This Request for Proposal is issued by the City of Jackson, Michigan, Community Development Department for housing rehabilitation services involving the strip and replacement of roofing and installation of new gutterwork at 115 W. Euclid. The project scope includes stripping and replacing the roof with architectural-style shingles, installing approximately 22 squares of new roofing material across all elevations including a carport, repairing approximately 100 square feet of roof decking, installing ice shield at lower roof edges, installing new felt underlayment, flashing, and ridge venting, and furnishing and installing new gutter and downspout systems in baked pre-enameled aluminum. Proposals were released on February 12, 2026, with a response deadline of March 3, 2026, at 9:00 a.m. No pre-bid meeting will be held; however, contractors may contact the homeowner, Rickey Parris, at (517) 962-1741 to schedule site access. Proposals must be submitted electronically through the City's e-Procurement Portal at https://procurement.opengov.com/portal/cityofjackson and will be evaluated on a lump sum basis for both the roofing and gutterwork line items. The contract will be awarded to the responsible bidder submitting the lowest compliant proposal, and the successful contractor will execute a Construction Contract for Rehabilitation of Residential Property with an eighteen-month warranty on all work and materials.
Bidders must be actively licensed by the State of Michigan, registered with the City of Jackson, and prequalified with registration completed on SAM.gov. Contractors must maintain comprehensive commercial general liability insurance with minimum limits of $300,000 per occurrence and $500,000 aggregate for bodily injury and property damage, along with automobile liability coverage. The project is funded through Community Development Block Grant (CDBG) program funds, and all contractors must comply with affirmative action and equal employment opportunity requirements established by the City of Jackson Commission (December 19, 1972) and federal Executive Order 11246. Contractors are responsible for obtaining all required permits, conducting final measurements, managing day-to-day progress, and notifying the Housing Rehabilitation Specialist for critical inspections. For any lead hazard reduction work, contractors must ensure site cleaning meets EPA thresholds and obtain clearance certification before occupants return to the property, with final payment withheld until clearance testing is passed. Proposals must remain in effect for 90 days after opening.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Labor_and_Material_Payment_Bond.pdf | ||
| All_Services_Sample_Contract_.docx | DOCX document | |
| G08_-_GUTTERWORK_(4).docx | DOCX document | |
| Maintenance_and_Guarantee_Bond.pdf | ||
| Performance_Bond.pdf | ||
| CDBG_Additional_Forms.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/cityofjackson
CITY OF JACKSON
2026-COMMUNITY DEVELOPMENT-009
115 W EUCLID - STRIP AND REPLACE ROOF AND GUTTERWORK
RELEASE DATE: February 12, 2026
RESPONSE DEADLINE: March 3, 2026, 9:00 am
Please refer to the project timeline in this document for all important deadlines.
Request For Proposal #2026-COMMUNITY DEVELOPMENT-009 Title: 115 W Euclid - Strip and Replace Roof and Gutterwork
Table Of Contents
1. Invitation to Bid
2. Instructions to Bidders
3. Scope of Work
4. Pricing Proposal
5. Vendor Questionnaire
6. Attachments
Attachments:
E - CDBG Additional Forms
Invitation to Bid
Sealed proposals for 115 W Euclid - Strip and Replace Roof and Gutterwork will be received by the
City of Jackson Purchasing Coordinator, Kari Kerstetter, via the City of Jackson e-Procurement
Portal, https://procurement.opengov.com/portal/cityofjackson.
The work includes the following partial listing of items with approximate quantities: Strip and replace roof and gutterwork
Bidders may obtain Instructions to Bidders, Proposal Forms, Specifications and Contract Forms on the City of Jackson e-Procurement Portal, https://procurement.opengov.com/portal/cityofjackson.
Bidders will be required to meet the City of Jackson's pre-qualification requirements prior to bid opening. Bidders must be prequalified for Registration completed on SAM.gov.
The City of Jackson does not discriminate on the basis of race, religion or national origin, color, age, sex, height, weight, marital status, and physical or mental handicap as to: access, availability, employment, or participation in any of its programs and activities.
