This is a Task Order Phasing Plan spreadsheet for the Engineering, Professional, and Administrative Support Services (EPASS) program, showing planned and actual dates for Fair Opportunity Proposal Requests (FOPRs) from 2016 through 2025. The document tracks FOPRs #38-85, including projected customer kickoff dates, draft FOPR dates, final FOPR dates, proposal receipt dates, and award dates.

The plan indicates that GSA OASIS Small Business IDIQ ordering period ended December 19, 2024, and new awards will transition to OASIS+ Small Business. Several FOPRs (77-85) are still pending domain/NAICS determination through market research on eBuy.GSA.gov. Most opportunities are unrestricted within OASIS SB, with only FOPRs #45 and #46 designated as SDVOSB set-asides. Key contractors include Credence, Odyssey, DCS Corp, ARS, and others across various OASIS SB pools. The document is current as of January 28, 2025, and includes color coding to indicate completed dates (green) and recent changes (blue font).

View the file

Other files

File Type Posted
EPASS Phasing Plan 20260724.pdf PDF
EPASS Phasing Plan 20260430.pdf PDF
EPASS Phasing Plan 20260211.pdf PDF
EPASS Phasing Plan 20251205.pdf PDF
EPASS Phasing Plan 20250807.pdf PDF
EPASS Phasing Plan 20250627.pdf PDF
EPASS Phasing Plan 20250424.pdf PDF
EPASS Phasing Plan 20250328.pdf PDF
EPASS Follow On TO Phasing Plan 20240927.pdf PDF
EPASS Phasing Plan 20240624.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240404.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240307.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240305.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240205 v2.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20230926.pdf PDF
EPASS TO Phasing for SAM Posting - 20230901.pdf PDF
EPASS TO Phasing for SAM Posting - 20230721v1.2.pdf PDF
EPASS TO Phasing for SAM Posting - 20230721.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 1 May 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 24 Mar 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 2 Feb 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 27 Jan 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 8 Dec 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 2 Nov 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 4 Oct 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 2 Sep 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 22 Jul 2022.pdf PDF
EPASS TO Phasing Plan for FBO Posting -- as of 10 June 22.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 09 May 2022.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 14 Mar 2022.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 16 Feb 2022.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 8 Sep 2021.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 12 Jul 2021.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 08 April 2021.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 04 Dec 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 30 Sep 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 26 Aug 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 9 Jul 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 10 Jun 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 06 May 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 26 Mar 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 05 Mar 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 22 Jan 2020.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 12 Dec 2019.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOPR # Program

Projected

Customer

Kickoff

Projected Draft

FOPR

Projected Final

FOPR

Projected

Proposal Receipt

Projected

Award

OASIS SB Pool/

OASIS+ SB

Domain/NAICS

Socio-

Economic

Set-Aside

Prime Contractor GSA IDIQ

38 HI (Business & Enterprise Systems Directorate) 26-Sep-16 3-Mar-17 7-Apr-17 15-Jun-18 6 None OASIS OASIS SB

39 HB (PEO Digital Directorate Hanscom) 22-Feb-18 27-Apr-18 29-May-18 13-Aug-18 6 None OASIS OASIS SB

40 HBQ (PEO Digital - Peterson AFB) N/A 27-Apr-18 29-May-18 27-Jul-18 6 None Odyssey OASIS SB

41 CROWS 13-Sep-17 6 None ARS OASIS SB

42 AFLCMC Cross Cutter (Staff/XP-OZ/F-35/NGB) 6-Jul-18 21-Sep-18 25-Oct-18 13-Dec-18 1 None Credence OASIS SB

43 HN (C3IN Directorate) 29-Jun-17 28-Feb-18 9-Apr-18 9-Jan-19 6 None ARS OASIS SB

44 AFLCMC Functionals (EN/LG/XZ-WPAFB/LP/A4N) 1-Aug-18 2-Nov-18 4-Dec-18 1-Mar-19 3 None Credence OASIS SB

45 WN-ACS (Wright-Patt & Robins) & LAIRCM 4-Feb-19 26-Mar-19 26-Apr-19 29-Jul-19 6 SDVOSB PE Systems OASIS SB

46 EBH/HBZ-Armament (Hill) 8-Aug-18 2-Nov-18 3-Dec-18 7-Feb-19 6 SDVOSB HX5 OASIS SB

47 WIH (Helicopter Program Office) 27-Aug-18 15-Feb-19 3-May-19 24-Jun-19 25-Sep-19 6 None DCS Corp OASIS SB

48 WWU (F-22) 21-Aug-18 29-Mar-19 28-May-19 28-Jun-19 12-Sep-19 6 None Peerless OASIS SB

49 HBG (C2ISR Robins & U-2) 11-Sep-18 17-Jan-19 13-Mar-19 15-Apr-19 2-Jul-19 3 None Credence OASIS SB

50 WL (Mobility USAF/FMS) & WV (PAR/Exec) & WK 5-Nov-18 16-May-19 27-Aug-19 30-Sep-19 3-Dec-19 6 None COLSA OASIS SB

51 WWM (F-16) 1-Nov-18 17-May-19 26-Jul-19 5-Sep-19 18-Nov-19 6 None Sumaria OASIS SB

52 WIN (ISR Sensors) 9-Nov-18 14-Aug-19 7-Nov-19 10-Dec-19 28-Feb-20 3 None Apogee OASIS SB

53 WIU (Rotary & Fixed Wing) 31-Oct-18 2-Jul-19 29-Aug-19 2-Oct-19 27-Dec-19 1 None Quantitech OASIS SB

54 EB (Robins) 27-Nov-18 17-Jun-19 12-Aug-19 20-Sep-19 22-Nov-19 3 None Credence OASIS SB

55 EB (Eglin) 27-Nov-18 25-Oct-19 3-Feb-20 16-Mar-20 10-Jun-20 5B None HX5 OASIS SB

WII (Medium Altitude UAV) 57 AFIT 23-Jan-19 25-Jun-19 13-Sep-19 15-Oct-19 21-Jan-20 1 None Credence OASIS SB

