12-SEP Solar ITB - Final Draft 4.22.26.pdf
PDF 3 MB Posted
- Attached to
- Solar Procurement and Installation for projects identified by the Sustainable Energy Partnership (“SEP”)
- Solicitation number
- 6599
- Issued by
- Montgomery County, Pennsylvania
About this file
Summary
This is an Invitation to Bid (ITB) issued by the Sustainable Energy Partnership (SEP), a consortium of four Pennsylvania counties—Bucks County, Chester County, Delaware County, and Montgomery County—for the procurement and installation of 14 solar photovoltaic (PV) projects on county-owned properties. The solicitation seeks qualified contractors to procure and construct solar systems ranging from approximately 22.82 kilowatts to 1.78 megawatts across the four counties. Bidders may submit proposals for projects in one or more counties but must bid on all projects within any county they select. The ITB was issued on April 23, 2026, with the bid due date of May 21, 2026, at 3:00 p.m. Site visits are scheduled for various dates in late April and early May 2026, with some requiring pre-clearance for security-sensitive locations including correctional facilities and county youth centers. The Q&A period runs through May 15, 2026, and Bucks County requires a separate Responsibility Certification Form submission two weeks prior to the bid deadline. Awards will be made on a county-by-county basis to the lowest responsive and responsible bidder, with the counties reserving the right to award on a project-by-project basis. The Form of Contract is provided for reference as Appendix E.
The counties are evaluating two financing structures for the projects: a Direct Pay structure in which the county owns the projects and finances them through cash resources and tax-exempt debt while pursuing federal investment tax credits through the direct pay option, and a Power Purchase Agreement (PPA) structure in which Capital Good Fund (CGF) becomes the project owner and operator and enters into a PPA to sell power to the counties. Bucks County is pursuing only the PPA structure, while Chester County's CCP-West site accepts only Direct Pay bids; all other projects require bidders to submit two bids—one using CGF's safe-harbored Enphase microinverters for the PPA structure and one using FEOC-compliant string inverters for the Direct Pay structure. Bidders must provide bid bonds equal to 10% of project costs and, if selected, submit performance and payment bonds equal to 100% of the total contract price. The bid must include detailed pricing for all equipment, labor, permitting, structural engineering, interconnection, construction, installation, operations and maintenance for year one, and warranties. Pennsylvania Solar Center will receive a one-time customer assistance contribution of $0.025 per contracted watt-dc, with at least 20% due 30 days after contract execution and the remainder due 30 days after interconnection approval. The project must comply with prevailing wage requirements, the Inflation Reduction Act (including apprenticeship, prevailing wage, and domestic content provisions for projects over one megawatt), and public works employment verification through E-Verify. Bidders must demonstrate NABCEP certification, sufficient cash flow and bonding capacity, successful completion of prior solar projects, and a minimum five-year workmanship warranty.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE COUNTY OF MONTGOMERY
Specification #6599
INVITATION TO BID FOR
Solar Procurement and Installation for projects identified by the Sustainable Energy Partnership (“SEP”) comprised of the following Pennsylvania Counties:
Bucks County, Chester County, Delaware County and Montgomery County.
Issue Date: April 23, 2026
Due Date For Bid: May 21, 2026
TABLE OF CONTENTS
A. Overview and Background of Project 4
B. Proposed Timeline 5
C. Information About the Parties 6
1. Sustainable Energy Partnership of Southeast Pennsylvania (SEP) 6
2. Pennsylvania Solar Center (PA Solar Center) 6
3. The Capital Good Fund 6
D. Summary of the Projects 8
BUCKS COUNTY SITE 8
CHESTER COUNTY SITES 8
DELAWARE COUNTY SITES 11
MONTGOMERY COUNTY SITES 14
E. Bidding Requirements 18
1. The Bonfire System 18
2. Questions and Clarifications 18
3. Overall Criteria for Bid Evaluation 18
4. Requirements for Submittal 19
a) Cover Letter 19
b) Submission Forms 19
c) Company and Project Narrative 19
d) Bid Bonds 22
5. Site Visits 22
6. Project Requirements and Bid Price 23
7. Additional Deliverables 30
8. Standard Instructions for Montgomery County Procurement Portal Solicitations 30
9. Legal Terms and Conditions 34
a. Responsibility 34
b. Governing Law 34
c. Assignment 34
d. Promotion 34
e. Indemnification 34
f. Right to Know 34
Appendix A - Submission Forms 36
1. Contractor Responsibility Certification Form 36
2. Bucks County Responsibility Certification Form 39
3. Public Disclosure Statement 42
4. Certification and Representations of Bidders 43
5. Local, Small And Disadvantaged Business Concern Certification 47
6. Worker Protection and Investment Certification Form 48
7. Responsible Contractor Status 50
Appendix B: Bid Form Containing Itemized and Total Pricing 51
Appendix C: Company and Project Narrative 52
Appendix D: References 53
Appendix E: Form of Contract (Direct Pay) 53
Appendix F: Prevailing Wage Determination 54
Appendix G: Payment and Performance Bonds 55
Appendix I: Bid Bond 61
Schedule I - Equipment List with Cost 61
Schedule II – Helioscopes for all Projects, Line Diagrams and Roof Information When Available
A. Overview and Background of Project
Bucks County, Chester County, Delaware County and Montgomery County (each, a “County” and together, the “Counties”), working as a consortium known as the Sustainable Energy Partnership (“SEP”), are requesting bids for procurement and installation of 14 solar photovoltaic (“PV”) projects (each a “Project”) on county-owned properties within their respective jurisdictions. Each County has prioritized properties that are ready for solar installation. This Invitation to Bid (“ITB”) seeks bid proposals from qualified contractors (each, a “Bidder”) to procure and construct each County’s Project(s).