City of Jackson
Heather Ehnis
Purchasing Agent
Instructions to Bidders
1. Project
The work includes the following partial listing of items with approximate quantities:
Strip and Replace Roof and Gutterwork at 115 W. Euclid
The scope of this work shall include all labor, equipment and materials necessary to complete this project according to the specifications listed in the contract documents. All labor, equipment and materials necessary for completion of the work, but not specifically listed as a pay item, will be deemed to be included in one or more of the pay items listed in the bid sheet.
2. No Pre-Bid Meeting - Housing Rehab
No pre-bid meeting will be held; contractors may contact the homeowner to schedule a date and time to access the property to better understand the project’s scope of work, if necessary.
HOMEOWNER: Rickey Parris PHONE: (517) 962-1741
3. Housing Rehabilition Basic Requirements
To be eligible for participation in City of Jackson, Community Development rehabilitation projects, a contractor must:
1. Be actively licensed by the State of Michigan and registered with the City of Jackson.
2. Possess “tools of the trade” which include basic contracting tools and vehicle for transporting materials, tools, and accessing the property.
3. Be familiar and at ease with the use of communication tools, i.e., computer and have access to electronic mail (email) and telephone.
4. Have a thorough knowledge of and adequately apply construction industry methodologies and standards.
5. Have an acceptable past performance record.
6. The contractor is responsible for obtaining all permits and/or submitting design review documents as required.
7. The contractor shall monitor day-to-day progress of their work to ensure high quality workmanship and timely completion. The Housing Rehabilitation Specialist will require notification for certain critical inspections such as discovery of dry rot or termite damage, completion of progress work and completion of final work. Failure to contact the Housing
Rehabilitation Specialist for such an inspection may result in progress payment delays or non-payment.
8. For all work that involves lead hazard reduction, the contractor is responsible for cleaning the site to a level below the current thresholds established by the Environmental Protection
Agency (EPA) for floors, interior sills, exterior window wells, and floors. The Housing
Rehabilitation Specialist will advise contractor which Lead Risk Assessor is selected for the project; the contractor is responsible for ordering the clearance examination. Lead clearance must be achieved before relocated occupants are allowed to return to their home. The contractor is responsible for all additional cleaning operations if the work fails to attain the mandated clearance thresholds as well as any additional cost assessed by the clearance technician for repeated visits, dust and/or laboratory fees. Final payment is withheld until the unit passes clearance testing.
9. The contractor will provide an eighteen (18) month warranty for work and materials completed under the contract.
1. Minimum required limits of liability:
a. For jobs with an estimated contract cost of less than $50,000
a. Comprehensive Commercial General Liability, limits of at least:
(1) Bodily Injury, each occurrence $300,000
(2) Bodily Injury, each aggregate $500,000
(3) Property Damage, each occurrence $100,000
(4) Property Damage, aggregate $100,000
(or in the alternative to 1, 2, 3, 4)
(5) Bodily Injury and Property Damage Combined Single Limit each occurrence $500,000 and aggregate $500,000
b. Automobile Liability, limits of at least:
(1) Bodily Injury, each person $300,000
(2) Bodily Injury, each occurrence $500,000
(3) Property Damage, each occurrence $100,000
(or in the alternate to 1, 2, 3)
(4) Bodily Injury and Property Damage Combined Single Limit each occurrence $500,000
4. Proposals for Housing Rehab
a. Proposals should be submitted to Submit Electronic Responses via the City’s e-Procurement
Portal, https://procurement.opengov.com/portal/cityofjackson.
b. Proposals, affidavits, certificates and all appendices must be fully and properly filled out and executed.
c. Proposals must be bid on a unit price basis as applied to the estimated quantities. Where errors of extension of totals are made, the unit price bid multiplied by the estimated quantity shall govern. The preliminary estimates of quantities indicated, although given with as much accuracy as possible, are to be regarded as approximately only, and are given for the general guidance of the bidders and as a basis upon which the different proposal may be compared. The City reserves the right to increase or diminish any or all of these quantities within reasonable limits and the Contractor will be paid for the actual work completed and accepted by the City at the prices stated in his Proposal.
