12-REQ-0008187 Solicitation Cover - Instructions to Vendors.pdf
PDF 289 KB Posted
- Attached to
- Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical Bldg. EB-20
- Solicitation number
- REQ- 0008187
- Issued by
- Wayne County, Michigan
About this file
This is a Solicitation Cover and Instructions to Vendors document issued by the Great Lakes Water Authority (GLWA) for a construction project in Michigan. GLWA is requesting bids from qualified construction companies to perform upgrades to the Primary Area Gas Detection System and replace Switchgear SD-1 in Electrical Building-20 (EB-20) at the Water Resource Recovery Facility (WRRF). The existing gas detection systems in Scum Buildings Nos. 1 through 14, meter vaults 13 through 18, sludge pump stations Nos. 1 & 2, and the Scum Concentration Building are beyond their useful life with parts no longer manufactured, and the unit substation SD-1 has exceeded its estimated 20-year service life. An optional solicitation meeting and site tour will be held on Thursday, April 2, 2026, at 9:00 AM EST at WRRF, 9300 W. Jefferson Ave., Detroit, MI 48209, with RSVP required by Tuesday, March 31, 2026, at 4:00 PM EST. All questions must be submitted through the Bonfire Hub portal by Monday, April 13, 2026, at 12:00 PM EST. Bid responses are due by Monday, April 27, 2026, at 12:00 PM EST, with late submittals not accepted. The estimated work start date is TBD.
Contractors must meet minimum qualifications including completion of at least two successful improvement/rehabilitation projects of similar size and scope at existing water or wastewater treatment facilities within the last fifteen years and demonstrate key personnel with a minimum of ten years of experience. A 5% bid bond is required, along with performance and payment bonds equal to 100% of the contract price. The Business Inclusion and Diversity (B.I.D.) Program requirements apply, with vendors required to submit a Proposed Diversity Plan and current diversity certifications (DBE, MBE, SBE, WBE, or equivalent). Evaluation will be based 97% on lowest cost/responsive/responsible bid and 3% on B.I.D. economic equity. No specialized funding is specified as applicable. GLWA strictly prohibits the use of Artificial Intelligence (AI) tools in bid preparation, with usage potentially resulting in bid rejection. Vendors must register with GLWA's Euna Procurement platform at no cost and comply with GLWA's Procurement Policy. Within ten business days of receiving an Award Determination Letter, the selected vendor must submit all required documentation, including executed contracts and certificates of insurance meeting contract requirements.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GLWA Procurement Solicitation
Advertisement Date:
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Issuing Buyer and E-Mail Address:
Dana Thurman dana.thurman@glwater.org
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20 Solicitation Cover/Instructions to Vendors
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 07.21.2025 Page 1 of 8
Solicitation Detail
This solicitation issued by the Great Lakes Water Authority (GLWA) is seeking submittals from experienced and qualified vendors for the Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical Bldg. EB-20 project.
The costs from the successful bid shall be included in the Contract executed by the parties. The Contract can be found in Attachment No. 1. Capitalized terms used in this solicitation, if not otherwise defined herein, shall have the meaning ascribed in the Contract.
Solicitation Meeting
Attendance: Optional Date: Thursday, April 2, 2026 Time: 9:00 AM EST Location: WRRF at 9300 W. Jefferson Ave., Detroit, MI 48209- Conf Room #401 Site Tour: Immediately Following Access to the site tour requires Pré-approval through GLWA Security and Integrity.
RSVP: By Tuesday, March 31, 2026, 4:00 PM EST via email. Send the GLWA Security and Integrity Access Form with a copy of your Driver’s License to Dana.Thurman@glwater.org.
GLWA advises that the usage of A-I (Artificial Intelligence) tools are strictly prohibited. Usage of these tools may cause your bid to be rejected.
Questions
All questions must be sent through https://glwater.bonfirehub.com/portal
Question Due Date/Time: Monday, April 13, 2026, 12:00 PM EST
Note: For construction projects only, addendums will be included in the final contract document.