Montgomery County is disseminating this solicitation on behalf of SEP and each of the Counties. In order to streamline the response effort, Montgomery County's bidding platform - known as Bonfire - will be used, as described below. Each County will make its own separate procurement decision regarding whether to proceed, and if they decide to proceed, which approach to pursue.
The Counties are considering two financing structures for the Projects. In the first (hereinafter, the “Direct
Pay”), the County would be the direct owner of its Projects, would finance the projects through a combination of available cash resources and tax-exempt debt, and would attempt to benefit from federal investment tax credits (“ITC”) through the direct pay option for non-taxpayers. In the second (the “Power
Purchase Agreement” or, “PPA”), the County would transfer the right to contract with the winning bidder for the project (along with an Operations and Maintenance Agreement) to Capital Good Fund or an affiliate
(together “CGF”) and CGF would enter into a power purchase agreement (“PPA”) with the County to sell the County the power produced by the Project. CGF would be the owner and operator of the Project and would use the ITC to reduce the cost of power to the Counties. CGF has safe harbored equipment prior to
December 31, 2025, and has entered into Letters of Intent with each of the Counties that will qualify the
Projects for the 2025 ITC regulations.
Both structures will also require an Operations and Maintenance agreement with the Bidder or its subcontractor.
As further described in the bidding requirements below, Bidders may bid on Projects for one or more
Counties but must submit a bid for all projects in any County for which they submit a bid proposal. Bids will be evaluated on a County-by-County basis. The Counties intend to award projects in aggregate across each county by project structure (PPA and/or Direct Pay) to the lowest responsive, responsible bidder to achieve administrative efficiency. But, the Counties reserve the right to award on a project-by-project basis.
The Counties will select the lowest cost, responsive and responsible bidder for the structure they believe is most advantageous.
With the exception of Bucks County (which is only pursuing the PPA structure), and the exception of the
Chester County CCP-West site (this is the only project of Chester County’s four projects for which they are only seeking Direct Pay bids), the Bidders shall provide two bids for each Project they are bidding on.
One bid (the “Direct Pay Bid”) shall reflect the use of the contractor's own Foreign Entity of Concern
(FEOC)-compliant equipment (i.e. not CGF's safe harbored equipment) and will be assessed in connection with the Direct Pay structure. The second bid shall reflect the use of the CGF safe-harbored equipment, provided as Schedule I and included in the bid form (Appendix B), and will be assessed in connection with the Power Purchase Agreement structure (the “PPA Bid”).
The Counties have not conducted a separate request for qualifications, however this solicitation includes mandatory pre-qualification requirements, as a prerequisite to submitting a bid. See Appendix A – Contractor Responsibility Certification Forms. Bidders for the Bucks County project shall be required to complete Bucks County’s separate Responsible Contractor Form in Appendix A as well.
B. Proposed Timeline
ITB issued April 23, 2026
ITB Q&A period From issuance of ITB through May 15, 2026
Online webinar information session -
Recording will be made available. (Optional for Bidders)
Week of April 27, 2026
Site visits for prospective bidders to review site conditions and electrical infrastructure. See
Section E.5 for detailed information on these site visits*. (Optional for Bidders)
Weeks of April 27, 2026 and May 4, 2026
Bucks County Responsible Contractor
Certification is Due along with any exceptions to the Contract form attached hereto. (Found in Appendix A)
Two Weeks Prior to Bid Due Date
Deadline for Bidders to submit Bids May 21, 2026
3:00 p.m.
*Delaware County Prison Project, Chester County Prison Projects, and the Montgomery County Youth Center and Eagleville sites require pre-approval of participants of site visits. Forms, timing and instructions for these site visits must be adhered to to participate, where applicable.
C. Information About the Parties
1. Sustainable Energy Partnership of Southeast Pennsylvania (SEP)
The SEP consists of four Pennsylvania Counties located in the greater Philadelphia area. SEP was created upon execution of a Memorandum of Understanding among the Counties as a result of a study commissioned by the Counties. Through a public solicitation, the Counties selected Enel X Advisory
Services USA, LLC (“Enel X”) to perform the study. Working in close collaboration with the Counties, the study was undertaken to explore the different energy procurement approaches and structures that could best meet the Counties’ long term energy goals of low-cost electricity, long term price stability, increased transparency, integration of renewable energy, and ease of on-boarding additional to-be-determined members into an aggregation approach.
Upon completion of the study, SEP determined to pursue a managed portfolio with a dedicated PJM subaccount procurement program delivered through a qualified Pennsylvania licensed electric supply service provider (“Supplier”). This program designed for local government aggregations has been successfully deployed with the support of Enel X since 2006. Under this program, SEP has adopted a block/index structure whereby competitively bid wholesale fixed rate blocks of energy are being purchased with the balance of energy purchased on the hourly markets. SEP has also been considering renewable energy purchase opportunities sourced through a variety of methods which may include purchases from member renewable energy projects, long-term PPAs sourced by the Supplier, piggybacking off other government renewable energy solicitations, and SEP issued renewable purchase solicitations for on-site projects. The program is overseen by the SEP Board consisting of appointed
County members and the program is being implemented and managed in accordance with the SEP approved Energy Cost Management and Procurement Plan.
2. Pennsylvania Solar Center (PA Solar Center)
The Pennsylvania Solar Center (“PA Solar Center”) is a nonprofit, statewide project that provides a centralized hub of resources and information for anyone who is seeking to power their home, business, house of worship or community organization with solar power. The PA Solar Center offers technical assistance to tax-exempt organizations and businesses to go solar by connecting them with trusted professionals and financing through its GET Solar program. The PA Solar Center has served as a consultant for this solicitation and has compiled the drawings, specification and calculations, this includes but is not limited to the HelioScopes provided for each project.
