Sol_12318721R0005_Amd_0003.pdf

PDF 300 KB Posted

Attached to
Wayne NF MATOC IDIQ ~ Roads and General Construction Federal contract opportunity
Solicitation number
12318721R0005
Issued by
Department of Agriculture Forest Service

About this file

This document contains a federal contract solicitation and related opportunity summary. The U.S. Forest Service is soliciting offers for a Multiple Award Task Order Contract for road and general construction work with an estimated shared capacity of $10 million over a base year and four option years. Associated with the solicitation are initial pricing requests for two anticipated task orders for road and trail maintenance and construction in Morgan, Lawrence, Scioto, Athens, and Fairfield Counties in Ohio. Scope of work includes road, bridge, structure, and site work such as construction, repair, decommissioning, and maintenance. The response deadline is not provided. It is anticipated that three indefinite delivery, indefinite quantity contracts will be awarded to complete future orders on an as-needed basis.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12318721R0005 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

540B

OSCODA MI 48750-1595

5761 N SKEEL

HURON SHORES RANGER STATION

USDA FOREST SERVICE

WASHINGTON DC 20250-1138

1400 INDEPENDENCE AVE SW MS-1138

AQM PROC PROPERTY

USDA FOREST SERVICE

06/21/20210003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/08/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to incorporate the FINAL Questions and Answers dated

7/8/2021. The Questions and Answer period has now closed. The government is not obligated to answer any questions submitted after this amendment.

All other terms and conditions remain the same.

Period of Performance: 08/01/2021 to 07/31/2026

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

DEBRA K. BRINN

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Q&A Wayne NF MATOC IDIQ Solicitation

12318721R0005

Q1: Is there any historical data, pricing, predecessor, or previous contract available for public review?

A1: All previous contracts were separate for Trail maintenance IDIQ or for Road maintenance IDIQ. The task orders of this contract are structured the same as previous individual contracts.

Q2: Will a formal site visit be offered for the two task orders? If not, can offerors request/arrange a site visit?

A2: No formal pre‐bid is scheduled. However, offerors can schedule a site visit with the 2 CORS. Chad Meenach 740‐753‐0549 Roads, and Bill Scripp 740‐753‐0416 Trails

Q3: Can you provide plans/drawings for each task order?

A3: There are standard details and specifications for all task orders, (attached).

Q4: What is your deadline for questions?

A4: Questions should be received no later than 8 July 2021 (REV 7/2/2021)

Q5: Can you please provide the % value of the id price or $ value required for the bid guarantee? Section 52.228‐ 1 of the solicitation does not specify the required values.

A5: There will not be a requirement for a bid guarantee. This will be removed from the requirement.

Q6: For this proposal, should Offerors submit one bid bond (for both task orders) or do you require two bid bonds (one for each task order)?

A6: There will not be a requirement for a bid guarantee. This will be removed from the requirement.

Q7: I have a question about this bid, at one point it states that this is an IDIQ contract but it appears to be a fixed price bid. I am confused by the solicitation and the breakdown of the items on the sheets.

A7: This is an Indefinite Delivery Indefinite Quantity (IDIQ) base contract with four option years. Over the next 5 years the exact times and/or exact quantities of future requirements are not known at the time of award. Once a need is identified and specific requirements are established a task order will be competed against the contract holders. The task orders issued off the base awards will be firm fixed price. Firm fixed price is implying that we are not negotiating prices in a typical task order.

There are two seed projects which are intended to be awarded as task orders along with the base awards.

Q8: Pine Grove trail Project Pay item 92112 Bottomless Arch Culvert it has a requirement for 4 but no size is given to give a responsible bid we will need detail description of length, width and height.

A8:

Q9: On the 1442 paragraph 13 B gives 30 calendar to accept bid. Do you have a start date and a number of days to complete the Task orders?

A9: Task Order 1 – Start 7 days after issuance of Notice to Proceed, 30 days to complete Task Oder 2 ‐

Q10: If we email this bid I know it is broken out 2 ways but on 1442 paragraph 13A it says original and 1 copy. I assume that would pertain to mailed hard copies not to e‐mailed bids?

A10: Email only requires one copy, even if broken into multiple emails. Hard copies mailed in will require one original and one copy.

