19. A001_SiteVisit Q-A_WRFR IRSC 08272022.pdf

PDF 570 KB Posted

Attached to
WHITE RIVER FIRE RECOVERY STEWARDSHIP IRSC – Mt. Hood NF, Barlow RD, Region 6 Oregon
Solicitation number
12363N22Q4091
Issued by

About this file

This document contains questions and answers regarding a solicitation for stewardship services on the Mt. Hood National Forest in Oregon. Two awards may be made under the solicitation to facilitate ongoing fire recovery activities within the 2020 White River Fire area and Bull Complex Fire suppression repair. Work includes felling fire-killed and damaged standing fuels, removing included green biomass, piling residual fuels, maintaining and reconstructing roads, and treating slash and erosion. It is desired to complete slash disposal of the Bull Complex using an air curtain burner or other innovative technologies. Estimated green biomass volume is 9,818 CCF of all conifer species. The site visit will be held on August 17, 2022 at the Barlow Ranger District Office. The solicitation is anticipated to be issued on or around August 12, 2022 and awarded using best value with a firm fixed price commercial services contract.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WHITE RIVER FIRE RECOVERY IRSC

Amendment 001 - Solicitation 12363N22Q4091

Site Visit Questions & Answers

Question: Is this contract subject to Davis-Bacon requirements? Are all laborers covered for all work (i.e. logging vs road work)?

Answer: Service work not associated with the road reconstruction work will require Service Contract Act Wage Determination and the work being performed for reconstruction will be subject to Construction Wages, aka Davis-Bacon Wages. Both documents are added to the contract as attachments.

Question: Can operational / danger trees be felled and or removed during implementation of contract?

Answer: Operational / Danger trees may be felled when pre-approved by the Forest Service.

Operational / Danger trees felled outside of a unit boundary shall be left on site and cannot be removed.

Operational / Danger trees felled within Cut Tree Mark (CTM) units that are within 100 feet of a roadway can be removed with the top and limb material treated as slash. Trees greater than 100 feet of a roadway shall be left on site and cannot be removed.

Operational / Danger trees felled within Leave Tree Mark (LTM) units cannot be removed.

Top and limb material shall be treated as slash.

Question: Are alternate / multiple proposals allowed from one offeror?

Answer: Provision 51. (a) (3) of the solicitation states: Offerors may, at their discretion, submit alternate proposals or proposals which deviate from the requirement, provided that an offeror also submit a proposal for performance of the work as specified in this solicitation.

Any "alternate" proposal may be considered if overall performance would be improved or not compromised, and if it is in the best interest of the Government. Alternate proposals, or deviations from any requirement of this RFQ, must be clearly identified.

An offeror can submit multiple proposals with differing technical approaches and pricing that will meet the desired end results. Government will award based on the best-value determination.

Question: Will there be multiple awards as part of this solicitation?

Answer: The work associated with the WHITE RIVER FIRE work may be awarded separately from the work associated with the BULL COMPLEX work.

Offerors who wish to submit a proposal for the WHITE RIVER FIRE work must provide price proposals on Mandatory Work Items 1-24 and Timber Products Removal Price Schedule.

Offerors who wish to submit a proposal for the BULL COMPLEX work must provide price proposals on Mandatory Work Items 25-32.

Offerors who wish to submit a proposal for both must provide price proposals on Mandatory Work Items 1-24 and 25-32 including the Timber Products Removal Price Schedule.