About this file
The document is a Supplier Coordination Request (SCR) Form from TerraPower, LLC, associated with a request for a Primary Neutron Source of Californium-252 (Cf-252) for the Natrium Project. The form is designed for suppliers to communicate non-conformances, deviations from contract requirements, requests for information, or other issues related to a purchase order or agreement. TerraPower is seeking a supplier to provide the Cf-252 neutron source, with the solicitation being hosted on the Bonfire platform and requiring all bidders to sign a non-disclosure agreement (NDA) prior to accessing the project opportunity package.
The solicitation is specific to Washington state and involves a technical procurement process with strict communication protocols. Suppliers are instructed to submit questions or comments through the Bonfire Q&A section by a specified deadline, with TerraPower providing responses to all invited bidders. The form includes provisions for different quality levels (QL1, QL2, QL3) and critical/non-critical classifications, and requires suppliers to send completed SCRs to submittals@terrapower.com, copying the Contract Administrator and Technical Representative. The document emphasizes confidentiality, with explicit instructions to avoid uploading export-controlled information (ECI) and to use alternative submission methods if such information is involved.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Supplier Coordination Request (SCR) Form TP-PRC-FORM-0006 Rev 10 TP-PRC-FORM-000X-Rev-0
FOR SUPPLIER USE
| Date Submitted |
| Response Required Date |
| Supplier Name |
(as shown on Order/Agreement)
| Purchase Order/Agreement No. |
| Supplier SCR No. |
Reason for SCR (Check box that applies)
☐ Non-Conformance Request (NCR) ☐ Deviation from Contract Requirements (DCR) ☐ Request for Information (RFI) ☐ Other ________________________________________________________________________________________________________________________________________
SCR details (Include documents; attach supporting information and comments/recommendations as needed)
SCR Impacts (Cost, Schedule, Scope, Technical, QA, Other)
Send the SCR to submittals@terrapower.com, the Contract Administrator (CA), and the Technical Representative (TR/SPE) for the Purchase Order. An incomplete form may require a re-submission. If this SCR contains export controlled information (ECI) or if any of the supporting documents/information contain ECI, DO NOT submit this SCR via e-mail. Please contact the CA to submit this SCR via ShareFile.
FOR TERRAPOWER USE
| SCR No. |
| Revision No. |
| Date Received |
| Date Closed |
| CA Name |
| TR/SPE Name |
Quality Level
| ☐ QL1 |
| ☐ QL2 |
| ☐ QL-3 |
| ☐ TPI Critical |
| ☐ TPI Non-Critical |
TerraPower Disposition*
☐ ACCEPTED – work may proceed as specified in TerraPower response. Resubmission is not needed.
☐ NOT ACCEPTED – stop work that is related to the subject SCR. Resubmission via revision is required.
PO Revision Required* ☐ No ☐ Yes
TerraPower Response (Attach sheets if needed)
TERRAPOWER PROPRIETARY AND CONFIDENTIAL – SUBJECT TO CONFIDENTIALITY AGREEMENT– Uncontrolled when printed
Guiding Procedure: TP-PRC-PROC-0006 Page 1 of 1 image1.png