Due Date Date: Monday, April 27, 2026 Time: 12:00 PM EST Late submittals will not be accepted.
Contract Details The terms and conditions of the Contract, including insurance requirements, are set forth in Attachment No. 1. The estimated start Work date is TBD.
Specialized Funding N/A
Business Inclusion and Diversity (B.I.D.)
The B.I.D. Requirement Applies The GLWA B.I.D. requirements can be found at:
www.glwater.org/vendors/doing-business-with-glwa/
Required Bonds
☐ N/A ☒ Bid Bond – 5% of Bid Price ☒ Performance Bond – 100% of Contract Price ☒ Payment Bond – 100% of Contract Price https://glwater.bonfirehub.com/portal http://www.glwater.org/vendors/doing-business-with-glwa/
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 07.21.2025 Page 2 of 8
Section 1. Project Overview/Background
1. GLWA requests bids from construction companies (“Contractor”) to perform the improvements to the primary area gas detection system upgrade and the switchgear SD-1 replacement in Electrical Building-20 (EB-20) at the Water Resource Recovery Facility (WRRF) per the Speci�ications and Drawings. The existing gas detection systems and equipment in Scum Buildings Nos. 1 through 14, meter vaults 13 through 18, sludge pump stations Nos. 1 & 2, and the Scum Concentration Building are beyond their estimated useful life. Parts for the system are no longer manufactured and are difficult to acquire. Some of the systems are not currently operational.
2. The existing unit substation SD-1 in the EB-20 is beyond its estimated 20-year life and needs replacement. Parts of the unit substation have been replaced over time due to age and failure.
This unit provides power for the Scum Concentration Building and power distribution panels for some of the primary rectangular settling tanks.
The full scope of Work is described in Exhibit A of Attachment No. 1.
Section 2. Minimum Qualifications
1. Contractor and its Subcontractors for site and civil, process mechanical, electrical, and instrumentation shall demonstrate completion of a minimum of two (2) successful improvement/rehabilitation projects of existing, operating water or wastewater treatment facilities of similar size and scope to this Project within the last fifteen (15) years. These prior projects of similar size and scope shall demonstrate an ability to complete the following key elements of this Project:
a. Installation of new or replacement of existing pumps integral to the main process train (preferably for sludge pumping application in an existing wastewater treatment facility).
b. Installation of process piping system above and underground (preferably for pressurized fluid conveyance within the existing wastewater treatment facility).
c. Maintenance of facility operation throughout the construction duration.
2. Contractor and Subcontractor key personnel (Project Managers and Superintendents) shall demonstrate a minimum of ten (10) years of experience performing similar duties on construction projects of similar size and scope as this Project.
3. The Contractor’s progress schedule preparer shall demonstrate no less than ten (10) years of experience using the scheduling software required on construction projects of a similar size to this Project.
4. The required B.I.D. Program documents shall be submitted as follows:
(a) Proposed Diversity Plan – Each Vendor shall provide their method for maximizing opportunities for inclusion and diversity participation for this solicitation. Good faith efforts in reporting will include the firms contacted and why they declined as well as firms recommended for award and other pertinent information. Please complete the form included at the end of this document and attach all supporting documentation.
(b) Diversity Certification Review and Assessment – Vendors must submit a copy of any certifications that they currently hold. If a vendor has certified subcontractors, then submit the
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 07.21.2025 Page 3 of 8 subcontractor’s certifications as well. The following certifications from a federal agency, the state of Michigan, or a Michigan local unit of government (including certifications upon which those entities might rely) will be accepted and must be submitted with the vendor’s plan. This list is not exclusive, and vendors may include other types of diversity certifications.
Disadvantaged Business Enterprise (DBE) Minority Business Enterprise (MBE) Small Business Enterprise (SBE) Woman Business Enterprise (WBE)
5. GLWA Vendor Performance Score – Vendors with a validated one (1) year aggregate score of less than
70% will be deemed non-responsible pursuant to the GLWA Procurement Policy.
