This document is a Request for Proposal (RFP) solicitation from the Madison Public Schools and the Town of Madison in Connecticut's New Haven County for MEP (mechanical, electrical, and plumbing) upgrades to the Polson Middle School. The project, which was approved through referendum on February 15, 2022, will be completed in two phases. Phase 1 involves developing schematic design documents and specifications for HVAC, electrical power, and distribution upgrades, as well as a feasibility study for a geothermal system. Phase 2 will include construction documents, bid support, construction administration, and project close-out. The RFP has a start date of August 8, 2022, and an end date of August 31, 2022, with no vendor Q&A period specified.
The RFP does not provide details on pricing terms, set-asides, incumbents, funding requirements, or sources. It states the estimated total value but does not specify a budget amount. The RFP is open to all vendors, and the selected engineer will be responsible for providing the requested MEP services for the Polson Middle School upgrades.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number: 10214
Polson Middle School MEP Upgrades
Request for Proposal (RFP)
Madison, Town of
August 08, 2022 - August 31, 2022
Page:2
General Header Information
This bid has no questions defined.
10214
No. 10214 Title: Polson Middle School MEP Upgrades Start Date: August 08, 2022 at 11:30:00 AM EDT End Date: August 31, 2022 at 2:00:00 PM EDT Vendor Q&A Start Date:
Vendor Q&A End Date:
Estimated Total Value:
Who can respond to this bid? : All Vendors Description: Madison Public Schools and the Town of Madison “Town” is seeking one qualified engineering firm “Engineer” to provide MEP services related with HVAC (heating, ventilation, and air conditioning), electrical power and distribution upgrades to the Polson Middle School, and geothermal studies to serve the school. The project was approved through referendum on February 15, 2022.
The intended project approach divides the total project scope into two (2) phases. The initial RFP (Phase 1) will include development of schematic design (SD) documents and specifications for a comprehensive HVAC, electrical power, distribution upgrade to the Polson Middle School and the feasibility study for installing a geothermal system. The Phase 2 scope will generally consist of competing construction documents, bid support, construction administration, and project close-out.
Delivery Terms: See Delivery Notes Payment Terms: Vendor Specified Contact Information: Madison, Town of
Blair Richardson, P.E., Director of Commissioning and Energy Services, blair.richardson@collierseng.com
Contact Details: If you have any questions, please contact:
Blair Richardson, P.E., Director of Commissioning and Energy Services, blair.richardson@collierseng.com
Selected Categories:
Page:3
Documents:
Madison Polson MEP RFP-RFQ FINAL.pdf
Madison Polson MEP RFP-RFQ - ADDENDUM 2.pdf
Madison Polson MEP RFP-RFQ - ADDENDUM 1.pdf
Page:4
Item Specifications Solicitation has been designated as having no line items.