This document is a phasing plan for the Engineering, Professional, and Administrative Support Services (EPASS) Round 2 Fair Opportunity Competitions (FOCs) for the Air Force Life Cycle Management Center (AFLCMC). The plan provides details on upcoming task order opportunities, including projected customer kickoff, draft and final FOPR release, proposal receipt, and award dates. The EPASS program acquires advisory and assistance services for AFLCMC, HQ AFMC, and AFIT. Prospective prime contractors must be in the designated GSA OASIS Small Business pool to be eligible for task order awards. The plan covers 84 task order opportunities across various AFLCMC directorates and portfolios, such as F-22/F-35, Global Hawk, F-16, ISR sensors, and more. The opportunities are phased over the next several years, with projected award dates ranging from September 2016 to May 2025. Socioeconomic set-asides, such as SDVOSB, are indicated where applicable.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOPR # Program
Projected
Customer
Kickoff
Projected
Draft FOPR
Projected
Final FOPR
Projected
Proposal
Receipt
Projected
Award
GSA
OASIS
SB Pool
Socio-
Economic
Set-Aside
Prime
Contractor
GSA IDIQ
38 HI (Business & Enterprise Systems Directorate) 26-Sep-16 3-Mar-17 7-Apr-17 15-Jun-18 6 None OASIS OASIS SB
39 HB (PEO Digital Directorate Hanscom) 22-Feb-18 27-Apr-18 29-May-18 13-Aug-18 6 None OASIS OASIS SB
40 HBQ (PEO Digital - Peterson AFB) N/A 27-Apr-18 29-May-18 27-Jul-18 6 None Odyssey OASIS SB
41 CROWS 13-Sep-17 6 None ARS OASIS SB
42 AFLCMC Cross Cutter (Staff/XP-OZ/F-35/NGB) 6-Jul-18 21-Sep-18 25-Oct-18 13-Dec-18 1 None Credence OASIS SB
43 HN (C3IN Directorate) 29-Jun-17 28-Feb-18 9-Apr-18 9-Jan-19 6 None ARS OASIS SB
44 AFLCMC Functionals (EN/LG/XZ-Wright Patt/LP/A4N) 1-Aug-18 2-Nov-18 4-Dec-18 1-Mar-19 3 None Credence OASIS SB
45 WN-ACS (Wright-Patt & Robins) & LAIRCM 4-Feb-19 26-Mar-19 26-Apr-19 29-Jul-19 6 SDVOSB PE Systems OASIS SB
46 EBH/HBZ-Armament (Hill) 8-Aug-18 2-Nov-18 3-Dec-18 7-Feb-19 6 SDVOSB HX5 OASIS SB
47 WIH (Helicopter Program Office) 27-Aug-18 15-Feb-19 3-May-19 24-Jun-19 25-Sep-19 6 None DCS Corp OASIS SB
48 WWU (F-22) 21-Aug-18 29-Mar-19 28-May-19 28-Jun-19 12-Sep-19 6 None Peerless OASIS SB
49 HBG (C2ISR Robins & U-2) 11-Sep-18 17-Jan-19 13-Mar-19 15-Apr-19 2-Jul-19 3 None Credence OASIS SB
50 WL (Mobility USAF/FMS) & WV (PAR/Exec) & WK (Tanker)5-Nov-18 16-May-19 27-Aug-19 30-Sep-19 3-Dec-19 6 None COLSA OASIS SB
51 WWM (F-16) 1-Nov-18 17-May-19 26-Jul-19 5-Sep-19 18-Nov-19 6 None Sumaria OASIS SB
52 WIN (ISR Sensors) 9-Nov-18 14-Aug-19 7-Nov-19 10-Dec-19 28-Feb-20 3 None Apogee OASIS SB
53 WIU (Rotary & Fixed Wing) 31-Oct-18 2-Jul-19 29-Aug-19 2-Oct-19 27-Dec-19 1 None Quantitech OASIS SB
54 EB (Robins) 27-Nov-18 17-Jun-19 12-Aug-19 20-Sep-19 22-Nov-19 3 None Credence OASIS SB
55 EB (Eglin) 27-Nov-18 25-Oct-19 3-Feb-20 16-Mar-20 10-Jun-20 5B None HX5 OASIS SB