Section 3. Attachments
All documents are found in Euna Procurement and should be reviewed to aid in responding to this solicitation. Failure to complete and submit required documents may result in the vendor’s response being deemed non-responsive.
Attachments Description Required Submittal Attachment No. 1 GLWA Contract/Agreement Attachment No. 2 Vendor Certifications (FSA_PRO_SUP_0002) X Attachment No. 3 Bid Bond (FSA_PRO_SUP_0004) X Attachment No. 4 B.I.D. Requirements (FSA_PRO_SUP_0005) X Attachment No. 5 Schedule of Manufacturers (FSA_PRO_SUP_0006) X Attachment No. 6 Proposed List of Subcontractors (FSA_PRO_SUP_0007) X Attachment No. 7 Specifications Attachment No. 8 Drawings Attachment No. 9 Payment/Performance Bond Forms Attachment No. 10 Access Request Form X Attachment No. 11 Statement of Minimum Qualifications X
Section 4. Evaluation Criteria RFB
(End Solicitation Cover - Instructions to Vendors begin on next page)
RFB Evaluation Criteria Weight B.I.D. - Economic Equity 3% Lowest Cost/Responsive/Responsible 97%
TOTAL 100%
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 – 07.21.2025 Page 4 of 8
Instructions to Vendors
1. GENERAL INFORMATION
1.1. Any vendor interested in submitting a response to this solicitation is required to be registered with Euna Procurement at https://glwater.bonfirehub.com. Registration is FREE. By responding to this solicitation, vendor is agreeing to comply with GLWA’s Procurement Policy, available on the GLWA website at https://www.glwater.org/vendors/doing-business-with-glwa/.
1.2. All communications pertaining to this solicitation are to be directed solely to the GLWA procurement staff designated in “Solicitation Cover”.
2. ADDENDA
2.1. It is the responsibility of Vendor’s to check for any addenda posted on Euna Procurement and to make inquiry as to any changes issued thereby. Vendors are advised that no oral interpretation, information, or instruction by any officer, employee, or representative of GLWA shall be binding upon GLWA.
2.2. Any interpretations, corrections, and additional provisions that GLWA may make to this solicitation shall be made only by addendum. Should a Vendor (i) be in doubt as to the true meaning of any portion of this solicitation, (ii) find any ambiguity, inconsistency, or omission herein, or (iii) intend to take exception to any requirement of the solicitation, the Vendor must make a written request for an official interpretation or correction on or before the close of the question-and-answer period established in the Solicitation Cover.
2.3. Any addenda issued by GLWA shall become part of this solicitation and shall be reflected by vendor in its response to this solicitation. Vendors shall submit the latest revision of any form or attachment issued by an addendum with its response.
2.4. If this solicitation is a Request for Bid resulting in a construction agreement, then all addenda issued by GLWA shall be fully incorporated by reference as a part of the contract documents.
3. PREPARATION OF RESPONSE
3.1. GLWA shall have no responsibility and shall not reimburse any Vendor for any costs incurred, however caused, in the process of responding to this solicitation including, without limitation
(i) preparing and submitting its response, (ii) attending solicitation meetings, site tours or oral interviews, (iii) withdrawing its response, (iv) objecting to an award, (v) receiving a “Non-Award Determination”, or (vi) negotiating a contract resulting from this solicitation.
3.2. Vendors are advised that the scope of work is intended to define the minimum standard of quality necessary to complete the work. By submitting a response to this solicitation, vendor affirms that except for assumptions and exceptions explicitly stated, vendor considers its response accurate and sufficient to complete the work.
3.3. Documents included with this solicitation are for vendor’s information and convenience only. If a vendor requires any information beyond what is contained in this solicitation, vendor may be required, in GLWA’s sole discretion, to first provide evidence of a security clearance from the U.S. Department of Homeland Security for each person that may have access to the requested https://glwater.bonfirehub.com/ https://www.glwater.org/vendors/doing-business-with-glwa/
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 – 07.21.2025 Page 5 of 8 information. Providing evidence of security clearance does not guarantee the vendor access to the requested information.
