This is a Special Conditions document for the Franklin Township Municipal Building Addition & Renovation Project located at 150 Century Lane in Franklin Township, York County, Pennsylvania. The project encompasses construction of a new municipal meeting room building and renovation of the existing municipal building, to be executed under four separate prime contracts: General Construction (Contract 1), Mechanical Construction (Contract 2), Electrical Construction (Contract 3), and Plumbing Construction (Contract 4). A non-mandatory pre-bid site visit will be held on August 26, 2026, from 10:00 to 11:00 AM at the Township Offices. Sealed proposals will be received online via the PennBid Program until 2:00 PM on September 22, 2026, with bids opening at 2:15 PM. Requests for Information must be submitted within the PennBid System no later than September 17, 2026, at 5:00 PM. The Franklin Township Board of Supervisors will vote on bid awards at a special meeting scheduled for 6:00 PM on September 22, 2026. Substantial completion for each prime contract is established at 10 calendar months from the date of execution of the Standard Form of Agreement.
All bids must be accompanied by a bid bond equal to 10 percent of the bid amount, made payable to the Township. The successful bidders will be required to furnish additional bonds as prescribed in the bidding documents. All bids remain subject to acceptance by the Township Board of Supervisors for up to 60 days during the evaluation and award period. The project is subject to Pennsylvania Prevailing Wages and the Public Works Employment Verification Act, with prevailing wage information to be displayed at a high-visibility site within the contract work area. Liquidated damages are established at $1,000 per day for any delay in substantial completion of each prime contract. The General Contractor will serve as the Project Coordinator responsible for coordination among all prime contractors and shall submit a Master Project Schedule incorporating the schedules of other prime contractors within ten working days following notification as the apparent low bidder. Franklin Township reserves the right to reject any or all bids or to waive any informality in bids received.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Franklin Township 1 Meeting Room Building and Renovation Special Conditions
SPECIAL CONDITIONS
A. GENERAL
1. Scope of Project
a. Location
The Project is a new municipal Meeting Room building and Renovation to the Existing building for the Owner (Franklin Township) located at the municipal building at 150 Century Lane in Franklin Township, York County, Pennsylvania in accordance with the Contract Documents.
b. Scope
It is the intent of the drawings and specifications to describe the construction of the New Meeting Room Addition and Renovation to the Existing Building to be performed under separate prime contracts (the “Prime Contracts”) as described below. Each Prime Contractor shall furnish all labor, materials, equipment, machinery, apparatus and tools and perform all operations necessary to install, equip and put into satisfactory operation the Work specified and shown on the Plans.
Any labor, materials, equipment, or apparatus not specifically mentioned in the plans or specifications which may be necessary for the proper completion of the entire Work shall be furnished by each Prime Contractor without additional compensation.
c. Contract Documents
The Contract Documents, as defined in the Standard Form of Agreement, which are made a part hereof. In the event of any inconsistency, the provisions of these Special Conditions shall control.
d. Starting and Completing Work
The Contract work shall be started immediately upon receipt of a written notice from the Owner and shall be continued in full force until completion, unless approval to suspend work is granted by the Owner or unless delays occur due to unfavorable weather.
Before filing his bid, the Bidder shall have made all arrangements to be fully equipped to expeditiously carry on all work in case he is awarded a Contract and shall have made all arrangements to permit immediate transportation to the site of the work of all equipment, materials and other facilities required to execute the work.
Franklin Township 2
In scheduling his operations, the Prime Contractor shall take into consideration all delays that may occur due to unfavorable weather; failure of public utilities or others to install, remove or adjust their structures when required; and the uncertainties prevailing on account of a national emergency in regard to obtaining critical materials and labor to complete the various portions of such work in time.
e. Release of Lien
For each application for payment, as well as upon request for final retainage, the Prime Contractor shall provide to the Construction Manager a release of liens as to all work performed and all material supplied by the Prime Contractor and all its subcontractors, sub-subcontractors, and all others who have provided labor or materials for the work in that Prime Contract, through the date for which payment is sought, and which release shall be properly signed by each such party and be in a format acceptable to the Township.
