EPASS Task Order Phasing Plan
Solicitation number
12-13-2019
Issued by

View the file

Other files

File Type Posted
EPASS Phasing Plan 20260724.pdf PDF
EPASS Phasing Plan 20260430.pdf PDF
EPASS Phasing Plan 20260211.pdf PDF
EPASS Phasing Plan 20251205.pdf PDF
EPASS Phasing Plan 20250807.pdf PDF
EPASS Phasing Plan 20250627.pdf PDF
EPASS Phasing Plan 20250424.pdf PDF
EPASS Phasing Plan 20250328.pdf PDF
EPASS Phasing Plan 20250128.pdf PDF
EPASS Follow On TO Phasing Plan 20240927.pdf PDF
EPASS Phasing Plan 20240624.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240404.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240307.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240305.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20240205 v2.pdf PDF
EPASS TO Phasing Plan for SAM Posting 20230926.pdf PDF
EPASS TO Phasing for SAM Posting - 20230721v1.2.pdf PDF
EPASS TO Phasing for SAM Posting - 20230721.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 1 May 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 24 Mar 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 2 Feb 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 27 Jan 2023.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 8 Dec 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 2 Nov 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 4 Oct 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 2 Sep 2022.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 22 Jul 2022.pdf PDF
EPASS TO Phasing Plan for FBO Posting -- as of 10 June 22.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 09 May 2022.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 14 Mar 2022.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 16 Feb 2022.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 8 Sep 2021.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 12 Jul 2021.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 08 April 2021.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 04 Dec 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 30 Sep 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 26 Aug 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 9 Jul 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 10 Jun 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 06 May 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 26 Mar 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 05 Mar 2020.pdf PDF
EPASS TO Phasing for FBO Posting -- as of 22 Jan 2020.pdf PDF
EPASS TO Phasing for SAM Posting -- as of 12 Dec 2019.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EPASS Follow On TO Phasing

FOPR

Program

Projected

Customer

Kickoff

Projected

Draft FOPR

Projected

Final FOPR

Projected

Proposal

Receipt

Projected

Award

GSA

OASIS

SB Pool

Socio‐

Economic

Set‐Aside

Prime

Contractor

GSA IDIQ

38 HI (Business & Enterprise Systems Directorate) 26‐Sep‐16 3‐Mar‐17 7‐Apr‐17 15‐Jun‐18 6 None OASIS OASIS SB

39 HB (PEO Digital Directorate Hanscom) 22‐Feb‐18 27‐Apr‐18 29‐May‐18 13‐Aug‐18 6 None OASIS OASIS SB

40 HBQ (PEO Digital ‐ Peterson AFB) N/A 27‐Apr‐18 29‐May‐18 27‐Jul‐18 6 None Odyssey OASIS SB

41 CROWS 13‐Sep‐17 6 None ARS OASIS SB

42 AFLCMC Cross Cutter (Staff/XP‐OZ/F‐35/NGB) 6‐Jul‐18 21‐Sep‐18 25‐Oct‐18 13‐Dec‐18 1 None Credence OASIS SB

43 HN (C3IN Directorate) 29‐Jun‐17 28‐Feb‐18 9‐Apr‐18 9‐Jan‐19 6 None ARS OASIS SB

44 AFLCMC Functionals (EN/LG/XZ‐Wright Patt/LP/A4N) 1‐Aug‐18 2‐Nov‐18 4‐Dec‐18 1‐Mar‐19 3 None Credence OASIS SB

45 WN‐ACS (Wright‐Patt & Robins) & LAIRCM 4‐Feb‐19 26‐Mar‐19 26‐Apr‐19 29‐Jul‐19 6 SDVOSB PE Systems OASIS SB

46 EBH/HBZ‐Armament (Hill) 8‐Aug‐18 2‐Nov‐18 3‐Dec‐18 7‐Feb‐19 6 SDVOSB HX5 OASIS SB

47 WIH (Helicopter Program Office) 27‐Aug‐18 15‐Feb‐19 3‐May‐19 24‐Jun‐19 25‐Sep‐19 6 None DCS Corp OASIS SB

48 WWU (F‐22) 21‐Aug‐18 29‐Mar‐19 28‐May‐19 28‐Jun‐19 12‐Sep‐19 6 None Peerless OASIS SB

49 HBG (C2ISR Robins & U‐2) 11‐Sep‐18 17‐Jan‐19 13‐Mar‐19 15‐Apr‐19 2‐Jul‐19 3 None Credence OASIS SB

50 WL (Mobility USAF/FMS) & WV (PAR/Exec) & WK (Tanker) 5‐Nov‐18 16‐May‐19 27‐Aug‐19 30‐Sep‐19 3‐Dec‐19 6 None COLSA OASIS SB