4. PREVAILING WAGES ON FEDERALLY FUNDED CONSTRUCTION PROJECTS
If the work under this solicitation is for a federally funded construction project the vendor shall be required to pay prevailing wage rates in compliance with the Davis-Bacon Act.
5. SECURITY FOR SOLICITATION
5.1. If security is required for this solicitation, the security shall be in the form of a bid bond. The bid bond shall (i) be submitted on GLWA’s bid bond form, (ii) name the vendor as principal, (iii) be executed by a surety, either licensed to do business in the State of Michigan or which has an A.M. Best’s rating of A-/VIII or greater and (iv) be properly executed and accompanied by a certified power of attorney. Vendor’s bid security shall be retained by GLWA until the latter of
(i) the end of the period during which bids shall remain open or (ii) seven (7) business days after contract award.
5.2. The bid security of the vendor that is awarded the contract shall be retained until that vendor has (i) submitted all required information, (ii) delivered evidence of insurance, (iii) furnished the required performance and payment bonds, and (iv) executed the contract.
5.3. If the awarded vendor fails to execute the contract as requested, GLWA may annul the award notification and, if so, the bid bond shall be forfeited to GLWA. If GLWA incurs any costs in the forfeiture of the bid bond, vendor and vendor's surety jointly and severally agree to reimburse all of GLWA's costs of collection thereon, including reasonable attorneys’ fees and court costs incurred, with or without suit and interest.
6. SUBCONTRACTORS
6.1. Vendors shall be prepared to retain specific subcontractors and/or suppliers for the performance of the work if required by the solicitation documents to do so. If vendor objects to retaining any specified subcontractor and/or supplier and the concern is not addressed by an addendum, then vendor should refrain from submitting a response to this solicitation.
6.2. GLWA may request the removal and/or replacement of any subcontractor nominated by a vendor prior to awarding the contract. In such event, the vendor shall promptly nominate a qualified substitute or state that it shall self-perform the work involved, if qualified to do so. If a vendor declines to act on either option or otherwise fails to act by the date specified by GLWA, GLWA may, in its sole discretion, elect not to recommend vendor for the award.
6.3. Subsequent to the vendor’s submission of its response to this solicitation, the vendor shall not add or replace any designated subcontractor unless vendor (i) gives written notice to GLWA within ten (10) business days of receipt of an “Award Determination Letter” and (ii) provides all information requested by GLWA. If vendor fails to abide by these terms, GLWA may, in its sole discretion, elect not to recommend vendor for the award.
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 – 07.21.2025 Page 6 of 8
7. MATERIAL/EQUIPMENT SUBSTITUTES AND “OR-EQUAL” ITEMS
7.1. Contracts shall be awarded on the basis of materials and equipment specified or described in the solicitation documents and any “or-equal” or substitute materials and equipment subsequently approved by GLWA. Requests by vendor for “or-equal” or substitute materials and/or equipment shall be submitted on or before the close of the question-and-answer period.
The request shall provide a detailed description of the “or-equal” or substitute material and/or equipment and its impact on the work, including time. The burden of proof of the merit of the proposed “or-equal” or substitute item shall be on the vendor. GLWA’s decision to accept or reject any “or-equal” or substitute materials and/or equipment shall be final and set forth in an addendum. Vendor shall not rely upon approvals made in any other manner.
7.2. All prices that a vendor sets forth in its response shall be based on the presumption that vendor will furnish the materials and equipment specified or described in the solicitation documents.
Any assumptions regarding the possibility of post-response approvals of “or-equal” or substitution requests shall be made at vendor’s sole risk.
7.3. This section shall not create or impose any express or implied duty on GLWA to exercise the authority granted herein.
