QA as of 7-2-21.pdf
PDF 131 KB Posted
- Attached to
- Wayne NF MATOC IDIQ ~ Roads and General Construction Federal contract opportunity
- Solicitation number
- 12318721R0005
- Issued by
- Department of Agriculture Forest Service
About this file
This document contains questions and answers related to a solicitation for a Multiple Award Task Order Contract for road and general construction work on the Wayne National Forest. The solicitation will result in the award of three Indefinite Delivery Indefinite Quantity contracts with a total estimated value of $10 million over a one-year base period and four one-year options. Offerors must submit pricing for two initial task orders for trail maintenance and repair work. Questions cover topics such as the availability of historical data, site visits, plans and drawings, question deadlines, bid bonds and guarantees, contract and task order periods of performance, office requirements, material sources, traffic control, equipment access, task order details, and technical approach requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_12318721R0005_Amd_0004.pdf | ||
| QA as of 7-8-21 (rev) FINAL.pdf | ||
| Sol_12318721R0005_Amd_0003.pdf | ||
| 3. Task Order #2 Trail Maintenance (REV 7-1-21).pdf | ||
| TO 2 (NEW) Ironton Hanging Rock.xlsx | XLSX spreadsheet | |
| Sol_12318721R0005_Amend_0002.pdf | ||
| TO 2 (Rev) S.O.I. Bear Claw Ironton BDA 3.xlsx | XLSX spreadsheet | |
| SOLICITATION 12318721R0005 Amend 0001 Signed to post.pdf | ||
| Attachment 4. Q&A as of June 21, 2021.pdf | ||
| 3. Task Order #2 Trail Maintenance.pdf | ||
| Task Order 2 Trail Maintenance Schedule of items - Ironton.xlsx | XLSX spreadsheet | |
| Task Order 1 Road Maintenance Schedule of items.xlsx | XLSX spreadsheet | |
| 2. Task Order #1 Road Maintenance.pdf | ||
| 1. Wage Det WD OH20210001 Dated 05282021.pdf | ||
| Task Order 2 Trail Maintenance Schedule of items - Bear Claw Ironton.xlsx | XLSX spreadsheet | |
| SOLICITATION 12318721R0005.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A Wayne NF MATOC IDIQ Solicitation
12318721R0005
Q1: Is there any historical data, pricing, predecessor, or previous contract available for public review?
A1: All previous contracts were separate for Trail maintenance IDIQ or for Road maintenance IDIQ. The task orders of this contract are structured the same as previous individual contracts.
Q2: Will a formal site visit be offered for the two task orders? If not, can offerors request/arrange a site visit?
A2: No formal pre‐bid is scheduled. However, offerors can schedule a site visit with the 2 CORS. Chad Meenach 740‐753‐0549 Roads, and Bill Scripp 740‐753‐0416 Trails
Q3: Can you provide plans/drawings for each task order?
A3: There are standard details and specifications for all task orders, (attached).
Q4: What is your deadline for questions?
A4: Questions should be received no later than 8 July 2021 (REV 7/2/2021)
Q5: Can you please provide the % value of the id price or $ value required for the bid guarantee? Section 52.228‐1 of the solicitation does not specify the required values.
A5: There will not be a requirement for a bid guarantee. This will be removed from the requirement.
Q6: For this proposal, should Offerors submit one bid bond (for both task orders) or do you require two bid bonds (one for each task order)?
A6: There will not be a requirement for a bid guarantee. This will be removed from the requirement.
Q7: I have a question about this bid, at one point it states that this is an IDIQ contract but it appears to be a fixed price bid. I am confused by the solicitation and the breakdown of the items on the sheets.
A7: This is an Indefinite Delivery Indefinite Quantity (IDIQ) base contract with four option years. Over the next 5 years the exact times and/or exact quantities of future requirements are not known at the time of award. Once a need is identified and specific requirements are established a task order will be competed against the contract holders. The task orders issued off the base awards will be firm fixed price. Firm fixed price is implying that we are not negotiating prices in a typical task order.
There are two seed projects which are intended to be awarded as task orders along with the base awards.
Q8: Pine Grove trail Project Pay item 92112 Bottomless Arch Culvert it has a requirement for 4 but no size is given to give a responsible bid we will need detail description of length, width and height.