58 WWZ (B-2)

59 WIO (ISR Crosscutter) 5-Jun-19 30-Oct-19 24-Jan-20 2-Mar-20 1-Sep-20 1 None Apogee OASIS SB

60 WA/WB (F/B Crosscutter) including B-2 8-Jul-19 9-Jan-20 5-Mar-20 13-Apr-20 17-Aug-21 6 None DCS Corp OASIS SB

61 WIG (Global Hawk) 16-Aug-19 3-Mar-20 26-May-20 29-Jun-20 29-Sep-20 6 None DCS Corp OASIS SB

62 WAQ (F-15) 5-Sep-19 4-Mar-20 5-May-20 5-Jun-20 10-Nov-20 6 None OASIS OASIS SB

63 HQ AFMC

64 WIS (SOF) 15-Aug-19 26-Nov-19 6-Feb-20 9-Mar-20 18-May-20 6 None Odyssey OASIS SB

65 AFLCMC Cross-Cutter/Functionals/CROWS 13-Aug-21 2-Sep-22 14-Apr-23 22-May-23 19-Dec-23 6 None Credence OASIS SB

66 WII (Medium Altitude UAV) 1-Dec-20 9-Apr-21 8-Jun-21 9-Jul-21 19-Jan-22 6 None Sumaria OASIS SB

67 HQ AFMC 11-Dec-19 30-Aug-21 11-Jan-22 11-Feb-22 25-May-22 1 None CDS OASIS SB

68 GB (Business & Enterprise Systems Directorate) 21-Sep-21 16-Mar-22 25-Jul-22 29-Aug-22 11-Jan-23 6 None Torch OASIS SB

69 HB Directorate (PEO Digital) 21-Oct-21 29-Apr-22 26-Oct-22 14-Dec-22 1-May-23 6 None Odyssey OASIS SB

70 USSF SSC SZQ (formerly HBQ - Peterson) 6-Jan-22 13-May-22 3-Oct-22 3-Nov-22 14-Apr-23 4 None Odyssey OASIS SB

71 WN-ACS Directorate 10-Jun-22 19-Jan-23 2-Jun-23 14-Jul-23 21-Dec-23 6 None PE Systems OASIS SB

72 Fifth-Generation Fighter (F-22 / F-35) 73 HN Directorate 23-Aug-22 27-Mar-23 17-Oct-23 1-Dec-23 3-Apr-24 6 None ARS OASIS SB

74 HBG Division 31-Jul-23 12-Jan-23 9-May-24 10-Jun-24 27-Sep-24 3 None Credence Dynamo OASIS SB

75 WI-RAFB 12-Apr-23 29-Nov-23 12-Apr-24 13-May-24 30-Aug-24 3 None CQJV, LLC. OASIS SB

76 WI-WPAFB 12-Apr-23 29-Nov-23 19-Apr-24 31-May-24 15-Oct-24 6 None Odyssey OASIS SB

77 WL/WV Directorates 14-Aug-23 4-Feb-25 15-Jul-25 15-Aug-25 9-Jan-26 TBD None TBD OASIS+ SB

78 F-16 Division 25-Aug-23 10-Jun-24 25-Jul-24 26-Aug-24 4-Dec-24 6 None ARS* OASIS SB

79 EB Directorate 14-Jun-23 7-Feb-25 21-Mar-25 21-Apr-25 13-Aug-25 TBD None TBD OASIS+ SB

80 AFIT 19-Oct-23 31-Mar-25 1-May-25 2-Jun-25 10-Nov-25 TBD None TBD OASIS+ SB

81 Fighter-Advanced A/C & Bomber Directorates 20-Aug-24 3-Feb-25 14-Mar-25 14-Apr-25 30-Jun-25 TBD None TBD OASIS+ SB

82 F-15 Division 20-Sep-24 10-Feb-25 21-Mar-25 21-Apr-25 29-Aug-25 TBD None TBD OASIS+ SB

83 MAUAS Jun-25 TBD TBD TBD TBD TBD None TBD OASIS+ SB

84 HQ AFMC Jul-25 TBD TBD TBD TBD TBD None TBD OASIS+ SB

85 WAU F-22 Division TBD TBD TBD TBD TBD TBD None TBD OASIS+ SB

Color Key: * Award Protested

Green Cells

Source Selection Information -- See FAR 2.101 & 3.104

Current as of: 28 Jan 2025

Prospective prime offerors must be in the indicated GSA OASIS+ Small Business Domain/NAICS. For details see https://buy.gsa.gov/interact/community/196/activity-feed/post/fe46eb45-5334-4db0-8936-d9ece9e7a5fb/GSA_announces_OASIS_Small_Business_Awards_and_NTPs . GSA OASIS SB IDIQ ordering period ended 19 Dec 2024.

CANCELLED

CANCELLED

CANCELLED

Notes:

= Actual date completed for competitions in-progress and awarded

The GSA OASIS+ Small Business (SB) Notices to Proceed were sent out to winning vendors on 19 Dec 2024. EPASS is conducting market research utilizing RFI's on eBuy.GSA.gov for the remaining Round 3 FOCs (FOPRs 77, 79, 80, 81, 82, 83, 84, 85) to identify Domain/NAICS.

Blue Font = Changes/Updates

CANCELLED

File details come from the government source that posted it. Updated .