Attachment 4 As-Built Electrical Drawings 3Sep21.pdf
PDF 6 MB Posted
- Attached to
- Greenhouse Construction, Blueberry and Cranberry Research Station, Chatsworth, New Jersey
- Solicitation number
- 12305B24R0030
About this file
This document is a Material Approval Submittal Cover Sheet for the Headhouse Electrical Upgrade project under Contract Number 12305B21C0040. The submittal is for As-Built Electrical Drawings (Revision 2) and includes review comments from the Engineer, Contracting Officer's Representative (COR), and Contracting Officer. The key details are:
The submittal was reviewed and accepted as noted by the COR and Contracting Officer. Review comments include ensuring the circuit breaker quantities and ratings match as-built conditions, verifying panel AIC ratings, including the as-built panel schedule, and providing the as-built dimensions of the concrete pad. The contractor is also required to summarize the installed metering system status. This submittal is related to the federal contract opportunity for Greenhouse Construction at the Blueberry and Cranberry Research Station in Chatsworth, New Jersey, under Solicitation Number 12305B24R0030. The contract opportunity is a Firm Fixed-Price, Total Small Business Set-Aside with a period of performance of 180 days and an estimated value between $1-5 million.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MATERIAL APPROVAL SUBMITTAL
TO: USDA/ARS CO
CC: A&E, COR
FROM: (Contractor)
G Force
PROJECT TITLE:
Headhouse Electrical Upgrade
CONTRACT NUMBER:
12305B21C0040
(To be completed by the Contractor) Government Use Only
SUBMITTAL
NUMBER: 022.2
PREVIOUS SUBMITTAL NUMBER
(only if items listed were submitted previously): 022.1 A&E
Recommendation
COR/EPM
Recommendation
Contracting Officer Approval/Disapproval
Line
No.
Specification Sect.
Para No., Draw No.
Description of Material
(Include type, model, mfg) APP DISAP
See Comments on Reverse APP DISAP
See Comments on Reverse APP DISAP
See Comments on
Reverse
01 01 01 00/1.12 As-Built Drawings Rev2
If an item is disapproved, a resubmittal is due within ________ calendar days of the Contracting Officer’s signature below.
Contractor (Ktr) A&E COR/EPM Contracting Officer TYPE or PRINT NAME & TITLE
William Whitesell/ Project Manger TYPE or PRINT NAME & TITLE TYPE or PRINT NAME & TITLE TYPE or PRINT NAME & TITLE
SIGNATURE:
William Whitesell
SIGNATURE: SIGNATURE: SIGNATURE:
DATE:
05/29/2024
DATE: DATE: DATE:
By completing this form, the above signed contractor certifies that the material complies with all specifications of the subject contract.
DATE RECEIVED FROM KTR: DATE RECEIVED FROM A&E: DATE RECEIVED FROM COR:
Material Approval Submittal Cover Sheet (11/2016)
Varun Lamba
05/29/2024
06/10/2024
X
Wayne Shekailo COR III
6/12/2024
6/11/2024
X
Wayne.Shekailo Line
Wayne.Shekailo Line
CONTRACT #:12305B21C0040 SUBMITTAL #: 022.2
COMMENTS
Instructions: Enter the initials of the individual making the comment, the Line Number of the item for which the comment is being made, and the comment.
Material Approval Submittal Cover Sheet (11/2016) (Reverse)
Line 1, WS: Please review Setty's notations below.
Mechanical | Electrical | Plumbing | Fire Protection Engineering | LEED Modeling | Commissioning | Master Controls Integration | Sustainable Design Forensic Engineering | Project Management | Building Sciences | Design-Build
SUBMITTAL PROCESSING FORM
SUBMITTAL REVIEW COMMENTS:
Corrections or comments made of the shop drawings during this review do not relieve contractor from compliance with the requirements of the drawings and specifications. This check is only for review of general compliance with the design concept of the project and general compliance with the information given in the Contract Documents. The contractor is responsible for confirming and correlating all quantities and dimensions; selecting fabrication process and techniques of construction; coordinating his work with that of all other trades and performing his work in a safe and satisfactory manner. Contractor shall provide coordinated submittals for each type of equipment, fixture, work, item, or process. Coordinated submittals shall be complete, separate from non-associated submittals, and with individual submittal numbers.
Review is categorized as: Accepted, Accepted as Noted, Partial Resubmittal, Revise and Resubmit, & Rejected. Where the submittal is marked “Rejected”, do not proceed with the work covered by the submittal. Prepare a complete new submittal for a product that complies with the Contract Documents.
3040 Williams Drive, Suite 600 535 8th Avenue, Suite 21s Fairfax, VA 22031 New York, NY 10018 P: 703-691-2115 P: 646-253-9000 F: 703-691-8084 F: 646-224-8497 www.setty.com
PROJECT NAME: USDA Headhouse #2 Rutgers PROJECT NO: SAG20056.13
SUBMITTAL NAME: R2 As-Built Drawings SUBMITTAL NO: 010100-022-2
SPECIFICATION SECTION: 010100 REVIEWER: Varun Lamba
ACTION: Accepted as Noted DATE: 06/10/2024
NOTATIONS:
1. Contractor to ensure circuit breaker quantity and ratings indicated on drawing E601 match as-built conditions as the breaker ratings are not indicated on the schedules included for circuit descriptions.
2. Contractor to ensure panel AIC ratings match installed conditions.
3. Include as-built schedule for Panel A.
4. Include shop drawing “Electrical Gear Support Frame” included in previous submittal 010100-022-1.
5. Indicate the as-built dimensions of concrete pad installed to support the electrical infrastructure in detail #6 on drawing E701.
6. Summarize installed metering system status.
Please call Setty & Associates Ltd. (703) 691-2115 if you have any questions.
COPIES TO: File By: Raghavendra/Enoch, CA Coordinator
| Submittal 022.2 - Asbuilt Drawings_052924.pdf |
| Submittal 022.1 - Asbuilt Drawings_041124 |
| stl submittal 4 |
| 2024-06-12T16:28:29-0400 | |
| WAYNE SHEKAILO |
| 2024-06-13T07:26:32-0500 | |
| MARK VOLK |
File details come from the government source that posted it. Updated .