This document is Exhibit E: Milestones & Deliverables for RFP SCC-26-030-BOI, a cloud-based hosted solution for the Commonwealth of Virginia's Board of Insurance (BOI) to support insurance regulatory, administrative, and payment processing functions. The RFP requires offerors to identify and describe proposed implementation milestones, key activities, deliverables, and a comprehensive implementation schedule. The solution must be implemented and services commenced prior to June 30, 2028. Offerors must submit responses to Exhibit E as part of their proposal, including a proposed implementation schedule that demonstrates their approach to successful, on-time delivery. The schedule should balance rapid implementation with cost effectiveness and efficiency in design, development, testing, and implementation phases. Offerors may include diagrams, charts, tables, and other visual content to support their response, and any proposed changes to SCC-provided language must be submitted separately in Appendix D rather than as redline edits in Exhibit E.
The deliverables matrix identifies 18 required deliverables spanning implementation and operations and maintenance (O&M) phases, including project management plans, integrated project schedules, staffing plans, requirements traceability matrices, solution design documents, data management plans, testing and defect management plans, training materials, system security and privacy plans, operations and maintenance support plans, deployment and go-live plans, implementation closeout reports, SOC 2 reports, transition and turnover plans, disaster recovery plans, and business continuity plans. Most planning deliverables must be completed within 60 days of the effective date, while technical deliverables such as solution design documents, testing plans, and security plans are due prior to testing initiation and go-live. The document provides specific acceptance criteria for each deliverable, emphasizing SCC approval requirements and ongoing maintenance or annual updates during the O&M phase.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1a RFP SCC-26-030-BOI Cover Page.docx | DOCX document | |
| 11 RFP SCC-26-030-BOI Exhibit F Pricing.xlsx | XLSX spreadsheet | |
| 0 Attachment A - BOI Information & Payment Processing System Current State Overview.docx | DOCX document | |
| 12 RFP SCC-26-030-BOI Exhibit G Subcontracting Plan.docx | DOCX document | |
| 00 RFP SCC-26-030-BOI BOI Information & Payment Processing System.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP SCC-26-030-BOI: BOI Information & Payment Processing System Exhibit E: Milestones & Deliverables
RFP SCC-26-030-BOI
BOI Information & Payment Processing System
Exhibit E: Milestones & Deliverables
< Insert Offeror Name >
Table of Contents
| 1.0 | Instructions | 3 |
| 2.0 | Implementation Milestones | 3 |
| 3.0 | Deliverables | 4 |
| 3.1 | Deliverables Matrix | 5 |
| 4.0 | Proposed Implementation Schedule | 11 |
Instructions Offeror must provide a response to Exhibit E: Milestones & Deliverables with their proposal. Exhibit E requires that Offeror provide responses to specific items, including the identification and description of implementation milestones, Offeror’s approach to the development and completion of deliverables, a proposed implementation schedule, and a proposed implementation plan. Diagrams, charts, tables, and other visual content may be included as part of the response to aid the SCC in understanding Offeror’s proposed solution.
Any changes Offeror wishes to propose to SCC-provided language and content in Exhibit E must be provided separately in Offeror’s response to Appendix D – Proposed Changes. Proposed changes and redline edits made by Offeror directly in Exhibit E will not be considered.
Implementation Milestones Based on Offeror’s knowledge and experience and the information provided in this RFP, Offeror must identify and describe the proposed milestones upon which implementation activities and deliverables will be based. Table 1 – Proposed Implementation Milestones below provides a template that should be used by Offeror to describe the implementation milestones it proposes. Each milestone must also indicate the key activities that must be completed, and the deliverables listed in Table 2 – Deliverables Matrix that Offeror proposes be tied to be each milestone. The activities and deliverables associated with each milestone will serve as key inputs to the acceptance criteria for each milestone. The milestones presented in this table should align with the milestones provided by Offeror in Exhibit F – Pricing.
| Milestone Title |
| Description |
| Timing |
| Key Activities |
| Associated Deliverables |
Table 1 – Proposed Implementation Milestones
Deliverables Supplier is required to complete and provide to the SCC the deliverables contained in Exhibit B: Solution Requirements, which are described in Table 2 – Deliverables Matrix below. The Deliverables Matrix provides a description, timing, recurrence, phase, and acceptance criteria for of each deliverable.
Offerors should review the Deliverables Matrix in detail to ensure understanding and alignment with the SCC’s expectations and needs. Any changes that Offeror proposes to the content of the Deliverables Matrix should be submitted to the SCC in the appropriate form in Offeror’s response to Appendix D: Proposed Changes. Proposed changes and redline edits provided by Offeror directly in the Deliverables Matrix will not be considered.
RFP SCC-26-030-BOI: BOI Information & Payment Processing System Exhibit E: Milestones & Deliverables
Deliverables Matrix
| # |
| Deliverable |
| Description |
| Approx. Timing |
| Implemen-tation Phase |
| O&M Phase |
| Frequency of Recurrence |
| Acceptance Criteria |
| 1 |
| Project Management Plan (PMP) |
| Describes the formal project management methodology (e.g. PMI PMBOK) that will be used and the approach to supporting the SCC-defined project governance structure. Provides details regarding the approach, tools, and documentation used for the management of scope, schedule, risk, quality, change control, communications, stakeholder engagement, and other relevant topics. Delineates project management and project governance roles and responsibilities. |
| Within 60 days following Effective Date |
| X |
| X |
| Implementation: N/A |
O&M: As requested (not a formal deliverable)
· The PMP clearly addresses the items included in the deliverable description.
· Templates and tools that will be used to support execution of the PMP have been fully developed.