3. The Capital Good Fund
CGF is a nonprofit financing provider, that provides long-term PPAs to make the benefits of solar energy accessible to community organizations throughout Pennsylvania. Pennsylvania BRIGHT Solar
Communities LLC is an affiliate of CGF who together with the PA Solar Center have previously partnered to bring solar leases to small businesses, nonprofits, and municipalities through PA Solar Center’s GET
Solar program.
In December 2025, CGF received nonbinding Letters of Intent from SEP participating Counties and purchased equipment to "safe harbor" the previously identified priority projects. This was to secure the
2025 ITC rules for an additional 4 years by officially commencing construction through purchasing equipment worth at least 5% of the system cost of the solar projects. Under 2025 rules, safe harbored projects are not subject to the Foreign Entities of Concern (FEOC) requirements, and are held to a threshold of 45% Domestic Content equipment to qualify for the ITC Domestic Content Bonus Adder.
CGF will prepare a PPA proposal based on the submissions of the selected Bidder(s) under this ITB. If
CGF's PPA pricing is selected as the preferred financing vehicle, CGF will enter into a PPA with the
Counties directly. If a Bidder’s proposal is selected by CGF, the Bidder will enter into an Engineering, Procurement and Construction (EPC) contract with CGF for the respective County’s projects that is mutually agreed upon. The County of Chester has not yet determined whether it will enter into a PPA through this solicitation process.
D. Summary of the Projects
A summary of all 14 projects are provided below. With the exception of the Bucks County project, and the
Chester County Prison Site West, each project includes two designs – one aligning with the PPA structure, utilizing the CGF safe-harbored Enphase micro inverters (Enphase), and the second designed to align with the Direct Pay structure that utilizes string inverters that will be supplied by the selected bidder (String).
The detailed designs of the Projects, including AC nameplate, for each County are contained in the
Helioscopes for each site, Schedule II. Electrical line diagrams and roof assessments are available for some projects, also found in Schedule II. The requirements for submitting Bids in accordance with the specifications identified and provided for each site are provided in Section E.6 of this ITB. This section also defines all additional project requirements.
BUCKS COUNTY SITE
1. Lower Bucks Brownfield - Enphase
Address: 7311 New Falls Rd, Levittown, PA 19055
• Module DC nameplate: 458.06 kW
• Components:
o Inverters: 783 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 783 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
• Layout:
CHESTER COUNTY SITES
1. Chester County Library
Address: 450 Exton Square Pkwy, Exton, PA 19341
(Enphase)
• Module DC nameplate: 328.19 kW
• Components:
o Inverters: 561 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 561 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String)
• Module DC nameplate: 328.19 kW
• Components:
o Inverters: 4 count SE66.6KUS (SolarEdge) o Optimizers: 281 count S1200 (SolarEdge) o Modules: 561 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
Layout:
2. Chester County Public Safety Campus
Address: 137 Modena Rd, Coatesville, PA 19320
(Enphase)
• Module DC nameplate: 694.4 kW
• Components:
o Inverters: 1,187 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 1,187 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String)
• Module DC nameplate: 694.4 kW
• Components:
o Inverters: 5 count SE120KUS (SolarEdge) o Optimizers: 599 count S1200 (SolarEdge) o Modules: 1,187 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
Layout:
3. Chester County Prison/Wastewater Treatment Site West
Address: 501 S. Wawaset Rd., West Chester, PA 19382
(String) o Module DC nameplate: 1.5 MW o Components:
▪ Inverters: 13 count SE100KUS (SolarEdge)
▪ Optimizers: 1,314 count S1200 (SolarEdge)
▪ Modules: 2,560 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
4. Chester County Prison/Wastewater Treatment Site East
Address: 501 S. Wawaset Rd., West Chester, PA 19382
(Enphase) o Module DC nameplate: 1.53 MW o Components:
▪ Inverters: 2,608 count IQ9N-3P-A-US-277 (2026)(Enphase)
▪ Modules: 2,608 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String) o Module DC nameplate: 1.53 MW o Components:
▪ Inverters: 13 count SE100KUS (SolarEdge)
▪ Optimizers: 1,348 count S1200 (SolarEdge)
▪ Modules: 2,608 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
Layout:
DELAWARE COUNTY SITES
1. Machine Warehouse
Address: 403 E 24th St, Chester, PA 19013
(Enphase)
• Module DC nameplate: 148.01 kW
• Components:
o Inverters: 253 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 253 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
• Module DC nameplate: 148.01 kW
• Components:
o Inverters: 1 count SE120KUS (SE-TRI-US00IBNS4) - Domestic Content
(SolarEdge) o Optimizers: 127 count S1200 (SolarEdge) o Modules: 253 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
Layout:
2. Redwood Community Center
Address: 280 6th St, Brookhaven, PA 19015
(Enphase)
• Module DC nameplate: 40.95 kW
• Components:
o Inverters: 70 count IQ8P-3P-72-E-US-208 (2026) (Enphase) o Modules: 70 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String)
• Module DC nameplate: 40.95 kW
• Components:
o Inverters: 1 count SE33.3K (380V) (2024) (SolarEdge) o Optimizers: 37 count S1200 (SolarEdge) o Modules: 70 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
3. Government Center
Address: 201 W Front St, Media, PA
(Enphase)
• Module DC nameplate: 343.4 kW
• Components:
o Inverters: 587 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 587 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String)
• Module DC nameplate: 343.4 kW
• Components:
o Inverters: 5 count SE55K (SolarEdge) o Optimizers: 299 count S1200 (SolarEdge) o Modules: 587 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
4. Delaware County George W Hill Correctional Facility
500 Cheyney Rd, Thornton, PA 19373
(Enphase)
• Module DC nameplate: 1.01 mW
• Components:
