Questions and Answers 04 April 2024.pdf
PDF 160 KB Posted
- Attached to
- LeGrande Water Development
- Solicitation number
- 12048924R0011
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains Questions and Answers related to the LaGrande Livestock Water Development Project, a federal contract opportunity solicited by the USFS. The key details are:
The project involves construction or reconstruction of 25 water developments, to be completed between 2024 and November 1, 2025. The contractor will be responsible for supplying all equipment, transportation, personnel, tools and supervision to construct the water developments and associated exclosure fencing. All materials will be provided by the USFS at the LaGrande Ranger District, which the contractor will be required to pick up and transport to the project sites.
The Questions and Answers address several technical details, including responsibility for water lines and fittings, availability of rock and drain rock, number of yards of drain rock per spring box, and provision of posts for troughs. The project sites have varying physical conditions that may affect equipment use, with some ponds requiring longer access by excavators. No site visit is scheduled, but the schedule of items provides details on the physical conditions and distances for each site.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ques�ons and Answers 04 April 2024
Is the contractor responsible for water lines and all galvanized fittings to connect to water troughs?
All hardware will be supplied by the USFS.
Is rock available at a forest service stockpile/pit or does it need to be hauled in?
Trough pla�orm rock will be supplied by the contractor but can be sourced from a USFS rock pit if requested, however rock at pits may not meet the specifica�ons.
Will drain rock be provided by the government?
Drain rock will be supplied by the contractor, none is available from USFS rock pits.
How many yards of drain rock needs to be around the spring box?
1/4 CYD es�mate per spring box. Depends on each site.
Will posts for troughs be provided by the government?
All hardware will be supplied by the USFS.
Could you describe current site conditions for required equipment use? If not, will there be a site visit scheduled?
Physical condi�ons for each site are described on the schedule of items. Springs would be hand tools or mini/small excavator. Pond cleaning will require longer reach excavator to fully clean pond. No site visit is scheduled.
How far is the pond from the road? How will site conditions and distance affect equipment use?
Physical condi�ons and distances are described in the schedule of items. Some ponds will require longer walk in for excavators due to road condi�ons. Pond cleaning will require longer reach excavator to fully clean pond.