2. Definitions
a. Permanent Enclosure
As determined by Architect/Engineer, permanent or temporary roofing, which is complete, insulated, and weathertight; exterior walls are insulated and weathertight;
and all openings are closed with permanent construction or substantial temporary closures.
3. Prime Contracts
a. Prime contracts for Project include the following:
Contract 1 – General Construction (Contract 1) Contract 2 – Mechanical Construction (Contract 2) Contract 3 – Electrical Construction (Contract 3) Contract 4 – Plumbing Construction (Contract 4)
4. Coordination
a. Project Coordinator shall be responsible for coordination among all Prime Contractors.
1) General Construction Contractor (“General Contractor”) shall act as the Project Coordinator and work closely with Franklin Township Construction Manager, COR Construction Services, Inc.
b. General Contractor
1) The General Contractor shall have coordination responsibility of all and each prime contractors. This shall include:
Franklin Township 3
a) Providing a master project schedule (“Master Project Schedule”) which includes each separate Prime Contractor’s scheduled responsibilities for delivery dates, installation, construction and critical activities for the Project.
b) Direct, schedule and control onsite activities of each separate Prime
Contractor.
c) Provide specific directions to each Prime Contractor when unforeseen interferences impact the progress of the work.
2) The General Contractor shall be experienced in administration and supervision of building construction, including the scheduling and coordination of plumbing, HVAC and electrical work.
3) The coordination activities of the General Contractor include, but are not limited to, the following:
a. Provide overall coordination of the Work.
b. Coordinate shared access to workspaces.
c. Coordinate product selections for compatibility.
d. Provide overall coordination of temporary facilities and controls.
e. Coordinate, schedule, and approve interruptions of permanent and temporary utilities, including those necessary to make connections for temporary services.
f. Coordinate construction and operations of the Work with work performed by each contract.
g. Prepare Coordination Drawings (if and as required) to coordinate work by more than one contract.
h. Coordinate sequencing and scheduling of the Work.
j. Provide quality-assurance and quality-control services.
k. Coordinate sequence of activities to accommodate tests and inspections, and coordinate schedule of tests and inspections with the testing laboratory.
l. Provide information necessary to adjust, move, or relocate existing utility structures affected by construction.
m. Set elevations provided by the Engineer. The General Contractor shall also be responsible for setting all corners, batterboards, off-set stakes and other construction lines from property lines or other reference points provided by the Engineer.
Franklin Township 4
n. Provide waste collection and progress cleaning of common areas and coordinate waste collection, recycling and progress cleaning of areas or pieces of equipment where more than one contractor has worked.
o. Coordinate cutting and patching of all the Work.
p. Coordinate protection of the Work.
q. Coordinate preparation of Project Record Documents; all information from all contractors is to be integrated to form one combined record set.
r. Print and submit Record CAD Drawings if installations by more than one contractor are indicated on the same Contract Drawing or Shop Drawing.
s. Collect Record Specification Sections from other contractors, collate Sections into numeric order, and submit one complete set.
t. Coordinate preparation of operation and maintenance manuals; all information from all contractors is to be integrated to form one combined record set.
c. Prime Contractors
1) Each Prime Contractor shall be responsible to the General Contractor to coordinate that Prime Contractor’s onsite activities. This includes submission of detailed information relating to the scheduling activities of material procurement, delivery dates, installation timeframes and notification of required work to be completed by other Prime Contractors prior to the installation of each Prime Contractor’s work.
2) All onsite interferences with other trades shall be coordinated with the
General Contractor. Unforeseen conditions that may arise and necessitate a Construction Change Directive shall be conveyed to the Engineer but shall be coordinated with the General Contractor.
3) The General Contractor shall be experienced in administration and supervision of building of building construction, including the scheduling and coordination of mechanical, plumbing and electrical work.
