- Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical Bldg. EB-20
- Solicitation number
- REQ- 0008187
- Issued by
- Wayne County, Michigan
About this file
This is a Statement of Minimum Qualifications form from the Great Lakes Water Authority (GLWA) for a construction project at the Water Recovery Facility in Michigan. The project involves a Primary Area Gas Detection System Upgrade and Switchgear SD-1 Replacement at Electrical Building-20 (Requisition No. 0008187). Contractors and their subcontractors must meet specific experience requirements to be eligible for bid consideration. The document serves as a guide for preparing qualification statements and references the solicitation cover and Section 2 for additional minimum qualifications details.
The minimum qualifications require that the Contractor and Subcontractors demonstrate completion of at least three successful improvement or rehabilitation projects of existing operating water or wastewater treatment facilities of similar size and scope within the last fifteen years, with documented experience in pump installation, process piping systems, and facility operation maintenance during construction. Additionally, key personnel including Project Managers and Superintendents must have a minimum of ten years of experience on similar construction projects, and the progress schedule preparer must have no less than ten years of experience with required scheduling software on comparable projects. The form includes spaces for vendor name, signature, printed name, title, and date to be completed by the bidding organization.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GLWA Procurement
Form Effective Date:
11/7/2025
Form Document #:
FSA_PRO_SUP_0012
Form Revision Date:
N/A
Form Revision#:
Document Title:
Statement of Minimum Qualifications
Document Owner/Department:
Procurement Team
Statement of Minimum Qualifications Page 1
Project/Contract Title: Primary Area Gas Detection System Upgrade and Switchgear Replacement at Electrical Bldg. EB-20 Requisition No.: 0008187
Statement of Minimum Qualifications
Instructions: This document can be used as a guide to create your Statement of Minimum Qualifications (SOQ). Please carefully read all solicitation documents. Your organization will be rated on your ability to adhere to the solicitation requirements, in addition to how well your experience and/or references meet the minimum qualifications listed in the solicitation. The minimum qualifications are identified on the Solicitation Cover, Section 2. Be sure to complete each statement below. Additional information can be submitted as an attachment to this document.
1. The Contractor and its Subcontractor for site and civil, process mechanical, electrical, and instrumentation shall demonstrate completion of a minimum of three (2) successful improvement/rehabilitation projects of existing operating water or wastewater treatment facilities of similar size and scope to this Project within the last ten (15) years. These prior projects of similar size and scope shall demonstrate an ability to complete the following key elements of this Project:
a. Installation of new or replacement of existing pumps integral to the main process train (preferably for sludge pumping application in an existing wastewater treatment facility.
b. Installation of process piping system above and underground (preferably for pressurized fluid conveyance within the existing wastewater treatment facility).
c. Maintenance of facility operation throughout the construction duration.
2. Contractor and Subcontractor key personnel (Project Managers and Superintendents) shall demonstrate a minimum of ten (10) years of experience performing similar duties on construction projects of similar size and scope as this Project.
3. Contractor’s progress schedule preparer shall demonstrate no less than ten (10) years of experience using the scheduling software required on construction projects of a similar size to this Project.
GLWA Procurement
Form Effective Date:
11/7/2025
Form Document #:
FSA_PRO_SUP_0012
Form Revision Date:
N/A
Form Revision#:
Document Title:
Statement of Minimum Qualifications
Document Owner/Department:
Procurement Team
Statement of Minimum Qualifications Page 2
Vendor: ___________________________________________________________
Signature: ___________________________________________________________
Print Name: ___________________________________________________________
Title: ___________________________________________________________
Dated: ___________________________________________________________
File details come from the government source that posted it. Updated .