8. OPENING OF RESPONSE
Responses to this solicitation shall be downloaded and opened by GLWA within one (1) business day of the advertised due date and time.
9. MODIFICATION OF RESPONSE
No modification, alteration or revision to vendor's response will be accepted after the solicitation closing time and date.
10. WITHDRAWAL OF RESPONSE
A Vendor’s response may be withdrawn subject to and in accordance with the following rules:
10.1. A Vendor’s response shall not be withdrawn unless the vendor, within one (1) business day after the solicitation response opening, files a written claim with GLWA substantiating a mathematical or clerical error in its response. The claim shall include a signed affidavit stating the facts of the error and a request that vendor’s response be withdrawn. The claim shall be e-mailed to Procurement@glwater.org with a subject line that states, “Response Withdrawal Request” and includes the solicitation number and title.
10.2. If a claim to withdraw a response due to an alleged mathematical or clerical error is timely filed, GLWA shall review the claim within ten (10) business days after its receipt.
10.3. GLWA shall review the claim for evidence as to whether:
10.3.1. A Vendor’s response contains an obvious mathematical or clerical error that does not involve a lack of good faith or fair dealing; and
10.3.2. The error is subject to objective certification and is of such grave consequences that to enforce the response by way of a contract would be unconscionable; and mailto:Procurement@glwater.org
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 – 07.21.2025 Page 7 of 8
10.3.3. The error is of a material nature; and
10.3.4. The error was not caused in any way by a vendor's violation of an affirmative legal duty or culpable negligence.
10.4. Upon completion of the review, GLWA shall notify the vendor within five (5) business days of its decision to allow or not allow vendor to withdraw its response.
10.5. If GLWA suffers no serious prejudice, except loss of bargain, then GLWA shall allow a vendor to withdraw its response and, if applicable, GLWA shall return vendor's bid security within a reasonable time. Upon withdrawal of its response, vendor shall not be allowed to submit another response to the solicitation. The decision of GLWA shall be final and binding on vendor.
11. EVALUATION OF RESPONSE
11.1. For “Requests for Bids” and “Invitations to Quote”, the award shall be made to the responsible vendor submitting the lowest responsive response. GLWA shall review and validate responses for responsibility and responsiveness and prepare a bid tabulation. Bid tabulation information shall not be made available to vendor until GLWA has validated all responses for responsibility and responsiveness.
11.2. For “Requests for Proposals”, “Requests for Qualifications” and “Requests for Information”, the award shall be made to the responsible vendor with the highest ranked score pending successful negotiations. GLWA shall review and validate responses for responsiveness prior to evaluating and scoring the response. Vendors are advised that an award for “Requests for Information” and “Requests for Qualifications” will not be made unless explicitly stated in the solicitation.
11.3. GLWA reserves the right to waive any minor deviations, irregularities and informalities in the response.
11.4. GLWA reserves the right to reject any and all responses to this solicitation for reasons including, without limitation, responses that GLWA determines are nonconforming, nonresponsive, or unbalanced; responses where vendor purports to add terms or conditions, take exception to any provision of the solicitation documents, alter any template provided by GLWA for vendor’s response, or be otherwise conditional in nature; and/or a finding of vendor non-responsibility as set forth in the GLWA Procurement Policy located at GLWA-Procurement-Policy- 10.26.22.pdf.
11.5. If any grounds for the rejection of a response from the vendor under consideration for award are found, a “Non-Award Determination” shall be made by GLWA, and no further consideration shall be given to that vendor’s response. GLWA shall give written notice thereof to such vendor, including the reasons therefor.
12. CONDITIONS TO FINAL AWARD
Vendor’s response shall not be considered responsible in accordance with the requirements of the solicitation unless vendor, within ten (10) business days after receiving an “Award Determination Letter”, submits all documents that GLWA, in its sole discretion, considers necessary to complete the execution of the contract including, without limitation, the contract and certificates of insurance https://glwa.wpenginepowered.com/wp-content/uploads/2018/06/GLWA-Procurement-Policy-10.26.22.pdf https://glwa.wpenginepowered.com/wp-content/uploads/2018/06/GLWA-Procurement-Policy-10.26.22.pdf
Monday, March 23, 2026
Requisition/Contract No.:
0008187
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical BLDG. EB-20
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #5 – 07.21.2025 Page 8 of 8 meeting the contract requirements and any required bonds.
13. POST-AWARD
13.1. Vendor shall be e-mailed a fully executed copy of the contract once completed. For some solicitations, a purchase order will constitute the fully executed contract.
13.2. GLWA may periodically evaluate the performance of vendor under any contract resulting from this solicitation. Information gained during this evaluation process may be used by GLWA to evaluate vendor's capabilities to perform future work for GLWA. The criteria by which vendor will be evaluated can be found at https://www.glwater.org/vendors/doing-business-with-glwa/.
(End Instructions to Vendors)
(End Solicitation Cover/Instructions to Vendors) https://www.glwater.org/vendors/doing-business-with-glwa/
| 1. General Information |
| 1.1. Any vendor interested in submitting a response to this solicitation is required to be registered with Euna Procurement at https://glwater.bonfirehub.com. Registration is FREE. By responding to this solicitation, vendor is agreeing to comply with... |
| 1.2. All communications pertaining to this solicitation are to be directed solely to the GLWA procurement staff designated in “Solicitation Cover”. |
| 2. Addenda |
| 2.1. It is the responsibility of Vendor’s to check for any addenda posted on Euna Procurement and to make inquiry as to any changes issued thereby. Vendors are advised that no oral interpretation, information, or instruction by any officer, employee,... |
| 2.2. Any interpretations, corrections, and additional provisions that GLWA may make to this solicitation shall be made only by addendum. Should a Vendor (i) be in doubt as to the true meaning of any portion of this solicitation, (ii) find any ambigui... |
| 2.3. Any addenda issued by GLWA shall become part of this solicitation and shall be reflected by vendor in its response to this solicitation. Vendors shall submit the latest revision of any form or attachment issued by an addendum with its response. |
| 2.4. If this solicitation is a Request for Bid resulting in a construction agreement, then all addenda issued by GLWA shall be fully incorporated by reference as a part of the contract documents. |
| 3. Preparation of Response |
| 3.1. GLWA shall have no responsibility and shall not reimburse any Vendor for any costs incurred, however caused, in the process of responding to this solicitation including, without limitation (i) preparing and submitting its response, (ii) attending... |
| 3.2. Vendors are advised that the scope of work is intended to define the minimum standard of quality necessary to complete the work. By submitting a response to this solicitation, vendor affirms that except for assumptions and exceptions explicitly ... |
| 3.3. Documents included with this solicitation are for vendor’s information and convenience only. If a vendor requires any information beyond what is contained in this solicitation, vendor may be required, in GLWA’s sole discretion, to first provide ... |
| 4. Prevailing Wages on Federally Funded Construction Projects |
| 5. Security for Solicitation |
| 5.1. If security is required for this solicitation, the security shall be in the form of a bid bond. The bid bond shall (i) be submitted on GLWA’s bid bond form, (ii) name the vendor as principal, (iii) be executed by a surety, either licensed to do ... |
| 5.2. The bid security of the vendor that is awarded the contract shall be retained until that vendor has (i) submitted all required information, (ii) delivered evidence of insurance, (iii) furnished the required performance and payment bonds, and (iv)... |
| 5.3. If the awarded vendor fails to execute the contract as requested, GLWA may annul the award notification and, if so, the bid bond shall be forfeited to GLWA. If GLWA incurs any costs in the forfeiture of the bid bond, vendor and vendor's surety j... |
| 6. Subcontractors |