5. Schedules
a. Pre-Award Information
The apparent low bidder for each Prime Contract shall, within ten (10) working days following notification of its status as apparent low bidder, provide the Engineer with an intended schedule for work to be completed. The Engineer shall transmit the information to the apparent General Contractor low bidder.
Franklin Township 5
b. Master Project Schedule
Within ten (10) working days following receipt of the information set forth in subsection a. above, the apparent low bidder for the General Construction Contract shall provide the Engineer with a Master Project Schedule which incorporates the schedules of the other Prime Contractors and which Master Project Schedule shall be controlling on all of the Prime Contractors thereafter.
Upon receipt, the Engineer shall provide a copy of the Master Project Schedule to each Prime Contractor along with the Notice of Award. No changes or deviations from the Master Project Schedule shall be permitted without approval from the Engineer and, if the change or deviation involves an extension in the time for completing the required Work, a written change order or directive as the case may be.
c. Form of Schedule
The Master Project Schedule shall be a critical path schedule in such form as is approved by the Engineer.
d. Failure to adhere to the Master Project Schedule by any Prime Contractor shall be considered a default of that Prime Contractor.
6. All Prime Contracts
a. Extent of Contract
Unless the Contract Documents contain a more specific description of the Work, names and terminology on Drawings and in Specification Sections determine which contract includes a specific element of Project.
1) All Work described in this Section for each contract shall be complete systems and assemblies, including products, components, accessories, and installation required by the Contract Documents.
2) Local custom and trade-union jurisdictional settlements do not control the scope of the Work of each contract. When a potential jurisdictional dispute or similar interruption of work is first identified or threatened, affected contractors shall negotiate a reasonable settlement to avoid or minimize interruption and delays.
3) Trenches for the Work of each contract shall be coordinated with and provided by the General Contractor unless otherwise specified (electrical service). See General Contractor specification for trenching specifications.
4) Selective demolition for the work of each contract shall be coordinated with the General Contractor and shall be provided by each Prime Contractor for its own work.
Franklin Township 6
5) Cutting and patching for the Work of each contract shall be coordinated with the General Contractor and shall be provided by each Prime Contractor for its own Work.
6) Firestopping for the Work of each contract shall be coordinated with the General Contractor and shall be provided by each Prime Contractor for its own Work.
b. Substitutions
Each contractor shall cooperate with other contractors involved to coordinate approved substitutions with remainder of the Work.
c. Temporary Facilities and Controls
Each Prime Contractor is responsible as follows:
1) Access to the Construction Site Access for all Prime Contractors to the Project site is the responsibility of the General Contractor, which shall construct and maintain temporary roads as necessary. Temporary roads shall be adequate to permit the entrance and egress of construction and supply vehicles of all contractors at all times during the construction period. No contractor/worker, or any subcontractor or supplier shall be permitted to use the existing driveways or any portion of the existing parking facilities without the approval of the Engineer.
2) Temporary Services
Each Prime Contractor is specifically responsible for the installation, operations, maintenance and removal of each temporary service or facility, usually recognized as related to that contractor’s normal scope of work.
3) Use/Utility Charges
a) General
All utility charges for temporary facilities shall be paid for by the General Contractor. The Owner will not assume responsibility for any utility costs until the Certificate of Completion has been issued for the Project.
Use charges (i.e., tapping fees, 3∅ power) will be paid by the Owner.
b) Sanitary Sewer Service
There shall be no discharge into the existing sanitary sewer system without prior written authorization by the Engineer.
c) Water Service
Cost of all metered water service used by each Prime Contractor shall be the responsibility of the General Contractor.
Franklin Township 7
For Franklin Township facility construction, water can be provided by the Township from the existing service line at the Township Office for low volume service, at the discretion of the Township. Township reserves the right to halt provision of water at its discretion.
d) Electrical Power Service
The cost for all temporary electric power service at the Project Site by all Prime Contractors shall be the responsibility of the General Contractor.