o Inverters: 1,732 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 1,732 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String)
• Module DC nameplate: 1.01 MW
• Components:
o Inverters: 12 count SE66.6KUS (SolarEdge) o Optimizers: 891 count S1200 (SolarEdge) o Modules: 1,732 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
Layout:
MONTGOMERY COUNTY SITES
1. Fire Academy
Address: 1175 Academy Dr, Conshohocken, PA 19428
(Enphase)
• Module DC nameplate: 127.07 kW
• Components:
o Inverters: 262 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 262 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
• Module DC nameplate: 127.07 kW
• Components:
o Inverters: 2 count SE66.6KUS (SolarEdge) o Optimizers: 134 count S1200 (SolarEdge) o Modules: 262 count QCELLS, Q.PEAK DUO XLG10.d/BFG 485W (485W)
(Layout)
2. Youth Center
Address: 540 Port Indian Rd, Eagleville, PA 19403
(Enphase)
• Module DC nameplate: 350.17 kW
• Components:
o Inverters: 722 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 722 count QCELLS, Q.PEAK DUO XL G10.d/BFG 485W (485W)
(String)
• Module DC nameplate: 350.17 kW
• Components:
o Inverters: 6 count SE66.6KUS (SolarEdge) o Optimizers: 368 count S1200 (SolarEdge) o Modules: 722 count QCELLS, Q.PEAK DUO XL G10.d/BFG 485W (485W)
(Layout)
3. Trail Center
Address: 75 East Lafayette St., Norristown, PA
(Enphase)
• Module DC nameplate: 22.82 kW
• Components:
o Inverters: 39 count IQ8P-3P-72-E-US-208 (2026)(Enphase) o Modules: 39 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String)
• Module DC nameplate: 22.82 kW
• Components:
o Inverters: 1 count CPS SCA25KTL-DO/US-208 (Chint Power Systems) o Modules: 39 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
4. Courthouse Annex
Address: 102 N York Rd, Willow Grove, PA 19090
(Enphase)
• Module DC nameplate: 39.29 kW
• Components:
o Inverters: 81 count IQ8P-3P-72-E-US-208 (2026)(Enphase) o Modules: 81 count QCELLS, Q.PEAK DUO XLG10.d/BFG 485W (485W)
(String)
• Module DC nameplate: 39.29 kW
• Components:
o Inverters: 1 count CPS SCA 36KTL-DO (US) (Chint) o Modules: 81 count QCELLS, Q.PEAK DUO XLG10.d/BFG 485W (485W)
Layout:
5. Eagleville Campus
Address: 60 Eagleville Rd, Eagleville, PA 19403
(Enphase)
• Module DC nameplate: 1.78 MW
• Components:
o Inverters: 3,047 count IQ9N-3P-A-US-277 (2026)(Enphase) o Modules: 3,047 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
(String)
• Module DC nameplate: 1.78 MW
• Components:
o Inverters: 35 count CPS SCA 36KTL-DO (US) (Chint) o Modules: 3,047 count QCells, Q.PEAK DUO XL-G11S 585W (585W)
E. Bidding Requirements
1. The Bonfire System
All Bidders must submit responses through the Bonfire system. All mandatory requirements for a bid are detailed below.
2. Questions and Clarifications
For questions or clarifications on any topics covered in this ITB, please use the Bonfire system. Available answers to questions will be made available in an Amendment/Addendum that will be provided through the Bonfire system.
3. Overall Criteria for Bid Evaluation
Only Bidders submitting acceptable Contractor Responsibility Certification Form(s) will be considered. The Contractor Responsibility Certification Forms are attached hereto and included in Appendix A. Note that there is a separate Contractor Responsibility
Certification Form Specifically for Bucks County that needs to be completed for Bidders wishing to bid the Bucks County Project and submitted two weeks prior to deadline for
Bidders to submit bids. Mail to: rcocertification@buckscounty.org Any exceptions to the form of contract included in this solicitation as Appendix E, must be communicated, in writing, contemporaneously with the Contractor Responsibility
Certification Form and may be cause for a determination of non-responsiveness.
The award of contracts in each County will be to the lowest cost, responsive and responsible
Bidder.
4. Requirements for Submittal
The bid must include the following:
a) Cover Letter as detailed below;
b) All applicable Submission Forms in Appendix A;
c) Company and Project Narrative, See Appendix C;
d) Bid Bonds in the form of Appendix I.
a) Cover Letter The cover letter should state the Bidder’s business name, address, and contact information and should be addressed to the Sustainable Energy Partnership. Attached to the Cover Letter should be the list of all projects within each County for which the Bidder is submitting a bid. A Bidder may bid on all of the Projects in one or more Counties. However, if a Bidder elects to bid on a Project within a
County, it must bid on all projects within that County. Bidders will be evaluated separately for each County. Cover letters must be submitted using the Bonfire System, not physically mailed, and signed by a legally authorized representative of the Bidder.
b) Submission Forms
All forms are included in Appendix A. Failure to include these forms may lead to rejection of the proposal as non-responsive. Each form must be signed by a person authorized to bind the company. Electronic signatures are acceptable.
1. Contractor Responsibility Certification Form (Required for all projects, including Bucks). This lists qualifications that are mandatory to qualify the Bidder as Responsible for purposes of this solicitation.
2. Bucks County Responsibility Certification Form (Required for Bucks County projects only).
Due two weeks prior to the bid due date emailed to: rcocertification@buckscounty.org
3. Public Disclosure Statement
4. Certification and Representations of Bidders
5. Local, Small, And Disadvantaged Business Concern Certification
6. Worker Protection and Investment Certification Form
7. Responsible Contractor Status
c) Company and Project Narrative
Items A) through K) below should be included in a narrative that includes information pertaining to all project sites Bidder is bidding on. Please use the following lettering sequence and headers in your narrative document. See Appendix C.
A. Narrative Summary: The Bidder should provide a brief narrative summary of its company (and any installation partner(s)’/subcontractor(s)’) profile that includes (please include paragraphs with these headers):
• How long has your company been in business?
• Physical location/address of your firm’s headquarters.