Upon the discovery of an obvious error in a bid document that could result in a change in the amount of a bid, the staff of the Purchasing Department shall contact the bidder in writing and advise the bidder that it has seven working days from the date of the letter to correct the error. This correction shall be in writing directed to the Purchasing Agent and shall be postmarked no later than seven working days from the date of the letter referred to in the first sentence of this paragraph.
If no correction is received in a timely fashion, then the Purchasing Agent shall reject the bid. If a correction is received and the Purchasing Department deems the same to be appropriate and proper in every way, the Purchasing staff shall attach same to the original bid document and shall then proceed to tabulate the bids as corrected.
d. Proposals may be withdrawn up to the time for opening bids announced in the Invitation for Bids.
Proposals shall remain in effect for 90 days after opening.
e. Each bidder shall be held to have examined the site of the proposed work and adjacent areas in order to arrive at a clear understanding of the conditions under which the work is to be done. He shall be held responsible to have compared the site with the drawings and specifications and to have satisfied himself as to the conditions of the site, existing obstructions, the actual elevations, and any other conditions affecting the carrying out of his work. No allowance or extra consideration on behalf of the Contractor shall be allowed by reason of error, negligence, oversight, or carelessness on the part of the Contractor.
5. Award for Housing Rehab
a. The contract will be awarded to the Responsible Bidder submitting the lowest proposal complying with the conditions of the Invitation for Bids and Instructions to Bidders, provided the bid is reasonable and it is in the interest of the Owner to accept it. The bidder to whom the award is made will be notified at the earliest practicable date. The Owner, however, reserves the right to reject any and all bids and to waive any informality in bids received whenever such rejection or waiver is in the interest of the Owner. Anything contained herein to the contrary notwithstanding, Owner may award the contract to a bidder submitting the non-lowest proposal, provided Owner pays the difference between the lowest proposal and the selected proposal.
b. The Owner and the City also reserve the right to reject the bid of any bidder who has previously failed to perform properly, or to complete on time, contracts of a similar nature; who is not in a position to perform the contract; or who has habitually and without just cause neglected the payment of bills or otherwise disregarded his obligations to subcontractors, material, men or employees.
6. Contract for Housing Rehab
The successful bidder will be required to enter into a contract with the property owner by executing a
Construction Contract Rehabilitation of Residential Property and shall comply with all terms and conditions contained therein.
Scope of Work
1. 1 - R05 - ROOF - STRIP AND INSTALL
*PERMIT REQUIRED*
Strip existing roof, removing all shingles and felt. Make repairs to the existing roof framing where required to provide adequate strength and a true and level surface. Install 7/16” oriented-strand board sheathing to cover all areas of roof deck. Just before proceeding, sweep roof thoroughly to remove all debris. Install ice shield at all lower roof edges. Ice shield shall extend at least 24" inside the interior surface of the exterior wall line of the building, in accordance with the Michigan Building Code. Install new 15% asphalt saturated felt according to manufacturer's directions. Furnish and install new roofing material of a color as selected by owner, must be architectural style. Installation shall include metal drip and rake edge, two layers of 90# roll valley or metal valley in all valleys. Reflash chimney, plumbing vents, and vertical walls with appropriate neoprene boots and metal step flashing where possible. Install ventilation units sufficient to vent all areas of attic. Ridge venting when used shall cover the full length of the roof ridge. Installation of all materials shall follow manufacturer's printed instructions and G.S. 1.
Contractor is responsible for final measurement.
Currently, there is a tarp on the rear lower roof, Plan on approximately 100 sq ft of decking repair prior to sheathing the roof.
Approximately 22 SQ squares on all elevations. To include the car port;
New roofing material type shall be architectural shingles.