For Franklin Township facility construction, electricity can be provided by the Township from the existing service line at the Township building or alternate location for general service, at the discretion of the Township. Township reserves the right to halt provision of electricity at its discretion.
e) Utility Extensions
The cost of extending utilities to and on the Project Site shall be as is otherwise set forth in the plans and specifications.
f) Security and Protection Facilities The General Contractor shall be responsible for installing temporary enclosures around partially completed areas of construction and provide lockable entrances to prevent unauthorized entrance, vandalism, theft and similar violations of security. Each Prime Contractor shall be responsible for securing that contractor’s own equipment and materials.
In the event of loss, the Owner shall not be responsible. Each Prime Contractor shall be responsible to secure the Project work area at the end of each workday.
d. Right of Property
No Prime Contractor shall have any right in any property or materials taken from any excavation and no earth, sand or other material from the Site shall be removed before any fill operations, except with the approval of the Engineer. The provisions of this paragraph shall not be construed to relieve any Prime Contractor of any of its obligations to remove and dispose of any excavated material with or without re-handling at its cost and expense as otherwise provided in the specifications.
e. Concrete Mix Computations
In addition to the requirements of the specification “Concrete Construction,” the Contractor shall employ a testing laboratory to prepare computations of the concrete mixes to be used, and submit the computations to the Engineer for approval. Such approval will not relieve the Contractor of responsibility of the mixes.
Franklin Township 8
f. Minimum Wage Rates
The applicable Pennsylvania prevailing wage determination for this Project are attached to the Contract Documents and shall be complied with in accordance with the instructions to bidders.
g. Painting Work by Others
All pipe, conduit, equipment installed under the Electrical Prime Contract (Contract
3) shall be painted by the General Contractor (Contract 1). Colors shall be as directed by the Engineer.
h. Safety and Health Regulations
Each Prime Contractor shall comply with the Department of Labor, Safety and Health Administration Regulations for construction promulgated under the Occupational, Safety and Health Act of 1970 (P.L. 91-596) and under Section 107 of the Contract Hours and Safety Act (P.L. 91-54).
i. Miscellaneous
1) Vehicle Removal and Barricades
Removal of vehicles, barricading and other operations necessary for the completion of the required work for each Prime Contractor is the responsibility of that Contractor.
2) Designated Representative
Each Prime Contractor shall provide at least one responsible worker to answer emergency calls on a 24-hour basis and perform emergency service during non-working hours for any condition resulting from that Prime Contractor’s construction activities which may present a hazard to the Project or to the public. This worker shall make himself available at any time of the day or night and any day of the week for any required emergency work and shall have available a proper vehicle, supplies and materials together with such authority as is required from the Prime Contractor to adequately perform his duties hereunder. If a contractor is notified of a deficiency which is not corrected within two hours from the time of notification, then the Owner may initiate repairs and the responsible Prime Contractor will be back charged.
3) Changes in the Project
Any changes in the Project which involve cost adjustments shall be only in accordance with the change order procedures otherwise set forth in the General Conditions.
Franklin Township 9
4) Payments
Payments to each Prime Contractor shall be in accordance with payment applications as otherwise set forth in the general conditions and shall be in accordance with a lump sum contract price.
5) Time for Completion and Liquidated Damages
The responsibility to perform the Work in each Prime Contract shall commence upon the date each Standard Form of Agreement is entered and shall continue until completion. Substantial Completion for each Prime Contract shall be 10 calendar months from the date of the execution of the Standard Form of Agreement. No delays will be permitted unless a change order granting an extension of time is issued and approved by the Owner.
The parties recognize that the Owner will incur damages if the Project is not completed within the 10-month period and also recognize that these damages shall be difficult to ascertain or quantify. After reasonable investigation and consideration, and by executing the Contract, each Prime Contractor agrees that $1,000 per day is a best effort estimate for damages resulting from delay in Substantial Completion as to each Prime Contract.