• How many government, not-for- profit and commercial solar projects have you developed?
• How many solar installations have you developed in Pennsylvania? (Include the number of government projects, number of not-for-profit projects and number of commercial photovoltaic (PV) projects in Pennsylvania.).
• What is the total solar capacity (in MW) that your company has installed and what is the approximate average capacity of projects that you have completed
• Number of employees (specify number of part-time and full-time); Number of employees in Pennsylvania; total number of installation crews, and list of the members of the project team proposed to work on installations bid in accordance with this ITB.
• Expected number and type of staff that would be assigned to the projects bid.
• List the utility areas your firm commonly works in and your level of experience with their interconnection process. Highlight experience with interconnection process with PECO.
• List any Authorities Having Jurisdiction with notably difficult permitting processes and your strategies for expediting permitting.
Briefly describe how Bidder will manage the volume of installations this ITB is expected to result in for the company.
B. References: Provide additional narrative information for two examples of relevant PV projects (include Pennsylvania projects, if possible). References and contact information for at least one project site may be requested, if selected. See Appendix D.
C. Subcontractors/Partners: Summarize all key members/companies of the project team and provide brief explanation of their experience, including, but not limited to, subcontractors and/or partners assisting in the project. Indicate which party or person will serve as the main contact and project manager for the project, who is responsible for equipment procurement, who coordinates permit applications and inspection, who serves as the on-site lead for the construction/installation during the installation, and who will be the client contact for operations and maintenance issues post installation. Describe which party will be organizing legal review, and operations and maintenance.
D. Insurance, including Liability Insurance, Worker’s Compensation and Property
Insurance: See Exhibit 5 in form of Contract attached as Appendix E. Please describe what entities will be required to hold insurance that will cover any damage to the solar property after installation.
E. Safety of workers. Describe your company/subcontractor policies and procedures for ensuring safety for the workers on site and for others who are present at the worksite.
F. Public Works Employment Verification. This project falls under The Commonwealth of
Pennsylvania enacted Act 141 of 2022, known as the Public Works Employment Verification
Act which requires all public work contractors and subcontractors to utilize the Federal
Government’s E-Verify system to ensure that all employees performing work on public work projects are authorized to work in the United States. All Bidders are required to submit a Public
Works Employment Verification Form as a precondition for the contract award.
G. WMDVBE Business. For informational purposes, please describe whether you or your subcontractors are certified Women, Minority, Disabled and/or Veteran Owned Business
Enterprises. Please describe what percentage of your current workforce could be classified as a minority, woman, veteran or disabled person.
H. Training and Certifications – Bidder is required at minimum to hold the following certifications: North American Board of Certified Energy Practitioners (NABCEP) certification (including the names of the individuals in your firm or subcontractor with
NABCEP and the type of certification). Other relevant training, certification, licenses, or memberships should be listed.
Opportunities for apprenticeship or training of new workers and working with educational/training partner (if the project is less than one megawatt they are desired, but not mandatory). The PA Solar Center and the Counties are interested in these projects serving as a training/educational opportunity for the new clean energy workforce, if and where possible. While we recognize the hurdles of training people in the solar industry, particularly when there is no clear path to a job, we are interested to understand, from your perspective, if: your company can build in a solar job training/educational component or possibly a job shadowing experience with these projects; how would you accomplish this, and would you (and how would you) give priority or focus to minority, immigrant, veteran and/or women participants.
I. Compliance with the Inflation Reduction Act provisions: If an individual project is larger than one megawatt, Bidder is required to comply with certain additional provisions of the
Inflation Reduction Act. Describe how you will meet and document the apprenticeship, prevailing wage, and the domestic content requirements as specified in the Inflation Reduction
Act.
J. Tax and Regulatory Status and Clearance Statement. Include a statement attesting to
Bidder’s tax and regulatory compliance with each of the Counties containing projects that you are bidding on.
K. Written indication of PA Solar Center Customer Assistance Contribution. Include
Acknowledgement that a customer assistance contribution will be provided to the PA Solar
Center if a contract is executed. The PA Solar Center research shows that customer acquisition costs for solar developers range from $37/kilowattdc to $50/kilowattdc. The Solar
Center is providing the Bidder with a client who has a confirmed interest in going solar. The
PA Solar Center provides considerable time and resources to work with the client organization to educate and ensure project completion that should save time and money for both Bidder and client. This contribution must be included in the Bid. To maintain impartiality, the PA Solar Center will not accept larger contributions beyond what is specified in this ITB for this project. If a contract is signed with the organization for the solar installation, the Bidder will provide the PA Solar Center the following:
A one-time contribution of $0.025 per contracted watt-dc ($25.00/kilowatt-dc). In fulfillment of this contribution, the following schedule applies:
a. At least twenty percent (20%) 30 days after the organization signs the contract for the solar system.
b. The remainder 30 days after receiving interconnection approval from the utility.
d) Bid Bonds
Bidders must provide bid bonds in the amount of 10% of project costs being bid. All counties in which Bidder is seeking a contract must be named on the Bid Bond along with Montgomery
County.
5. Site Visits
Site visits to all projects is highly recommended. The Counties will be available on the following dates, at the following times, for the following site visits. Any site not mentioned below may be visited at the
Bidder’s convenience.