Manufacturer: _____________________________
Color Name/Number: ______________________
Contractor's Initials: ____________________
Owner's Initials: ______________
Rehab Initials: ________________
2. 2 - G08 - GUTTERWORK
Furnish and install gutter and downspout. Replacements shall match existing as to materials, finish, shape and size. Do not mix galvanized with copper or aluminum. Where replacements are of a complete system or side of a system having no cross connections with sections not to be replaced, use baked pre-enameled aluminum, 5-inch K-type in standard colors. Minimum thickness of aluminum shall be .027 inches for troughs and fittings. Use one or a combination of strap hangers, spike and ferrules or fascia hangers. Space hangers and slip joint connectors per manufacturer's instructions. Maximum spacing of hangers shall be 48 inches OC for galvanized and 30 inches for aluminum. Use only recommended gutter seal and rivets or screws at all joints.
All work, whether a complete new system or a partial replacement, shall have the system with a pitch of not less than 1 inch in 16 feet. Divert the water away from the foundation using appropriate extensions and/or concrete splash blocks. All work to conform to code and G.S. 4a.
Contractor responsible for final measurements.
All Downspouts shall be commercial size.
Approximately __________ linear feet of gutter on all elevation(s).
Approximately ___________ linear feet of downspout on all elevation(s).
Pricing Proposal
The Undersigned has examined the plans, specifications, and the location of the above-described work, and is fully informed as to the conditions relating to its performance, and understands the quantities shown in the estimate and on the plans are accurate to the best belief and knowledge of the Engineer but are not guaranteed.
The undersigned hereby proposes to furnish all equipment, materials, supplies, labor, and services necessary to commence and complete the project as described in the Contract Documents; and in strict conformity with the requirements of the Specifications and such other special provisions and supplemental specifications as may be a part of this proposal for the above described project at the following unit prices all labor, equipment and materials necessary for completion of the work, but not specifically listed as a pay item, will be deemed to be included in one or more of the pay items listed in the bid sheet.
Bidder has examined and carefully studied the Bidding Documents, other related data identified in the
Bidding Documents.
115 W. EUCLID - STRIP AND REPLACE ROOF, ADD NEW GUTTERS
Line Item Description Quantity Unit of Measure Unit Cost Total
1 Strip & Replace
Roof per specifications
1 LUMP SUM
2 Gutterwork per specifications
1 LUMP SUM
TOTAL
Vendor Questionnaire
1. Confirmations
Proposal Confirmation* By submitting this application, I, the bidder, hereby propose to perform said work, strictly as specified in the bid documents at the prices set forth on the attached schedule of bid prices, upon receipt of written notice of acceptance of this bid within one hundred twenty (120) calendar days after opening of the bids at the time stated in said Invitation; to execute a properly completed contract in the form provided with the bid documents in accordance with this bid; to give bond with good and sufficient surety or sureties, satisfactory to the City Attorney of Jackson, for the faithful performance of said contract, for payment of labor and materials, and, if required, for maintenance of work; and to give such bond within ten (10) days after notice of award.
☐ Please confirm
*Response required
Contract Compliance* The Commission of the City of Jackson, on 12/19/72, passed a resolution committing the City to a policy and procedure regarding compliance to affirmative hiring practices by contracting agencies doing business with the City of Jackson, effective 12/20/72.
The purpose of the policy and procedure is to ensure that all citizens of our community have the opportunity for equality of treatment in service and employment.
The City requests that all bidders who will be doing business with the City in the amount of $5,000 or more during any fiscal year, shall comply with the provisions of the Contract Compliance Policy.
Bidders will be required to show an Equal Employment Opportunity Certificate of Compliance or demonstrate compliance with standards for equal employment opportunity established by state and federal statute:
will not discriminate against any employee or applicant for employment with respect to hire, tenure, term, conditions, or privileges or employment because race, religion or national origin, color, age, sex, height, weight, marital status, sexual orientation, gender identity, and physical or mental handicap.
In connection with this commitment, the bidder understands that they will be reviewed by the State of
Michigan, Department of Civil Rights for determination of its status as an awardable Bidder.
The undersigned hereby agrees that they will abide by the terms of any agreements made with the
City of Jackson in order to achieve awardable status.