The Prime Contractors also agree that any damages resulting from failure to perform and complete the Work under each Prime Contract shall result in additional damages as are otherwise permitted to the Owner under applicable Pennsylvania law and which shall include additional engineering fees, inspection work and any other damages which are properly recoverable.
6) Insurance
Each Prime Contractor shall provide evidence of coverage of insurances as required under the General Conditions.
7) Indemnification
Each Prime Contractor shall indemnify and hold harmless the Owner, the Engineer and their respective agents and employees from and against all claims, damages, losses and expenses, including attorney’s fees arising out of or resulting from the performance of that Prime Contractor’s Work, providing that any such claim, damage, loss or expense is:
a) attributable to bodily injury, sickness, disease or death or to injury to or destruction of tangible property including the loss of use resulting therefrom.
b) caused in whole or in part by any intentional or negligent act or omission of a Prime Contractor, its employees, subcontractors, suppliers or materialmen or anyone directly or indirectly employed
Franklin Township 10 by any of them or anyone for whose acts may be liable, regardless of whether or not it is caused in part by anyone indemnified hereunder.
c) in any and all claims against the Owner or any of its agents or employees by any employee of any Prime Contractor, any subcontractor, supplier or materialmen of any of them, the indemnification obligation under this section shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor under workman’s compensation acts, disability acts or other employee’s benefit acts.
8) Operation and Maintenance Manuals
Each Prime Contractor shall collect two sets of catalog data including instructions for operations and care of all equipment, diagram, drawings, etc. for all pieces of equipment furnished under that Prime Contractor’s contract. The data shall be submitted to the General Contractor who shall reduce it into a single notebook form and suitably indexed. In addition to the data provided herein, the information contained shall include any and all manufacturer or supplier warranties which are issued pursuant to the required Work under the Contract. The General Contractor shall cause the same to be delivered to the Engineer prior to the release of final payment.
This record shall also include the plan location and elevation of all underground piping and utilities and shall include “as built” buildings.
7. General Construction Contract
a. Work in the General Construction Contract includes, but is not limited to, the following:
1) Site preparation, including cleaning and relocations and earthwork.
2) Site improvements, including site development furnishings and equipment, final grading, apply 4” minimum topsoil for seeding, and final seeding/restoration as to all Prime Contract disturbances.
3) Stormwater inlets, piping, stone and all components to install the required stormwater management system.
4) Sanitary sewer lateral from oil/water separator to existing lateral.
5) Water supply lateral from existing supply to new building.
6) Tunnels and trenching for site utilities.
7) Foundations, including footings, foundation walls.
Franklin Township 11
8) Slabs-on-grade, including earthwork, subdrainage systems, and insulation.
9) Paving and concrete as depicted on the plan for the site.
10) Permanent Signs installation .
11) Concrete Bollards, Wheel Stops, and Concrete Bin Blocks and installation
12) Below-grade building construction, including excavation, backfill, and thermal and moisture protection.
13) Superstructure, including roof construction.
14) Exterior closure, including walls, parapets, doors, windows and louvers.
15) Roofing, including coverings, flashings, roof specialties and openings.
16) Interior construction, including partitions, doors, interior windows, and fittings.
17) Interior finishes.
18) Furnishings, including casework (no furniture or appliances).
b. Temporary facilities and controls in the General Construction Contract include, but are not limited to, the following:
1) Temporary facilities and controls that are not otherwise specifically assigned to the Plumbing Contract, HVAC/Mechanical Contract or Electrical Contract.
2) Unpiped sewers and drainage, including drainage ditches, dry wells, stabilization ponds, and containers. There shall be no discharge into the sanitary sewer system without prior written authorization by the Owner.
3) Stormwater control, including the following:
a. Erosion and sediment controls
b. Foundation drainage system.
c. Site drainage system.
4) Unpiped portable or temporary toilet fixtures, wash facilities, and drinking water facilities, including disposable supplies.
5) Temporary enclosure for building exterior, except as indicated.