1. Bucks County Site –
a. Brownfield
7311 New Falls Rd, Levittown, PA 19055
May 7, 2026 10:00 AM – 12:00 PM
2. Chester County Sites –
a. Chester County Prison/Wastewater Treatment Site
501 S. Wawaset Rd., West Chester, PA 19382
May 5th, 2026 1:00 PM – 3:00 PM
Note: pre-clearance is necessary. The pre-clearance form is available on the Bonfire platform and must be submitted at least five business days prior to the scheduled site visit. Send form to Major Theobald: jtheobald@chesco.org
b. Chester County Library
450 Exton Square Pkwy, Exton, PA 19341
April 30, 2026 10:00 AM – 12:00 PM
c. Public Safety Campus
137 Modena Rd, Coatesville, PA 19320
April 30, 2026 1:00 PM – 3:00 PM
3. Delaware County Sites –
a. George Hill Prison 500 Cheyney Rd, Thornton, PA 19373 May 6, 2026 10:00 AM – 12:00 PM
Note: pre-clearance is necessary. The pre-clearance form is available on the Bonfire platform and must be submitted at least five business days prior to the scheduled site visit. Send form to Nicole Miller at millerni@co.delaware.pa.us.
b. Government Center
201 W Front St, Media, PA 19063
May 6, 2026 1:00 PM – 3:00 PM
4. Montgomery County Sites –
a. Eagleville Campus
60 Eagleville Rd, Eagleville, PA 19403
Tuesday May 5, 2026 9:00AM – 11:00 AM.
Note: Montgomery County must be notified of the names of visitors prior to site visits. Email Names of all persons attending and the company with whom they are affiliated to: Ray.Heydt@MontgomeryCountyPA.Gov
6. Project Requirements and Bid Price
The Bid Price Form (Appendix B) must include itemized costs to complete the tasks described in the project scope, inclusive of all permitting, structural engineering, interconnection requirements, labor, and equipment. The specifications and project requirements for each of the 14 projects are provided in Appendix
B, and further summarized below.
In addition to the Bid Price Form (Appendix B), bidders must provide the detail on the following list of items below as detailed in the table and the remainder of this section below.
• List of Balance of System Equipment that includes a written itemization and description of this equipment.
• Form of Operation and Maintenance Agreement
• Timeline Projections/Estimates
With the exception of the Bucks County project, each project includes two designs – one aligning with the
PPA structure, utilizing the CGF safe-harbored micro inverters, and the second designed to align with the
Direct Pay structure that utilizes string inverters. The details of the Projects for each County are contained in the Helioscopes for each site, Schedule II. The Bidder shall provide a FEOC-compliant bid as an alternative to the power purchase agreement. This will be used in the event a County or Counties opt for a
Direct Pay approach. In that case, Bidder must ensure that its equipment complies with the latest Foreign
Entities of Concern (“FEOC”) requirements.
Category Equipment and Work Specified
PV Modules PV Modules shall be commercially available, off-the-shelf products and must meet the Underwriter’s Laboratory (UL) 61730, and shall be UL/ET listed accordingly. System wiring, devices and equipment shall be installed in accordance with the provisions of the NEC 2020 or later.
The following types of PV modules are specified across the 14 projects, as detailed in Appendix C. Bidders must provide price for the equipment specified in Appendix C, or equivalent, in their response.
• QCells, Q.PEAK DUO XL-G11S 585W (585W)
• QCELLS, Q.PEAK DUO XL G10.d/BFG 485W (485W)
Bidders must provide price for the equipment specified in Appendix B, or equivalent, in their response.
Inverters Inverters shall comply to IEEE 1547-2018, UL 1741 standards and be listed with an efficiency of 98% or higher.
The following types of Inverters are specified across the 14 projects, as detailed in Appendix C. The PPA Projects are designed using the CGF safe-harbored Enphase microinverters, and the Direct Pay Projects are designed using the SolarEdge or Chint Power Systems inverters, as listed below.
Bidders must not provide a price for the PPA project (Enphase) microinverters, as these have already been purchased for these projects.
Bidders must provide price for Direct Pay Project inverters, as specified in Appendix B, or FEOC compliant equivalent, in their response. If using a FEOC compliant equivalent, Bidders include the specification in Appendix B as well.
Direct Pay Inverters (Installer-supplied inverters)
• SE33.3KUS (SolarEdge)
• SE55K (SolarEdge)
• SE100KUS (SolarEdge)
• SE66.6KUS (SolarEdge)
• SE120KUS (SE-TRI-US00IBNS4) Domestic Content (SolarEdge)
• CPS SCA25KTL-DO/US-208 (Chint Power Systems)
• CPS SCA36KTL-DO/US-480 (Chint Power Systems)
PPA Inverters (Already Purchased for these projects)
• IQ9N-3P-277-A-DOM-US (Enphase)
• IQ9N-3P-A-US-277 (2026)(Enphase)
• IQ8P-3P-72-E-US-208 (2026) (Enphase)
Optimizers The following type of optimizer is specified across the 14 projects, for the Direct Pay projects only, when Solar Edge inverters are used, as detailed in Appendix C.
• S1200 (SolarEdge)
When specified in Appendix B, Bidders must provide price for optimizers, or equivalent equipment as relevant to the inverter specified. If using equivalent, Bidders include the specification in Appendix C as well.
Racking System The mounting and racking system shall be designed in accordance with all applicable state and local codes and standards. Ideally, all structural components shall be non-corrosive (galvanized steel, stainless steel or aluminum) and shall be designed to obtain a minimum 40-year design life. 100% of any steel and iron in the racking system should be of U.S. origin if possible.
Bidders must provide total Racking System Cost for each project bid in Appendix B.
BOS Equipment If the facility service voltage is 208 VAC and the solar system consists of 480 VAC string inverters or microinverters (not 208 VAC), then a stepdown transformer is required.
Bidders must provide a written itemization and description of items in the Balance of System line item on the Bid Form Appendix B.
Bidders must provide total BOS Equipment Cost for each project bid in Appendix B.
Construction & Installation (includes all labor, site work, electrical installation, and commissioning)
Construction and installation includes all labor, site work, electrical installation, inspection and commissioning.
Bidders must provide total price of Construction & Installation in Appendix B.
For the installation portion of the proposal, contractors and subcontractors on-site will need to comply with the PA Prevailing Wage Act.