57 AFIT 23-Jan-19 25-Jun-19 13-Sep-19 15-Oct-19 21-Jan-20 1 None Credence OASIS SB
59 WIO (ISR Crosscutter) 5-Jun-19 30-Oct-19 24-Jan-20 2-Mar-20 1-Sep-20 1 None Apogee OASIS SB
60 WA/WB (F/B Crosscutter) including B-2 8-Jul-19 9-Jan-20 5-Mar-20 13-Apr-20 17-Aug-21 6 None DCS Corp OASIS SB
61 WIG (Global Hawk) 16-Aug-19 3-Mar-20 26-May-20 29-Jun-20 29-Sep-20 6 None DCS Corp OASIS SB
62 WAQ (F-15) 5-Sep-19 4-Mar-20 5-May-20 5-Jun-20 10-Nov-20 6 None OASIS OASIS SB
64 WIS (SOF) 15-Aug-19 26-Nov-19 6-Feb-20 9-Mar-20 18-May-20 6 None Odyssey OASIS SB
65 AFLCMC Cross-Cutter/Functionals/CROWS Round Three13-Aug-21 2-Sep-22 14-Apr-23 22-May-23 19-Dec-23 6 None Credence OASIS SB
66 WII (Medium Altitude UAV) 1-Dec-20 9-Apr-21 8-Jun-21 9-Jul-21 19-Jan-22 6 None Sumaria OASIS SB
67 HQ AFMC 11-Dec-19 30-Aug-21 11-Jan-22 11-Feb-22 25-May-22 1 None CDS OASIS SB
68 GB (Business & Enterprise Systems Directorate) Follow On21-Sep-21 16-Mar-22 25-Jul-22 29-Aug-22 11-Jan-23 6 None Torch OASIS SB
69 HB Directorate (PEO Digital) 21-Oct-21 29-Apr-22 26-Oct-22 14-Dec-22 1-May-23 6 None Odyssey OASIS SB
70 USSF SSC SZQ (formerly HBQ - Peterson) 6-Jan-22 13-May-22 3-Oct-22 3-Nov-22 14-Apr-23 4 None Odyssey OASIS SB
71 WN-ACS Directorate 10-Jun-22 19-Jan-23 2-Jun-23 14-Jul-23 21-Dec-23 6 None PE Systems OASIS SB
72 Fifth-Generation Fighter (F-22 / F-35) 20-Jul-22 6-Jun-23 20-Oct-23 30-Nov-23 28-May-24 6 None TBD OASIS SB
73 HN Directorate 23-Aug-22 27-Mar-23 17-Oct-23 1-Dec-23 3-Apr-24 6 None TBD OASIS SB
74 HBG Division 31-Jul-23 12-Jan-23 9-May-24 10-Jun-24 16-Sep-24 3 None TBD OASIS SB
75 WI-RAFB 12-Apr-23 29-Nov-23 12-Apr-24 13-May-24 30-Aug-24 3 None TBD OASIS SB
76 WI-WPAFB 12-Apr-23 29-Nov-23 19-Apr-24 31-May-24 13-Sep-24 6 None TBD OASIS SB
77 WL/WV Directorates 14-Aug-23 TBD TBD TBD TBD TBD TBD TBD OASIS Plus SB*
78 F-16 Division 25-Aug-23 10-Jun-24 24-Jul-24 24-Aug-24 30-Nov-24 Pool 6 None TBD OASIS SB
79 EB Directorate 14-Jun-23 TBD TBD TBD TBD TBD TBD TBD OASIS Plus SB*
80 AFIT 19-Oct-23 TBD TBD TBD TBD TBD TBD TBD OASIS Plus SB*
81 Attack/Bomber/Adv Aircraft Aug-23 TBD TBD TBD TBD TBD TBD TBD OASIS Plus SB*
82 F-15 Division Aug-23 TBD TBD TBD TBD TBD TBD TBD OASIS Plus SB*
83 MAUAS Jun-25 TBD TBD TBD TBD TBD TBD TBD OASIS Plus SB*
84 HQ AFMC Jul-25 TBD TBD TBD TBD TBD TBD TBD OASIS Plus SB*
Green Cells Blue Font = Changes/Updates
= Actua date completed for competitions in-progress and awarded
*EPASS Acquisition Strategy approval to utilize GSA OASIS+ MAC IDIQ approved on 17 June 2024
TBD = Projection dates will be determined after award of the OASIS+ SB Contract
Prospective prime offerors are required to be in the indicated GSA OASIS SB pool. See details at: https://www.gsa.gov/buying-selling/products-services/professional-services/buy-services/one-acquisition-solution-for-integrated-services-oasis. GSA OASIS SB IDIQ ordering period ends 19 December 2024
2024.
Notes:
Source Selection Information -- See FAR 2.101 & 3.104
Current as of: 20 June 2024
Color Key: