consistent with all other Amershield callouts in Table 1.
Reference: Appendix 1, Table 1
a. Government Response: Refer to question 42, apply at manufacturer’s recommended
DFT.
42. Finish coat type. Aliphatic polyurethane is formulated primarily for UV and weather resistance. The bilge has no UV exposure but is subject to condensation and standing water. Please confirm whether a white epoxy finish coat, compatible with the specified primer system and applied at the manufacturer's recommended DFT, is acceptable in place of Amershield as an approved equal under paragraph 2.01.
Reference: Appendix 1, 2.01, Table 1
a. Government Response: Yes, that is an acceptable substitution.
43. Area quantity. PWS paragraph 3.5.1.2.1 estimates the center compartment repair area at approximately 850 SF. Please confirm whether offerors should price 850 SF as a fixed quantity, with any additional area handled as over-and-above work under PWS paragraph 1.16, or whether a unit price per square foot should be provided for adjustment to actual quantities. Please also confirm whether the 850 SF is measured surface area (including stiffeners and overhead) or plan area.
Reference: PWS 1.16, 3.5.1.2.1
a. Government Response: The highlighted area on Appendix 2, should be a 13’ W x 24’L x 6’6” H area to include stiffeners, bracing, ceiling, bulkhead and side exterior walls. Please price as a fixed quantity.
44. Area beneath potable water tanks. The red-boxed blast and paint area on Appendix 2, Hull Interior General Arrangement (Sheet 2 of 2), includes the floor beneath potable water tanks #3, #4, and #5. Please confirm whether the tanks are to be removed so the floor beneath them can be blasted and coated, or whether the area beneath the tanks is excluded from the scope.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 13
Reference: Appendix 2, Sheet 2 of 2
a. Government Response: The water tanks shall be removed to address the floor beneath them.
45. Interior area limits. Appendix 3, Photos 11 and 12 (page 3, middle row) show rust and water ponding, captioned "Rust dust and deposits from water ponding towards forward compartment" and "Towards forward compactment." Please confirm whether the areas shown in Photos 11 through 14 are within the red-boxed area on Appendix 2, Sheet 2 of 2, and that areas outside the red box, including the forward compartment, are excluded from CLIN 0004.
Reference: PWS 3.5.1.2; Appendix 2, Sheet 2 of 2; Appendix 3, Photos 11–14
a. Government Response: Yes, the areas pictured are in the red boxed area. Correct, areas outside of this, including the forward compartment are not included.
46. Fuel tank and RO system. PWS 3.5.1.2 includes the "bottom edge of fuel tank," but both fuel oil tanks (#1 and #2) are shown outside the red-boxed area. Appendix 3, Photo 19 shows the RO unit overflow drain rusting at the fuel tank, and the RO unit sits next to Fuel Oil Tank #2 on Appendix 2, Sheet 2 of 2. Please confirm that the bottom edge of Fuel Oil Tank #2 is the area included. Please also confirm whether disconnecting and reconnecting the RO unit, UV sterilizer, and chlorinator requires a manufacturer's representative or any specific restart or sanitizing procedure.
Reference: PWS 3.5.1.1, 3.5.1.2; Appendix 2; Appendix 3, Photo 19
a. Government Response: Yes, the bottom edge of fuel tank #1 and #2 is in the red boxed area and should be included along with the connect pipe and RO stand (#1 in foreground, #2 show on pg 5 (picture 1 &2) of Appendix 3. No manufacturer rep is needed nor restart procedures.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 14
47. Steel condition after blasting. Appendix 3 photos show heavy corrosion and pitting on the bilge floor plating and stiffeners in the center compartment, and Appendix 2 shows bottom and side shell plating of 1/4". Abrasive blasting to the specified standard may expose plating or stiffeners with section loss, through-pitting, or holes that cannot be properly coated. Please confirm the following:
a. Are any ultrasonic thickness gauging results available from previous drydockings?
b. If steel with section loss or holes is found, what wastage criteria will the Government use to determine whether steel renewal is required?
c. Confirm that steel repair or renewal will be handled as over-and-above work under PWS paragraph 1.16, and state the expected turnaround time for Government authorization.
Blasted steel awaiting authorization cannot be primed and will flash-rust; please confirm that any re-blasting required due to authorization delays will also be handled as over-and-above work.
d. Confirm that additional lay days and schedule time resulting from Government review and steel repair will be compensated and the period of performance adjusted accordingly.
Reference: PWS 1.16, 3.5.1.2; Appendix 2, 3
a. Government Response: No ultrasonic thickness gauging results are available.
Government will be looking for recommendations on whether steel renewal would be needed. Yes, all would be considered over and above work.
48. Bilge access. Please confirm the number and location of deck hatches or other openings that give access to the center compartment for ventilation, lighting, and removal of spent abrasive.
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 15
Reference: PWS 3.5.1
a. Government Response: Please refer to additional previous renovation drawings/asbuilts. Two deck hatches on forward and aft, and one door to center compartment from aft and one from forward.
H. CLIN 0005 – Bilge Tanks Cleaning
49. Fuel tanks. Please confirm:
a. The expected fuel quantity and fuel type aboard on arrival.
b. Whether the fuel may be stored ashore in contractor-furnished containers while the tanks are cleaned.
c. Whether "return fuel" includes filtering or polishing. If fuel is found contaminated, confirm whether its disposal and replacement will be handled as over-and-above work.
Reference: PWS 3.6.2
a. Government Response: Fuel Tanks are estimated to be half full (500 gallons total). Fuel may be stored in contractor-furnished containers while tanks are cleaned. Returned fuel does not include filtering or polishing. If fuel is found contaminated, its disposal and replacement would be handled as over and above work.
50. Potable water tanks. Please confirm the required disinfection standard or chlorine concentration and contact time for shocking the three 500-gallon tanks, and whether a bacteriological test is required before the system is returned to service. If so, confirm who is responsible for the test.
Reference: PWS 3.6.1
a. Government Response: Shock with 200 ppm of chlorine for 24 hours. A bacti test is not required to be returned to service.
51. Sewage and aeration tanks. Please provide the estimated sludge volume in the aeration tank and the primary and secondary treatment tanks, and the make and model of the treatment unit and MSD. Please also confirm whether any restart or re-seeding procedure is required after pumping.
Reference: PWS 3.6.3
a. Government Response: The barge had little seasonal use over the last 5 years since it was last emptied. Sludge expected to be minimal. Please refer to attached asbuilt drawings. No restart or re-seeding required.
I. Pricing, Payment, Over-and-Above Work, and Quality Control
52. Over-and-above work. PWS 1.16 treats items not listed in the PWS as over-and-above work.
Please confirm whether offerors should include straight-time and overtime labor rates and a material markup in the quotation for pricing over-and-above work, and the expected turnaround time for Government authorization.
Reference: PWS 1.16
a. Government Response: Any work that falls within the over and above clin shall be negotiated at time of discovery. Providing current rates are not required.
53. Government inspections. Several hold points require Government inspection (block setup, haul-out, tank inspections before refill). Please confirm whether the COR will be on site for these inspections or will inspect remotely, and whether delays waiting for Government inspection beyond the stated notice periods will extend the schedule.
Reference: PWS 3.2.4, 3.2.5, 3.6
Highmark Marine Group – RFQ 1240BF27Q0002 Questions | Page 16
a. Government Response: If located within southeast Alaska, government inspections will be on site and should not affect the schedule.
54. Payment. Please confirm whether partial payments may be invoiced as each CLIN is completed and accepted, or whether payment is made in full only after recommissioning under PWS 3.1.7.
Reference: PWS 3.1.7; FAR 52.212-4
a. Government Response: Yes Partial Payments are allowed during performance for work completed by the contractor and accepted by the government.
55. Sales tax. Please confirm that this contract is exempt from local sales tax, and whether the Government will provide exemption documentation to the contractor.
a. Government Response: The Government will not provide a SF1094 to exempt the services of this contract. Offers are encouraged to incorporate any taxes or other state or local government taxes or fees into their pricing/offer.
56. Quality Control Plan. PWS paragraphs 1.10 and 1.14 require a Quality Control Representative to implement and maintain a Quality Control Plan, but the plan is not listed in the Section 4 deliverables. Please confirm whether a Quality Control Plan is to be submitted, and if so, the required content and due date.
Reference: PWS 1.10, 1.14, Section 4
a. Government Response: The contractor shall be responsible for providing a quality control plan after award, to the government. See attached example from a different barge.
57. Marine Chemist services. The PWS does not address hot work or confined space entry. Please confirm:
a. Marine Chemist certification required under 29 CFR 1915 Subpart B for work within the PWS is the Contractor's responsibility and is to be included in the CLIN prices, and Marine Chemist services needed for over-and-above work (such as steel repair adjacent to fuel tanks) will be priced as part of that over-and-above work under PWS 1.16.
b. The Government will provide the contents history (last three contents) of the fuel oil tanks and adjacent spaces, any previous gas-free or Marine Chemist certificates, and whether the fuel tanks will be emptied before the tow.
Reference: PWS 1.6, 1.16, 3.4.8.6, 3.6.2; 29 CFR 1915.14
a. Government Response: a. correct. B. fuel tanks have only had #2 diesel. Fuel tanks will not be emptied before the tow.
| A. Solicitation, Submission, and Schedule |
| B. Vessel Data and Records |
| C. CLIN 0001 – Haul Out, Lay Days, and Weather Protection |
| D. Coatings – General (applies to CLINs 0002–0004) |
| E. CLIN 0002 – Exterior Hull Painting and Repairs |
| F. CLIN 0003 – Exterior Deck and Appurtenances |
| G. CLIN 0004 – Interior Hull Painting |
| H. CLIN 0005 – Bilge Tanks Cleaning |
| I. Pricing, Payment, Over-and-Above Work, and Quality Control |