6) Dewatering facilities and drains.
7) General hoisting facilities for materials and personnel.
Franklin Township 12
8) Project identification and temporary signs as shall be designed and paid for by the General Construction Contractor.
9) General waste recycling and disposal facilities.
10) Temporary fire-protection equipment.
11) Security enclosure and lockup.
12) Traffic Control
13) Environmental protection.
14) Restoration of Owner's existing utilities (water and electric)
15) Soil stabilization; sedimentation and erosion control.
16) Temporary office facilities
17) Temporary heat and ventilation for new and existing facilities.
c. Miscellaneous
1) The General Contractor shall be responsible for determining the exact location of all utilities on the site and shall protect the utilities during the course of the work performed by all Prime Contractors. Notwithstanding, each Prime Contractor, shall at the discretion of the utility involved, repair or have repaired all damage to any utility which the result of the work of that Prime Contractor at no cost to the Owner. Each Prime Contractor is required to comply with all provisions of Act 287 of the Commonwealth of Pennsylvania effective April 9, 1975.
2) Safety of the General Public. The General Contractor shall be responsible for the safety of the general public in or about the site at all times. All excavated areas shall be backfilled daily or roped off with lighted barricading.
3) The General Contractor is responsible for the obtaining of all necessary permits (i.e., building permit, excavation permit, etc.) from Franklin Township, York County or any governmental body having legal jurisdiction over the same. The cost of all permits (excluding permit fees due Franklin Township, which shall be waived) shall be included in the bid price of the General Contractor.
8. Plumbing Contract
a. Work in the Plumbing Contract includes, but is not limited to, the following:
Franklin Township 13
1) Site water supply and distribution.
2) Site sanitary sewer.
3) Site special plumbing systems.
4) Plumbing fixtures.
5) Domestic water distribution.
6) Sanitary waste.
7) Plumbing connections to equipment furnished by the General Construction
Contract, Plumbing Contract, HVAC/Mechanical Contract and Electrical Contract.
b. Temporary facilities and controls in the Plumbing Contract include, but are not limited to, the following:
1) Piped water service.
2) Plumbing connections to existing systems and temporary facilities and controls furnished by the General Construction Contract, Plumbing Contract, HVAC/ Mechanical Contract and Electrical Contract.
9. HVAC/Mechanical Contract
a. Work in the HVAC/Mechanical Contract includes, but is not limited to, the following:
1) Heat generation.
2) Refrigeration.
3) HVAC distribution.
4) Terminal and packaged units.
5) HVAC instrumentation and controls.
6) HVAC testing, adjusting, and balancing.
7) Mechanical connections to equipment furnished by the General
Construction Contract, Plumbing Contract, HVAC/Mechanical Contract and Electrical Contract.
10. Electrical Contract
a. Work in the Electrical Contract includes, but is not limited to, the following:
Franklin Township 14
1) Site electrical distribution (See site drawings).
2) Site lighting.
3) Electrical service and distribution.
4) Lighting and branch wiring.
5) Telecommunications, security, computer wiring and audio-visual wiring.
Equipment will be supplied by others.
8) Electrical connections to equipment furnished by the General Construction
Contract, Plumbing Contract, HVAC/Mechanical Contract and Electrical Contract.
b. Temporary facilities and controls in the Electrical Contract include, but are not limited to, the following:
1) Electric power service and distribution.
2) Lighting, including site lighting.
3) Electrical connections to existing systems and temporary facilities and controls furnished by the General Construction Contract, Plumbing Contract, HVAC/ Mechanical Contract and Electrical Contract.
11. Separate Contracts
Any additional separate contracts will be secured by the Owner. Coordinate work prior to completion of rooms and final work. The following work will be provided by the Owner:
a. Telephone and Data System Equipment
b. Security System Equipment
c. Furniture
12. Progress of the Work
a. All scheduling and sequencing of the Construction Work shall be coordinated with the Owner.
b. It is essential that the Contractors communicate on this job. A list of Contractors will be supplied by the Engineer prior to the start of work. The Contractors are directed to check on the progress of each contract to maintain a smooth flow of trades through the duration of the project. The General Construction Contractor (Contract
1) shall act as the project coordinator. The Owner and Engineer will not be responsible for changes or rework necessary due to lack of coordination between Contractors.
