This document is a Special Provisions file for a municipal infrastructure project involving the City of Tallahassee and Leon County in Florida, specifically for the Wednesday Street Sewer Improvements project. The contract involves installing approximately 2,505 linear feet of new water main, including associated valves, services, meters, fire hydrants, and fittings. The project scope encompasses infrastructure replacement, sediment and erosion control, material disposal, maintenance of traffic, and restoration of disturbed areas including driveways, curb and gutter, and pavement. A mandatory pre-bid meeting was scheduled for Tuesday, November 18, 2025, at 2:00 PM EST via Microsoft Teams, with specific meeting details and dial-in information provided.
The project is locally funded, with no federal funds involved, which means certain federal provisions do not apply to this contract. Construction operations are restricted to between 8:30 am and 7:00 pm Monday through Saturday, subject to approval from City of Tallahassee Traffic Engineering and Underground Utilities and Public Infrastructure. Multiple permits have been secured for the project, including an NPDES Permit, City of Tallahassee Water & Sewer General Permit, Right of Way Permits, and a Florida Department of Transportation Utility Permit. The contractor will be responsible for examining and complying with all permit conditions, and must pre-approve any offsite staging areas with Leon County's Department of Development Support and Environmental Management or the City's Growth Management Department.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
I. PERMITS AND REPORTS
The following permit(s) have been secured by the City (unless otherwise noted) and apply to this Contract.
1. NPDES Permit (not provided by the City).
2. City of Tallahassee – UUPI Water & Sewer General Permit, TEM 220057 (Appendix A) City of Tallahassee – Permit to Work in the Right of Way, ROW 2025-196 (Appendix B) City of Tallahassee – Permit to Work in the Right of Way, Approved Plans (Appendix C) Florida Department of Transportation (F.D.O.T.) – Utility Permit, 2025-H-392-002333 (Appendix D) Wantman SUE Report Dated Feb. 10, 2025 & revised April 1, 2025 (Appendix E)
Bidders shall examine the permits, review and understand all permit conditions, and abide by same during execution of the work, and anticipate all costs associated with doing so. No claims for project delays or unanticipated work associated with those tasks will be considered.
In addition to the permit conditions, bidders are advised that the Contractor will be solely responsible for determining what, if any, offsite staging areas will be used, and shall be responsible to the owner of such areas regarding leasing, restoration, traffic control, etc. All staging areas to be used must be pre-approved by Leon County’s Dept. of Development Support and Environmental Management or the City’s Growth Management Department prior to their use.
The Contractor shall abide by these requirements before final payment will be released. Photographs of deficient areas existing prior to construction shall be produced by the Contractor to document such deficiencies. Otherwise, the Contractor may be required to correct such deficiencies as part of the restoration work at no extra cost to the City.
Appendices on Bonfire
II. PROSECUTION AND PROGRESS
Subarticle 8-3.4 of the Supplemental Specifications is expanded by the following:
All construction operations shall be scheduled to begin no earlier than 8:30 am and to end no later than 7:00 pm Monday through Saturday, unless otherwise approved by both City of Tallahassee Traffic Engineering and Underground Utilities and Public Infrastructure. See Project Specific Note No. 15, for more detail and workday restrictions.
The City reserves the right to limit the Contractor’s work and/or lane closure hours at any time during the project duration from those hours identified within these documents. The Contractor agrees to make no claim for additional compensation as a result of this decision by the City. However, the Contractor may be entitled to an extension of time for such acts by the City, only for the number of days which the City determines to be due to such acts.