51 WWM (F‐16) 1‐Nov‐18 17‐May‐19 26‐Jul‐19 5‐Sep‐19 18‐Nov‐19 6 None Sumaria OASIS SB

52 WIN (ISR Sensors) 9‐Nov‐18 14‐Aug‐19 7‐Nov‐19 10‐Dec‐19 28‐Feb‐20 3 None Apogee OASIS SB

53 WIU (Rotary & Fixed Wing) 31‐Oct‐18 2‐Jul‐19 29‐Aug‐19 2‐Oct‐19 27‐Dec‐19 1 None Quantitech OASIS SB

54 EB (Robins) 27‐Nov‐18 17‐Jun‐19 12‐Aug‐19 20‐Sep‐19 22‐Nov‐19 3 None Credence OASIS SB

55 EB (Eglin) 27‐Nov‐18 25‐Oct‐19 3‐Feb‐20 16‐Mar‐20 10‐Jun‐20 5B None HX5 OASIS SB

56 WII (Medium Altitude UAV)

57 AFIT 23‐Jan‐19 25‐Jun‐19 13‐Sep‐19 15‐Oct‐19 21‐Jan‐20 1 None Credence OASIS SB

58 WWZ (B‐2)

59 WIO (ISR Crosscutter) 5‐Jun‐19 30‐Oct‐19 24‐Jan‐20 2‐Mar‐20 1‐Sep‐20 1 None Apogee OASIS SB

60 WA/WB (F/B Crosscutter) including B‐2 8‐Jul‐19 9‐Jan‐20 5‐Mar‐20 13‐Apr‐20 17‐Aug‐21 6 None DCS Corp OASIS SB

61 WIG (Global Hawk) 16‐Aug‐19 3‐Mar‐20 26‐May‐20 29‐Jun‐20 29‐Sep‐20 6 None DCS Corp OASIS SB

62 WAQ (F‐15) 5‐Sep‐19 4‐Mar‐20 5‐May‐20 5‐Jun‐20 10‐Nov‐20 6 None OASIS OASIS SB

63 HQ AFMC

64 WIS (SOF) 15‐Aug‐19 26‐Nov‐19 6‐Feb‐20 9‐Mar‐20 18‐May‐20 6 None Odyssey OASIS SB

65 AFLCMC Cross‐Cutter/Functionals/CROWS Round Three 13‐Aug‐21 2‐Sep‐22 14‐Apr‐23 22‐May‐23 12‐Oct‐23 6 None TBD OASIS SB

66 WII (Medium Altitude UAV) 1‐Dec‐20 9‐Apr‐21 8‐Jun‐21 9‐Jul‐21 19‐Jan‐22 6 None Sumaria OASIS SB

67 HQ AFMC 11‐Dec‐19 30‐Aug‐21 11‐Jan‐22 11‐Feb‐22 25‐May‐22 1 None CDS OASIS SB

68 GB (Business & Enterprise Systems Directorate) Follow On 21‐Sep‐21 16‐Mar‐22 25‐Jul‐22 29‐Aug‐22 11‐Jan‐23 6 None Torch OASIS SB

69 HB Directorate (PEO Digital) 21‐Oct‐21 29‐Apr‐22 26‐Oct‐22 14‐Dec‐22 1‐May‐23 6 None Odyssey OASIS SB

70 USSF SSC SZQ (formerly HBQ ‐ Peterson) 6‐Jan‐22 13‐May‐22 3‐Oct‐22 3‐Nov‐22 14‐Apr‐23 4 None Odyssey OASIS SB

71 WN‐ACS Directorate 10‐Jun‐22 19‐Jan‐23 2‐Jun‐23 14‐Jul‐23 14‐Nov‐23 6 None TBD OASIS SB

72 Fifth‐Generation Fighter (F‐22 / F‐35) 20‐Jul‐22 6‐Jun‐23 12‐Sep‐23 16‐Oct‐23 21‐Feb‐24 6 None TBD OASIS SB

73 HN Directorate 23‐Aug‐22 27‐Mar‐23 20‐Sep‐23 24‐Oct‐23 19‐Mar‐24 6 None TBD OASIS SB

74 HBG Division 31‐Jul‐23 15‐Nov‐23 31‐Jan‐24 5‐Mar‐24 31‐Jul‐24 TBD TBD TBD OASIS SB

75 WI‐RAFB 12‐Apr‐23 20‐Oct‐23 23‐Feb‐24 27‐Mar‐24 26‐Aug‐24 TBD TBD TBD OASIS SB

76 WI‐WPAFB 12‐Apr‐23 20‐Oct‐23 23‐Feb‐24 27‐Mar‐24 26‐Aug‐24 TBD TBD TBD OASIS SB 77 WL/WV Directorates 14‐Aug‐23 18‐Dec‐24 16‐Apr‐24 17‐May‐24 17‐Oct‐24 TBD TBD TBD TBD

78 F‐16 Division 25‐Aug‐23 10‐Jan‐24 23‐Apr‐24 24‐May‐24 23‐Oct‐24 TBD TBD TBD TBD

79 EB Directorate 14‐Jun‐22 21‐Dec‐23 18‐Mar‐24 18‐Apr‐24 16‐Sep‐24 TBD TBD TBD TBD

80 AFIT Oct‐23 Jan‐24 May‐24 Jun‐24 Nov‐24 TBD TBD TBD TBD

81 Attack/Bomber/Adv Aircraft Feb‐24 May‐24 Sep‐24 Oct‐24 Mar‐25 TBD TBD TBD TBD

82 F‐15 Division Jul‐24 Oct‐24 Feb‐25 Mar‐25 Aug‐25 TBD TBD TBD TBD

83 MAUAS Jul‐25 Oct‐25 Feb‐26 Mar‐26 Aug‐26 TBD TBD TBD TBD

84 HQ AFMC Aug‐25 Nov‐25 Mar‐26 Apr‐26 Sep‐26 TBD TBD TBD TBD

Prospective prime offerors must be in the indicated GSA OASIS SB pool. See https://www.gsa.gov/buying‐selling/products‐services/professional‐services/buy‐services/one‐acquisition‐solution‐for‐integrated‐services‐ oasis for details. End of GSA OASIS SB IDIQ ordering period is 19 December 2024.

Last Updated: 1 Sep 2023 (updates in blue font) Completed steps/competitions (awarded task orders) are in dark green.

Source Selection Information ‐‐ See FAR 2.101 & 3.104

CANCELLED

CANCELLED

CANCELLED

9/3/2023