Bidders must provide a separate narrative description of its process for including local labor in the project (i.e., who is the installation company, where are they located, what are their training and hiring practices, how do they find and train workers, etc.). Describe if there are differences in terms of installation companies for the various project sites.
The following are requirements for Inspection and Commissioning:
a. To ensure compliance with all electrical codes, an inspection by a licensed electrical inspector is mandatory after construction is complete.
Commissioning tests shall be included in the final inspection and QCP. A SEP-provided commissioning agent shall ensure that:
i. All equipment specifications match the proposed equipment specifications
ii. The physical layout aligns with the as-built diagrams with variations to proposed system noted
iii. The electrical system as laid out and connected aligns with the as built one-line diagrams including fuses, relays and switches with variation to proposed system noted
b. The SEP-provided commissioning agent will oversee the Bidder's commissioning tests, which will include the following:
i. Check the manual disconnect switch operates correctly and the solar PV system shuts down as expected.
ii. Conduct open circuit voltage (Voc) test per DC string against expected Voc - For string inverters, only.
iii. Conduct operating current test per DC or AC string - for string inverters or microinverters, respectively. Test for consistency across strings.
iv. Conduct performance test per string inverter based on inverter displayed or monitored power output compared to expected power output, relative to PV array capacity, irradiance and back of the module temperature measurements, and assumed derating factors.
v. Conduct solar thermal inspection - using an infrared drone camera to measure, assess and create a thermal integrity baseline of all the solar PV modules in the system.
vi. May conduct IV curve tracer tests of string inverters, if appropriate.
Operation and Maintenance (O&M) Agreement
The Operations and Maintenance (O&M) Agreement will be a separate agreement between either the EPC or its designated subcontractor for this work provided in their Proposal and the project owner (either CGF in case of a PPA or the County in the case of a Direct Pay project). The O&M Agreement must include, but is not limited to:
i. Online monitoring;
ii. Performance monitoring, notification, and troubleshooting, down time, predicted production;
iii. Corrective maintenance to mitigate any risk to the system; and
iv. Annual system performance reports that compare actual production to
Preventative maintenance and inspections to identify and fix problems before they occur, including infrared photography for hot spots, manufacturer recommended maintenance, hardware torque checks, and array cleanings.
v. For Ground Mount Systems, cutting grass and other lawn maintenance shall be required.
vi. For rooftop and ground mounted systems, this agreement shall require the contractor address any performance issues as they arise and annual or bi-annual site visits.
Bidders must provide a description of the Operation and Maintenance Agreement. In the agreement, Bidders must describe who will be responsible for the operation and maintenance of the system along with the agreement that will be offered to them. Describe the provisions to address scheduled and corrective maintenance, system monitoring and communications protocols, as well as associated customer costs for each. The agreement must list additional costs for foreseeable issues, listed as "exclusions."
In Appendix B, Bidders must provide Year 1 price for the O&M Agreement of the entire system that is the annual fee that represents what is reflected in the Operation and Maintenance Agreement that is provided as part of the response. The O & M Agreement should include two options to extend the agreement for an additional year. O&M beyond year 1 of operation will be considered as an alternate option by each county for Direct Pay Projects.
Annual escalation shall be limited to 1.5% plus one-half of the Consumer Price Index for all Urban Consumers (CPI-U) (Philadelphia-Camden-Wilmington). See Form of Contract in Appendix E.
Warranties The following warranties are required for all projects.
PV Modules: 25-Year linear Power Output warranty & 12 Year Product.
Inverter: (If using inverters other than the specified Enphase microinverters, (i.e. for the Direct Pay option) 10-Year Product Warranty or longer. Provide a price and/or plan for inverter replacement in year 11 and beyond, or pricing to extend the product warranty to 20 years.
Workmanship: Minimum 5 Year Limited Warranty, See Article 9 of the Form of Contract (Direct Pay) in Appendix E, hereto.
Racking/Mounting System: The mounting and racking system shall be designed in accordance with all applicable state and local code standards. All structural components shall be non-corrosive (galvanized steel, stainless steel or aluminum) and shall be designed to obtain a minimum 40-year design life. Racking systems shall ensure that roof warranties are maintained after solar installation.
The Bidder must provide their standard system warranty coverage along with specific equipment warranty coverage for modules, inverter, racking/mounting and workmanship, as specified here and in Article 9 of the Contract. Bidder must describe all warranties and guarantees provided beyond those offered by Original Equipment Manufacturer, especially workmanship guaranties.
Describe quality assurance process for installations. Attach a sample workmanship warranty policy provided by your company. Describe your service call process within the terms of your workmanship warranty. Describe your service call process beyond the terms of your workmanship warranty.
Permitting, Structural Engineering and Interconnection Requirements.
Bidder is responsible for all permitting and licenses and should include the cost of all permitting and interconnection requirements in their proposal. Bidders should be familiar with PECO regulations, and have established on-site safety standards.
In Appendix B, Bidder must include the cost of Permitting, Structural Engineering and Interconnection Requirements.
Additional Requirements and Code Specifications
• The Bidder shall explicitly state whether their bid package will meet the IRS Domestic Content
Bonus Credit and will be contractually obligated to provide the necessary documentation to secure this Credit.
• The Bidder shall explicitly state the Not to Exceed Break Fee per Section 3.3(b) of Contract.
• The Counties reserve the right to modify the scope of the project at any time.
• Roof Mounting systems shall limit roof penetrations or be fully ballasted. Mounting system design needs to meet applicable local building code requirements with respect to snow and wind loading factors. Solar system installation must not void the roof warranty.
• Ground Mounting Systems require solid foundations, such as driven piers, helical anchors, ground screws, concrete footings or above ground concrete ballast, which are designed for local wind and snow loads, typically at a 25 or 30 degree tilt. However, concrete footings are to be avoided, so that the ground mounted structure can be fully decommissioned returning the ground area back to its original state. The ground-mounted structure must meet local zoning setbacks
(often 5–30 ft or more from property lines, streets, etc.), and requires a fence surrounding the ground-mounted structure and equipment per local code requirements.