A8:
Q9: On the 1442 paragraph 13 B gives 30 calendar to accept bid. Do you have a start date and a number of days to complete the Task orders?
A9: Task Order 1 – Start 7 days after issuance of Notice to Proceed, 30 days to complete Task Oder 2 ‐
Q10: If we email this bid I know it is broken out 2 ways but on 1442 paragraph 13A it says original and 1 copy. I assume that would pertain to mailed hard copies not to e‐mailed bids?
A10: Email only requires one copy, even if broken into multiple emails. Hard copies mailed in will require one original and one copy.
Q11: Task order #1 states that the projects are located in Morgan, Lawrence & Scioto Counties;
however, based on maps, the Burr Oak project appears to be in Athens County and the FR 132 project appears to be in Fair Field County. Can you please confirm that all work for Burr Oak occurs within Athens County and all work for FR 132 occurs within Fair Field County?
A11: Burr Oak project is in Athens County. FR 132 is partially in Scioto County and partially in Lawrence County.
Q12. Can you please provide the applicable Davis‐Bacon wage determinations for each task order?
A12 The applicable Davis Bacon is an attachment already available
Q13. For Task Order 1, can you please provide the total length and starting point(s) and ending point(s) for SPEC No. 04, milling and repaving?
A13 13,000 sq. ft. was completed in 2020. The milling and repaving is for the next 13,000 sq. ft. of pavement on the Burr Oak Cove Rd., beginning at the end of the previous new pavement.
Q14. For Task Order 2, can you please provide the dimensions of the bottomless arch culverts (4 EA) on the Pine Grove Trail A14
Q15. For Task Order #1, can you please provide the starting point(s) and ending point(s) advise where the placement of millings will occur in relation to the project site.
A15 13,000 sq. ft. was completed in 2020. The milling and repaving is for the next 13,000 sq. ft. of pavement on the Burr Oak Cove Rd., beginning at the end of the previous new pavement.
Q16. Can you please provide the period of performance or duration (days) for each task order?
A17 Task Order 1 – 30 days
Task Order 2 ‐
Q17. Is the contractor required to provide an office trailer for Government use? If so, what are the requirements?
A17 There are no office trailer requirements.
Q18. For Task Order #2, can offeror assume that existing onsite material will be suitable for use as backfill material?
A18
Q19. For Task Order #2, there is no pay item for traffic control. Is the Contractor required to keep
Pine Grove Trail open to the public while construction is underway?
A19
Q20. For Task Order #2 Pay Item 91303.9 (aggregate surfacing, additional 1/4 mile haul pay rate), are these areas accessible by large, heavy equipment and haul trucks?
A20
Q21. For Task Order #2 pay item 91210 is labeled as "brush cutting;" however, in the specifications section, 912.10 refers to clearing and grubbing and 912.20 refers to brush cutting. Can you please provide clarification on what specification applies for this pay item?
A21
Q22. For Task Order #2 pay item 98901, what material is being furnished by the Government and what are the location coordinates?
A22
Q23. For task order #2, can you please advise what type of trails are being constructed example (ATV, Horse, mountain bike, hiking) and what trail classes?
A23
Q24. For Task Order #2, can you please provide the specific plans for bottomless arch culverts? The specifications for 921.21 were not included in the solicitation packet and the standard trail plan for bottomless arch culverts (drawing no. STD‐921‐60‐01) does not include culvert dimensions.
A24
Q25. For Task Order #2, pay item 92112, can you please confirm offerors are to include all items under specification 921?
A25
Q26: 21. When writing the technical proposal, are you looking for a specific plan of work, resources, traffic plan etc. for each of the two task orders, or do you want our technical approach to be based on the needs of the entire contract and therefore, a more general approach?
A26: The technical approach should apply to the contract as a whole.
Q27: I am just wondering how wide the trail width is for the new trail construction? Knowing this will help us better create a cost for this multi‐year maintenance project.
A27: The task orders are for trails that are typically 60” wide
Q28: If awarded, when would construction begin?
A28: We would like to start trail task orders as soon as possible, which equates to approximately 14 days after award.
Q29: On the bear claw task order there are no line items for tread maintenance And do I have to bid the paving A29: A revised schedule of items has been added to the solicitation attachments/uploads. We are looking for companies that have the ability to provide all items in the requirements therefore we are looking for complete bids.
File details come from the government source that posted it. Updated .