☐ Please confirm
*Response required
Non-Discrimination Clause for All City of Jackson Contracts * In connection with the performance of this contract, the contractor agrees as follows:
1. The contractor will not discriminate against any employee/employer for employment because of race, religion or national origin, color, age, sex, height, weight, marital status, sexual orientation, gender identity, and physical or mental handicap. The contractor will take affirmative action to ensure that minority applicants are employed, and that employees are treated during employment without regard to their race, religion, color, national origin, age, sex, height, weight, marital status or handicap. Such action shall include, but not be limited to, the following: layoff or termination, rates of pay or other forms of compensation, selection for training, upgrading or promotion, transfer or recruitment.
2. The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to race, religion, color, national origin, age, sex, height, weight, marital status or handicap. As a disclaimer, the contractor may state in the advertisement that he/she is an equal opportunity employer.
3. The contractor will furnish and file compliance reports with the City of Jackson as requested. Such reports shall elicit information as to the practices, policies, program and employment statistics for the contractor and said contractor shall permit access to all books, records and accounts regarding employment practices by agents and representatives of the City duly charged with investigative duties to assure compliance with this clause.
4. Breach of the covenants herein may be regarded as a material breach of the contract or purchasing agreement.
5. The contractor will include, or incorporate by reference, the provisions of paragraphs (1) through
(4) in every subcontract or purchase order unless exempted by the rules, regulations or orders of the
Michigan Civil Rights Commission and will provide in every subcontract or purchase order that said provisions will be binding upon each subcontractor or seller.
☐ Please confirm
*Response required
Equal Employment Opportunity Certification * The undersigned understands and agrees that, as a Contractor for services, there shall be no discrimination against any employee or applicant for employment because of race, religion or national origin, color, age, sex, height, weight, marital status, sexual orientation, gender identity, and physical or mental handicap, including but no limited to employment, upgrading, demotion, or transfer;
recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation and selection for training.
The Contractor further agrees to the following:
(a) It will assist and actively cooperate with the City in obtaining compliance of any subcontractors with the equal opportunity rules, regulations, and relevant orders.
(2) It will furnish the City such information as might be required for the supervision of its compliance program and will otherwise assist the City in the discharge of its responsibility for ensuring compliance.
(3) In the event that the Contractor fails or refuses to comply with the equal opportunity regulations, the City may cause to be canceled, terminated, or suspended in whole or in part the contractual arrangement between the City and the Contractor.
☐ Please confirm
*Response required
SAM.gov UIN* Please provide your sam.gov Unique ldentity Number (UlN), if you have received it. lf you have applied for your UIN and have not received it, please indicate the date of application.
*Response required
Attach required Certificate of Insurance and Builder's License(s)* *Response required
Additional Documents
Equal Opportunity Clause* During the performance of this contract, the contractor agrees as follows:
(1) The contractor will not discriminate against any employee or applicant for employment because of race, creed, color, or national origin. The contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to their race, creed, color, or national origin. Such action shall include, but not be limited to the following:
employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the contracting officer setting forth the provisions of this nondiscrimination clause.
(2) The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to race, creed, color, or national origin.
(3) The contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice, to be provided by the agency contracting officer, advising the labor union or workers' representative of the contractor's commitments under Section 202 of Executive Order No. 11246 of September 24, 1965, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
(4) The contractor will comply with all provisions of Executive Order No. 11246 of Sept. 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
(5) The contractor will furnish all information and reports required by Executive Order No. 11246 of
September 24, 1965, and by the rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the contracting agency and the
Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
(6) In the event of the contractor's noncompliance with the nondiscrimination clauses of this contract or with any of such rules, regulations, or orders, this contract may be cancelled, terminated or suspended in whole or in part and the contractor may be declared ineligible for further Government contracts in accordance with procedures authorized in Executive Order No. 11246 of Sept 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order No.
11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
(7) The contractor will include the provisions of Paragraphs (1) through (7) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order No. 11246 of Sept. 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The contractor will take such action with respect to any subcontract or purchase order as the contracting agency may direct as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, That in the event the contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the contracting agency, the contractor may request the United States to enter into such litigation to protect the interests of the United States."