• All roof access points shall be securely locked at the end of each day during construction or O&M activities.
• System layout shall meet local fire department, code and ordinance requirements for roof access.
• The installation and power generation and transmission equipment shall comply with applicable building, mechanical, fire, seismic, structural, and electrical codes. Only products that are listed, tested, identified, or labeled by Underwriters Laboratories (UL) or another nationally recognized testing laboratory shall be used as components in the project. Construction must comply with current adopted Building Code, which includes: International Building Code and National Electric
Code (NEC) 2020 ed. (NEC / NFPA 70-20)
• Modules: System modules shall be certified to Underwriter Laboratories (UL)
61730 fire code listed.
• Inverters: Shall comply to IEEE 1547-2018, UL 1741 standards and be listed with an efficiency of 98% or higher.
Background Checks Required for Work at Certain Sites:
• Delaware County: GW Hill Correctional Facility All employees must pass a background check to work at the GW Hill Correctional Facility. If subcontractors are utilized, primary contractor is responsible for ensuring all subcontractor personnel is cleared. Other background checks, clearances, or certifications are not sufficient. Prior convictions will not prevent any people from working on the site, but all previous convictions must be properly disclosed. Any undisclosed convictions, no matter how minor, will result in failing the background checks. Background checks are managed entirely by GW Hill Correctional Facility and are done at no cost.
• Montgomery County: Eagleville Campus and Youth Center: All employees must pass a background check to work at these two sites. Background checks are managed entirely by
Montgomery County.
Timeline Projections/Estimates:
General timeline projections should describe the key activities and estimated timeline including acquiring equipment, required permits (zoning, electrical, building, utility interconnection), inspections, earliest proposed installation dates and duration of installation, and the anticipated date online. This can be provided as a summary for all the projects with the understanding that timelines will vary based on each client decision making, differing permitting timelines, etc. Please include any foreseen delays such as workload issues for the company, supply chain difficulties.
In the case of the Direct Pay approach, the Counties would like to either satisfy the requirements of the
Investment Tax Credit rules, to avail themselves to the extended four-year construction time-line, or have assurances from the contractor that the installation can be completed and permission to operate obtained, prior to December 31, 2027. Please specify in the timeline how the beginning of construction or installation will meet either the Physical Work Test or the Five Percent Safe Harbor before July 4, 2026, consistent with current guidance regarding federal tax credits. If for any particular project you cannot meet the
Physical Work Test or Five Percent Safe Harbor, please indicate which projects, if any, can be completed prior to December 31, 2027. If neither of the ITC requirements can be met in the opinion of Bidder, a statement to that effect should be made.
7. Additional Deliverables
If selected, the Bid Awardee (Awardee) will be expected to provide the following:
1) Performance Bond. The selected Awardee shall submit to the County (or in the case of a PPA, CGF) a Performance Bond in the amount of 100% of the total contract price of the award prior to providing service. The Performance Bond shall be issued by a surety company legally authorized to do business within the Commonwealth of Pennsylvania. Power of Attorney must be included. The form of the
Payment Bond is attached hereto as Appendix G and will be included in the Form of Contract attached in Appendix E.
2) Payment Bond. The selected Awardee shall submit to the participating organization a Payment
Bond in the amount of 100% of the total contract price of the award prior to providing service. The
Payment Bond shall be issued by a surety company legally authorized to be business within the
Commonwealth of Pennsylvania and shall be in compliance with sections 3 and 3.1 of the Public
Works Contractors’ Bond Law of 1967, 8 P.S. § 191 et seq. The form of the Payment Bond is attached hereto as Appendix G and will be included in the Form of Contract attached in Appendix E.
Awardee shall submit the Payment and Performance Bonds, using the forms provided in Appendix
G, no later than 10 Business Days after award of the contract, unless otherwise agreed to in writing by the respective County, or, in the case of a PPA, by CGF.
8. Standard Instructions for Montgomery County Procurement Portal Solicitations
1. No verbal instructions or information to bidders will be binding. The specifications will be considered clear and complete unless written attention is called to any apparent discrepancies or incompleteness thereof, before the opening of bids. Should any inquiries be received by Montgomery County relating to this bid or proposal, only answers posted on the Montgomery County Procurement Portal will be considered binding and incorporated into the specification.
2. Bids or proposals will be considered as conclusive evidence of complete examination of specifications, addendums, samples and any other document included with the solicitation. Also, electronic submission of the document will be considered as providing a binding digital signature to the bid or proposal.
3. County reserves the right to reject any or all bids, proposals or parts thereof for projects in its jurisdiction, as deemed to be in the best interest of the County.
4. Any instructions contained in the description section of Montgomery County Procurement Portal for this solicitation shall be considered binding and part of this specification.
5. Montgomery County shall answer questions on a best-efforts basis unless otherwise stated. Questions received less than seven days prior to the opening of a bid or proposal may not receive a response.
6. All bids should be submitted through the Montgomery County Procurement Portal unless otherwise stated.
7. If a vendor experiences a technical problem uploading a bid or proposal to the Montgomery County
Procurement Portal, the County may accept the proposal through alternate means, provided the problem was brought to the County’s attention at least a half-hour prior to the solicitation’s close. Acceptance through alternate means will be solely at the discretion of the County, and may not be challenged.
Technical problems of any kind raised within a half-hour of the solicitation’s closing, regardless of cause will be solely attributed to the vendor’s negligence unless the County determines it is in the
County’s best interest to allow the submission.
Specification
8. These specifications are intended to cover the furnishing of all materials and the performance of all work that may be required or necessary for the complete performance of the contract, and the
Contractor will be required to do all things that may be necessary to fully complete the work within the…