| 6.1. Vendors shall be prepared to retain specific subcontractors and/or suppliers for the performance of the work if required by the solicitation documents to do so. If vendor objects to retaining any specified subcontractor and/or supplier and the co... |
| 6.2. GLWA may request the removal and/or replacement of any subcontractor nominated by a vendor prior to awarding the contract. In such event, the vendor shall promptly nominate a qualified substitute or state that it shall self-perform the work invo... |
| 6.3. Subsequent to the vendor’s submission of its response to this solicitation, the vendor shall not add or replace any designated subcontractor unless vendor (i) gives written notice to GLWA within ten (10) business days of receipt of an “Award Dete... |
| 7. Material/Equipment Substitutes and “or-Equal” Items |
| 7.1. Contracts shall be awarded on the basis of materials and equipment specified or described in the solicitation documents and any “or-equal” or substitute materials and equipment subsequently approved by GLWA. Requests by vendor for “or-equal” or s... |
| 7.2. All prices that a vendor sets forth in its response shall be based on the presumption that vendor will furnish the materials and equipment specified or described in the solicitation documents. Any assumptions regarding the possibility of post-res... |
| 7.3. This section shall not create or impose any express or implied duty on GLWA to exercise the authority granted herein. |
| 8. Opening of Response |
| 9. Modification of Response |
| 10. Withdrawal of Response |
| 10.1. A Vendor’s response shall not be withdrawn unless the vendor, within one (1) business day after the solicitation response opening, files a written claim with GLWA substantiating a mathematical or clerical error in its response. The claim shall ... |
| 10.2. If a claim to withdraw a response due to an alleged mathematical or clerical error is timely filed, GLWA shall review the claim within ten (10) business days after its receipt. |
| 10.3. GLWA shall review the claim for evidence as to whether: |
| 10.3.1. A Vendor’s response contains an obvious mathematical or clerical error that does not involve a lack of good faith or fair dealing; and |
| 10.3.2. The error is subject to objective certification and is of such grave consequences that to enforce the response by way of a contract would be unconscionable; and |
| 10.3.3. The error is of a material nature; and |
| 10.3.4. The error was not caused in any way by a vendor's violation of an affirmative legal duty or culpable negligence. |
| 10.4. Upon completion of the review, GLWA shall notify the vendor within five (5) business days of its decision to allow or not allow vendor to withdraw its response. |
| 10.5. If GLWA suffers no serious prejudice, except loss of bargain, then GLWA shall allow a vendor to withdraw its response and, if applicable, GLWA shall return vendor's bid security within a reasonable time. Upon withdrawal of its response, vendor ... |
| 11. Evaluation of Response |
| 11.1. For “Requests for Bids” and “Invitations to Quote”, the award shall be made to the responsible vendor submitting the lowest responsive response. GLWA shall review and validate responses for responsibility and responsiveness and prepare a bid ta... |
| 11.2. For “Requests for Proposals”, “Requests for Qualifications” and “Requests for Information”, the award shall be made to the responsible vendor with the highest ranked score pending successful negotiations. GLWA shall review and validate response... |
| 11.3. GLWA reserves the right to waive any minor deviations, irregularities and informalities in the response. |
| 11.4. GLWA reserves the right to reject any and all responses to this solicitation for reasons including, without limitation, responses that GLWA determines are nonconforming, nonresponsive, or unbalanced; responses where vendor purports to add terms ... |
| 11.5. If any grounds for the rejection of a response from the vendor under consideration for award are found, a “Non-Award Determination” shall be made by GLWA, and no further consideration shall be given to that vendor’s response. GLWA shall give wri... |
| 12. Conditions to Final Award |
| 13. Post-Award |
| 13.1. Vendor shall be e-mailed a fully executed copy of the contract once completed. For some solicitations, a purchase order will constitute the fully executed contract. |
| 13.2. GLWA may periodically evaluate the performance of vendor under any contract resulting from this solicitation. Information gained during this evaluation process may be used by GLWA to evaluate vendor's capabilities to perform future work for GLW... |
File details come from the government source that posted it. Updated .