Franklin Township 15
Upon award of the project, the General Contractor (Contract 1) shall arrange and conduct a sequencing and scheduling meeting with all contracts. Prior to construction, a master project schedule shall be submitted to the Township for review and approval.
13. Subsurface Conditions
From investigations, including surveys made at the site, it is assumed that physical conditions are approximate, as indicated on the drawings, but the nature of the materials below the surface or the depth to satisfactory foundations, are not guaranteed. No additional compensation shall be paid for rock or any other subsurface condition. The Contractors expressly assumes the risk of any unexpected subsurface condition. No boring has been performed.
14. Non-Classified Excavation
All excavation shall be unclassified. The Contractors are hereby advised that where rock is encountered within the lines and grades shown on the drawings or described by the specifications for lump sum items on the contract proposal, removal of same will be paid for as a part of the applicable lump sum price bid and no extra compensation will be made therefore.
15. Project Photographs
Prior to construction, the General Contractor shall furnish three (3) sets of photographs of the site from four (4) views. During construction, the Contractor shall provide three (3) sets of detailed project photographs each month during construction. Copies of the photographs shall be supplied to the Engineer with pay applications.
16. Cleaning
a. General
1) Description
a) Throughout the construction period, maintain the renovation area in a standard of cleanliness as described in this Section.
b) Owner requires that this project generate the least amount of trash and waste possible. All Contractors shall comply with Section 017419 Construction Waste Management and Disposal.
2) Quality Assurance
c) Conduct daily inspections and more often, if necessary, to verify that requirements for cleanliness are being met.
Franklin Township 16
d) In addition to the standards described in this Section, comply with pertinent requirements of governmental agencies having jurisdiction.
b. Products
1) Cleaning Materials and Equipment
Provide required personnel, equipment and materials needed to maintain the specified standard of cleanliness for a clean and neat site.
2) Compatibility
Use only the cleaning materials and equipment which are compatible with the surface being cleaned, as recommended by the manufacturer of the material.
c. Execution
1) Progress Cleaning
a) General
(1) Retain stored items in an orderly arrangement allowing maximum access, not impeding traffic and providing required protection of materials.
(2) Do not allow accumulation of scrap, debris, waste material and other items not required for construction of this work.
(3) At least once each week, and more often if necessary, completely remove all scrap, debris and waste material from the job site.
(4) Provide adequate storage for all items awaiting removal from the job site, observing requirements for fire protection and protection of the environment.
b) Building
(1) At the end of each day’s work, inspect the building and pick up all scrap, debris and waste material. Remove such items to the place designated for their storage.
(2) At the end of each day’s work, sweep interior spaces clean; free from dust and other material capable of being removed by use of reasonable effort and a handheld broom.
Franklin Township 17
(3) As required preparatory to installation of succeeding materials, clean the building or pertinent portions thereof to the degree of cleanliness recommended by the manufacturer of the succeeding material, using equipment and materials required to achieve the necessary cleanliness.
(4) Following the installation of finish floor materials, the finish floor shall be kept clean and protected at all times while work is being performed in the space in which finish materials are installed; free from foreign material which may be injurious to the finish floor material.
2) Final Cleaning
a) Final cleaning shall be provided by skilled cleaners using commercial quality building maintenance equipment and materials.
b) Prior to completion of the work, remove from the buildings job site all tools, surplus materials, equipment, scrap, debris, and waste. Conduct final progress cleaning as described in Article C.1 above.
c) Building
(1) Exterior
(a) Remove all traces of soil, waste materials, smudges and other foreign matter from exterior surfaces.
b) In the event of stubborn stains not removable with water, the Architect may require other additional cleaning at no additional cost to the Owner.
