EPASS TO Phasing for SAM Posting -- as of 22 Jul 2022.pdf
PDF 97 KB Posted
- Attached to
- EPASS Task Order Phasing Plan
- Solicitation number
- 12-13-2019
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOPR
Program Projected Customer
Kickoff
Projected Draft FOPR
Projected Final FOPR
Projected Proposal Receipt
Projected Award
GSA
OASIS
SB Pool
Socio- Economic Set-Aside
Prime Contractor
GSA IDIQ
38 HI (Business & Enterprise Systems Directorate) 26-Sep-16 3-Mar-17 7-Apr-17 15-Jun-18 6 None OASIS OASIS SB 39 HB (PEO Digital Directorate Hanscom) 22-Feb-18 27-Apr-18 29-May-18 13-Aug-18 6 None OASIS OASIS SB 40 HBQ (PEO Digital - Peterson AFB) N/A 27-Apr-18 29-May-18 27-Jul-18 6 None Odyssey OASIS SB 41 CROWS 13-Sep-17 6 None ARS OASIS SB 42 AFLCMC Cross Cutter (Staff/XP-OZ/F-35/NGB) 6-Jul-18 21-Sep-18 25-Oct-18 13-Dec-18 1 None Credence OASIS SB 43 HN (C3IN Directorate) 29-Jun-17 28-Feb-18 9-Apr-18 9-Jan-19 6 None ARS OASIS SB 44 AFLCMC Functionals (EN/LG/XZ-Wright Patt/LP/A4N) 1-Aug-18 2-Nov-18 4-Dec-18 1-Mar-19 3 None Credence OASIS SB 45 WN-ACS (Wright-Patt & Robins) & LAIRCM 4-Feb-19 26-Mar-19 26-Apr-19 29-Jul-19 6 SDVOSB PE Systems OASIS SB 46 EBH/HBZ-Armament (Hill) 8-Aug-18 2-Nov-18 3-Dec-18 7-Feb-19 6 SDVOSB HX5 OASIS SB 47 WIH (Helicopter Program Office) 27-Aug-18 15-Feb-19 3-May-19 24-Jun-19 25-Sep-19 6 None DCS Corp OASIS SB 48 WWU (F-22) 21-Aug-18 29-Mar-19 28-May-19 28-Jun-19 12-Sep-19 6 None Peerless OASIS SB 49 HBG (C2ISR Robins & U-2) 11-Sep-18 17-Jan-19 13-Mar-19 15-Apr-19 2-Jul-19 3 None Credence OASIS SB 50 WL (Mobility USAF/FMS) & WV (PAR/Exec) & WK (Tanker) 5-Nov-18 16-May-19 27-Aug-19 30-Sep-19 3-Dec-19 6 None COLSA OASIS SB 51 WWM (F-16) 1-Nov-18 17-May-19 26-Jul-19 5-Sep-19 18-Nov-19 6 None Sumaria OASIS SB 52 WIN (ISR Sensors) 9-Nov-18 14-Aug-19 7-Nov-19 10-Dec-19 28-Feb-20 3 None Apogee OASIS SB 53 WIU (Rotary & Fixed Wing) 31-Oct-18 2-Jul-19 29-Aug-19 2-Oct-19 27-Dec-19 1 None Quantitech OASIS SB 54 EB (Robins) 27-Nov-18 17-Jun-19 12-Aug-19 20-Sep-19 22-Nov-19 3 None Credence OASIS SB 55 EB (Eglin) 27-Nov-18 25-Oct-19 3-Feb-20 16-Mar-20 10-Jun-20 5B None HX5 OASIS SB 56 WII (Medium Altitude UAV) 57 AFIT 23-Jan-19 25-Jun-19 13-Sep-19 15-Oct-19 21-Jan-20 1 None Credence OASIS SB
58 WWZ (B-2)
59 WIO (ISR Crosscutter) 5-Jun-19 30-Oct-19 24-Jan-20 2-Mar-20 1-Sep-20 1 None Apogee OASIS SB 60 WA/WB (F/B Crosscutter) including B-2 8-Jul-19 9-Jan-20 5-Mar-20 13-Apr-20 17-Aug-21 6 None DCS Corp OASIS SB 61 WIG (Global Hawk) 16-Aug-19 3-Mar-20 26-May-20 29-Jun-20 29-Sep-20 6 None DCS Corp OASIS SB 62 WAQ (F-15) 5-Sep-19 4-Mar-20 5-May-20 5-Jun-20 10-Nov-20 6 None OASIS OASIS SB
63 HQ AFMC
64 WIS (SOF) 15-Aug-19 26-Nov-19 6-Feb-20 9-Mar-20 18-May-20 6 None Odyssey OASIS SB 65 AFLCMC Cross-Cutter/Functionals/CROWS Round Three 13-Aug-21 17-Aug-22 27-Oct-22 2-Dec-22 20-Apr-23 TBD TBD TBD OASIS SB 66 WII (Medium Altitude UAV) 1-Dec-20 9-Apr-21 8-Jun-21 9-Jul-21 19-Jan-22 6 None Sumaria OASIS SB 67 HQ AFMC 11-Dec-19 30-Aug-21 11-Jan-22 11-Feb-22 25-May-22 1 None CDS OASIS SB 68 HI (Business & Enterprise Systems Directorate) Follow On 21-Sep-21 16-Mar-22 25-Jul-22 25-Aug-22 4-Nov-22 6 None TBD OASIS SB 69 HB Directorate (PEO Digital) 21-Oct-21 29-Apr-22 25-Aug-22 28-Sep-22 13-Feb-23 6 None TBD OASIS SB 70 USSF SSC SZQ (formerly HBQ - Peterson) 6-Jan-22 13-May-22 25-Aug-22 27-Sep-22 16-Feb-23 4 None TBD OASIS SB 71 WN-ACS Directorate 10-Jun-22 17-Nov-22 3-Feb-23 9-Mar-23 25-Aug-23 TBD TBD TBD OASIS SB 72 Fifth-Generation Fighter (F-22 / F-35) 20-Jul-22 Dec 2022 Feb 2023 Mar 2023 Aug 2023 TBD TBD TBD OASIS SB 73 HN Directorate Aug 2022 Jan 2023 Mar 2023 Apr 2023 Sep 2023 TBD TBD TBD OASIS SB
Last Updated: 22 Jul 2022 (updates in blue font) Completed steps/competitions (awarded task orders) are in dark green.
CANCELLED
CANCELLED
CANCELLED
Prospective prime offerors must be in the indicated GSA OASIS SB pool. See https://www.gsa.gov/buying-selling/products-services/professional-services/buy-services/one-acquisition-solution-for-integrated-services-oasis for details. End of GSA OASIS SB IDIQ ordering period is 19 December 2024.
File details come from the government source that posted it. Updated .