Q11: Task order #1 states that the projects are located in Morgan, Lawrence & Scioto Counties; however, based on maps, the Burr Oak project appears to be in Athens County and the FR 132 project appears to be in Fair Field County. Can you please confirm that all work for Burr Oak occurs within Athens County and all work for FR 132 occurs within Fair Field County?

A11: Burr Oak project is in Athens County. FR 132 is partially in Scioto County and partially in Lawrence County.

Q12. Can you please provide the applicable Davis‐Bacon wage determinations for each task order?

A12 The applicable Davis Bacon is an attachment already available

Q13. For Task Order 1, can you please provide the total length and starting point(s) and ending point(s) for

SPEC No. 04, milling and repaving?

A13 13,000 sq. ft. was completed in 2020. The milling and repaving is for the next 13,000 sq. ft. of pavement on the Burr Oak Cove Rd., beginning at the end of the previous new pavement.

Q14. For Task Order 2, can you please provide the dimensions of the bottomless arch culverts (4 EA) on the

Pine Grove Trail A14

Q15. For Task Order #1, can you please provide the starting point(s) and ending point(s) advise where the placement of millings will occur in relation to the project site.

A15 13,000 sq. ft. was completed in 2020. The milling and repaving is for the next 13,000 sq. ft. of pavement on the Burr Oak Cove Rd., beginning at the end of the previous new pavement.

Q16. Can you please provide the period of performance or duration (days) for each task order?

A17 Task Order 1 – 30 days

Task Order 2 ‐

Q17. Is the contractor required to provide an office trailer for Government use? If so, what are the requirements?

A17 There are no office trailer requirements.

Q18. For Task Order #2, can offeror assume that existing onsite material will be suitable for use as backfill material?

A18

Q19. For Task Order #2, there is no pay item for traffic control. Is the Contractor required to keep Pine Grove

Trail open to the public while construction is underway?

A19

Q20. For Task Order #2 Pay Item 91303.9 (aggregate surfacing, additional 1/4 mile haul pay rate), are these areas accessible by large, heavy equipment and haul trucks?

A20

Q21. For Task Order #2 pay item 91210 is labeled as "brush cutting;" however, in the specifications section,

912.10 refers to clearing and grubbing and 912.20 refers to brush cutting. Can you please provide clarification on what specification applies for this pay item?

A21

Q22. For Task Order #2 pay item 98901, what material is being furnished by the Government and what are the location coordinates?

A22

Q23. For task order #2, can you please advise what type of trails are being constructed example (ATV, Horse, mountain bike, hiking) and what trail classes?

A23

Q24. For Task Order #2, can you please provide the specific plans for bottomless arch culverts? The specifications for 921.21 were not included in the solicitation packet and the standard trail plan for bottomless arch culverts (drawing no. STD‐921‐60‐01) does not include culvert dimensions.

A24

Q25. For Task Order #2, pay item 92112, can you please confirm offerors are to include all items under specification 921?

A25

Q26: 21. When writing the technical proposal, are you looking for a specific plan of work, resources, traffic plan etc. for each of the two task orders, or do you want our technical approach to be based on the needs of the entire contract and therefore, a more general approach?

A26: The technical approach should apply to the contract as a whole.

Q27: I am just wondering how wide the trail width is for the new trail construction? Knowing this will help us better create a cost for this multi‐year maintenance project.

A27: The task orders are for trails that are typically 60” wide

Q28: If awarded, when would construction begin?

A28: We would like to start trail task orders as soon as possible, which equates to approximately 14 days after award.

Q29: On the bear claw task order there are no line items for tread maintenance And do I have to bid the paving A29: A revised schedule of items has been added to the solicitation attachments/uploads. We are looking for companies that have the ability to provide all items in the requirements therefore we are looking for complete bids.

Q30: This question pertains to milling the Burr Oak Site. This is a full pavement removal from the description if so there will be several dump truck loads of millings. Please give us a better description of where these will be placed. After looking at site we feel like there’s not enough places for the amount that is being removed. Is there an area to stockpile on site?

A30: Millings can be used as berm and spread in remaining camp sites with a COR present. A site on Burr Oak State park (0.9 miles) east of Burr Oak Cove Road has been identified as a placement site for any excess millings.

KEY: Greyed out questions pertained to a task order that was removed, therefore will not be answered

Q##: XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

A##: