About this file
This document is a pre-solicitation notice for the BCLH Stewardship IRSC Phase 3 project, issued by the Department of Agriculture Forest Service. The project aims to reduce the risks of hazardous fuels and restore access to areas affected by the 2020 Beachie Creek and Lionshead fires within the Willamette National Forest.
The scope of work includes cutting and removing fire-killed trees within 100 feet of roads, hazard tree mitigation, small fuels treatment, road reconstruction, and delivery of non-commercial fish logs. The work is divided into Mandatory and Optional requirements, with an estimated value between $1,000,000 and $5,000,000 for each. A site visit is scheduled for November 5, 2024, and the final solicitation is anticipated to be issued on or around March 31, 2025, with award planned for approximately June 6, 2025. The contract will be awarded using a best value source selection method, and will require construction bonding.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SiteVisitNotes_110424.pdf | ||
| DRAFT_Phase3_Appendix B_103024.docx | DOCX document | |
| DRAFT_Phase3_Appendix A_103024.docx | DOCX document | |
| DRAFT Slope Table 102924.xlsx | XLSX spreadsheet | |
| DRAFT Burn Severity Table 102924.xlsx | XLSX spreadsheet | |
| DRAFT_Phase3_Construction_FSSS_102924.pdf | ||
| DRAFT_ConstructionTypicals_102924.pdf | ||
| DRAFT_Phase3_BurnSeverityMap_102924.pdf | ||
| DRAFT Phase 3 Appendix C_102924.pdf | ||
| Excerpt_DRAFT_RFP_Phase3_102924.pdf | ||
| Attachment1_VICINITY MAPS.pdf | ||
| Attachment2_ProjectAreaAccessInstructions.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BC-3
BC-4
BC-5
LH-7ALH-7
LH-10
BC-2
LH-7B
BC-2B
BC-2A
BC-6
LH-7AA
LH-7C
BC-7
LH-7AB
BC-2BB
LH-73
3 1
5 4
4 5
6 4
126 4 3
145 23 6 5 3 2 1 6 4
3 2
34 3536
28 25
1516171813
16171314 32151617
636633
203 133
697504
270307
520 060
086712
520 643
T 0 8 S
T 0 9 S
T 1 0 S
T 0 8 S
T 1 1 S
T 1 1 S
T 0 9 S
R 06 ER 05 ER 03 E
R 04 E R 05 E R 06 E
R 04 E
W a l d o L a k e
Hwy 22
R
0 1 20.5 Miles
TJR - 10/28/2024
Contract Provision References C5.12# Use of Roads by Purchaser: Applies to All Roads Identified on the Contract Area Map and as Agreed to by Forest Service C2.355# Applies to All Subdivisions C6.74# Slash Treatment Requirements: Applies to All Mandatory Subdivisions
Hwy 22
Portland
BendEugene
Roseburg
§̈¦80
§̈¦5
§̈¦5 ¬«97
¬«97
¬«58
Willamette National Forest
BCLH Phase 3 DxP IRSC Project Area
¬«58
¬«22
¬«20
¬«126
Place Holder for C5.12# info
Bull of the Woods Wilderness
BCLH Phase 3 DxP IRSC Contract Area Map
Detroit Ranger District Willamette National Forest
§̈¦80
BC-2
BC-2A
BC-2B
BC-2BB
BC-3
BC-4
BC-5
BC-6
BC-7
LH-10
LH-7
LH-73
LH-7A
LH-7AA
LH-7AB
LH-7B
LH-7C
BCLH Phase 3 DxP IRSC Boundary
Waterbody
! ! ! ! Protect Streams B6.5
PRIVATE
Wilderness
# Subdivision, C2.355#
Subdivision # B1.1
Total Tree Felling Ac.
C2.355#
Total Required
Fuels Treamtent
(0-30')
BC-2 69.7 68
BC-3 77.3 111.6
BC-4 0 39.1
BC-5 43.6 53.2
TOTAL 190.6 271.9
Subdivision # B1.1
Total Tree Felling Ac.
C2.355#
Total Required
Fuels Treamtent
(0-30')
BC-1D 28.5 14.5
BC-2A 8.3 6.8
BC-2B 15.3 17
BC-2BB 1.6 3
BC-6 0 1.4
BC-7 0 1.1
LH-10 30.6 19
LH-7 50 37.3
LH-7A 45.4 28.7
LH-7AA 5.3 2.1
LH-7AB 10.2 7.4
LH-7B 21.6 5.6
LH-7C 10.2 5.6
TOTAL 227 149.5
Optional Subdivisions
Mandatory Subdivisions