(2) Interior
(a) Remove all traces of soil, waste materials, smudges and other foreign matter from interior surfaces.
(b) Remove all traces of splashed material from adjacent surfaces.
(c) Remove paint droppings, spots, stains and dirt from finished surfaces.
(3) Polished Surfaces
To surfaces requiring routine application of buffed polish, apply the polish recommended by the manufacturer of the material being polished.
Franklin Township 18
d) Schedule final cleaning as approved by the Engineer to enable the
Owner to accept a completely clean facility.
e) Final acceptance of the building is contingent on approval of final cleaning.
3) Cleaning During Partial Occupancy
Should the Owner occupy the work of any portion thereof prior to its completion by the Contractor and acceptance by the Owner, responsibilities for interim and final cleaning shall be as determined by the Engineer.
B. SAFETY OF GENERAL PUBLIC
The Contractor shall be responsible for the safety of the general public in or about the project site at all times. Excavated areas shall be backfilled daily or roped off with lighted barricading. Entrances to driveways and adjoining residents shall have sound steel plating or wood planking of uniform thickness, with handrails and adequate lighting across excavated areas to provide for a safe travel way to each residence. Notification to adjoining residents is to be given by the Contractor within a reasonable time to facilitate their arrival or departure from the residence. Notification to the Township Board of Supervisors shall be given prior to any traffic restrictions, detours or road closings for coordination purposes.
C. CONTRACT DRAWINGS AND SPECIFICATIONS
The plan copies or drawings of this project, prepared by Gibson-Thomas Engineering Co., Inc., KD3 Design Studio, Inc., and Shamenek Engineering, LLC, are included in these contract documents and on PennBID are hereby made an integral part of these contract Documents and Specifications. One set of the Contractor's drawings and Specifications shall be available at the job site at all times for use by the Engineer or his authorized representative.
D. PAYMENT OF PREVAILING WAGES
The Contractor must compensate all employees associated with this project in accordance with the prevailing wage determinations made a part of these contract documents. The prevailing wage information must be displayed at a high-visibility site located in the contract work area. Pennsylvania Prevailing Wages apply to this project.
E. PRE-CONSTRUCTION CONFERENCE
A pre-construction conference will be held with all Prime Contractors, the Construction Manager, and the Engineer prior to the commencement of the project.
Franklin Township 19
F. CONSTRUCTION STAKE-OUT
The contractor will be furnished with all benchmarks and field information from the original survey notes. The contractor will be responsible for the stakeout of all construction work included in this contract. This work shall be subject to the approval of the Engineer.
G. TEMPORARY SERVICES
It shall be the responsibility of the General Contractor to provide temporary services throughout the entire period of construction and until the work performed under his contract is completed and the placed in operation with the Owner's personnel. The temporary services shall include heat and water, as follows:
a. Temporary Heat
The General Contractor shall operate portable heaters or maintain a temporary heating system. The General Contractor shall pay all costs including fuel for the operation and maintenance of the equipment, either temporary or permanent, to provide adequate heat. Facilities shall be maintained at a minimum temperature of 65° F except when a lower temperature is authorized by the Engineer. The General Contractor shall remove all soot, smudges and other deposits from walls and all exposed surfaces which are the result of the use of any temporary heating equipment including the use of the permanent heating system for temporary heat purposes. He shall not do any finish work until all such surfaces are properly cleaned. The General Contractor shall be responsible for the dismantling and/or removal of portable heaters and other temporary heating apparatus and equipment.
H. COORDINATION OF WORK – ALL CONTRACTS
It is essential that the Contractors communicate on this job. A list of Contractors will be supplied to the Construction Manager and the Engineer prior to the start of work. The Contractors are directed to check on the progress of each contract to maintain a smooth flow of trades throughout the duration of the project. The Owner, Construction Manager, and Engineer will not be responsible for changes or rework necessary due to lack of coordination between Contractors.
END OF SECTION