· The PMP has been approved by SCC.
| 2 |
| Integrated Project Schedule |
| Provides both summary-level and detailed information regarding project milestones, activities, and deliverables using written and visual elements. Includes the following items, at a minimum: |
· A summary-level schedule that contains project phases and major milestones for key components of the solution.
· A detailed schedule that contains:
· Project phases, milestones, activities, and deliverables required to deliver all components of the proposed solution within the solution timeline indicated above.
· Start date, end date, and estimated duration of each phase, milestone, activity, and deliverable.
· Internal and external dependencies between project phases, milestones, activities, and deliverables.
| Within 60 days following Effective Date |
| X |
| X |
| Implementation: N/A |
(Note: this is a one-time deliverable that must be updated bi-weekly during Implementation) O&M: as agreed upon for Solution enhancements and changes
· All defined phases, milestones, activities, and deliverables are represented in the schedule.
· The schedule is accompanied by clearly articulated assumptions.
· The schedule is available and accessible on the online project management tool.
· The Integrated Project Schedule has been approved by SCC.
| 3 |
| Staffing Plan |
| Describes the approach to staffing for each phase of the contract. Includes, at a minimum: |
· Implementation Phase organization structure and how that organization interacts with all stakeholders.
· Key Personnel assigned with clearly defined roles and responsibilities.
· O&M Phase organization structure, with staffing levels and roles and responsibilities described by job title/function.
· Discloses the planned use of companies not owned by the contractor and/or individuals not employed by the contractor to perform functions during solution Implementation and O&M, and the functions these entities will perform.
· Describes retention strategies to minimize the impact of personnel changes during the course of the implementation.
· Describes recruitment strategies and processes to rapidly address any staffing gaps or deficiencies during the course of the implementation.
| Within 60 days following Effective Date |
| X |
| X |
| Implementation: N/A |
O&M: As requested or as needed to reflect resource, team, or access changes
· The plan clearly addresses the items included in the deliverable description.
· The Staffing Plan has been approved by SCC.
| 4 |
| Requirements Traceability Matrix (RTM) |
| Provides traceability of requirements contained in the RFP to the Supplier’s solution. Includes a log of all changes to requirements. Describes how the functionality and features of the solution satisfy each individual requirement. |
The RTM will be updated, maintained, and made available to the SCC on an on-going basis during both Implementation and O&M phases.
During the early stages of Solution Design;
Updated prior to Go-Live
| X |
| X |
| Implementation: Updated prior to go-live |
O&M: Annually
· All requirements have been formally reviewed and approved by SCC.
· All requirements have been accepted by the Supplier.
· All changes to requirements have been documented and traceability is intact.
· Requirements are available and accessible to all parties.
· A requirements management and change control process, along with associated tools, has been developed and approved by SCC.
· The RTM has been approved by SCC.
| 5 |
| Solution Design Documents |
| Provides both high-level and detailed solution design information, which may be accomplished using multiple design documents. Includes design information related technological and operational elements of the solution, such as solution functionality, features, modules, architecture, data, interfaces, integrations, workflows, business rules, business processes, procedures, report, software, middleware, infrastructure, security, etc. |
| Prior to initiation of Testing activities |
| X |
| X |
| Implementation: N/A |
O&M: As needed to reflect changes to the solution
· System design documents clearly address the items included in the deliverable description.
· System design documents have undergone SCC Enterprise Architecture Review when appropriate.
· System design documents have undergone SCC information security review when appropriate.
· Additional criteria will be defined during contract negotiations to ensure alignment with the Supplier’s approach, methodology, and capabilities.
· Solution Design Documents have been approved by SCC.
| 6 |
| Data Management Plan |
| Describes how data will be managed, accessed, used, shared, stored, and protected. Specifies the data management strategy and approach by data type (e.g., project data, consumer data, test data, production data, etc.) and by project phase (e.g., Implementation, O&M). |
In addition, the data management plan must identify and provide:
· Master data and metadata definitions.
· End-to-end data model for all business processes, workflows, interfaces, reports, and operational specifications.
· Data archiving and data retention plans.
· Database management and administration standards and practices.
· Offeror’s plans to ensure that data management plans and procedures meet all federal and state data protection and security policies.
| During Solution Design |
| X |
Implementation: N/A O&M: N/A
· The plan clearly addresses the items included in the deliverable description.
· The plan has undergone SCC information security review.
· Additional criteria will be defined during contract negotiations to ensure alignment with the Supplier’s solution.
· The Data Management Plan has been approved by SCC.
| 7 |
| Testing Plan |
| Describes the approach, methodology, and activities for conducting testing of all technological and operational components of the MCIS, to include unit testing, integration testing, performance testing, regression testing, data testing, and User Acceptance Testing (UAT). Describes the success criteria and standards for all forms of testing. |
| During Solution Design |
| X |
Implementation: N/A O&M: N/A
· Clear entrance and exit criteria have been defined for each phase of testing.
· Testing roles and responsibility have been agreed to.
· The Testing schedule has been agreed to.
· The Testing Plan has been approved by SCC.
| 8 |
| Defect Management Plan |
| Describes the approach, methodology, and activities for identifying, documenting, analyzing, resolving, testing, and closing defects in the MCIS. Addresses defects related to solution functionality, data, and other elements. Describes the tiers for defects based on severity and priority, and the criteria for resolving and closing defects. |
| During Solution Design |
| X |
Implementation: N/A O&M: N/A
· A defect management methodology has been defined and agreed to.
· All supporting tools and processes have been developed and approved.
· The Defect Management Plan has been approved by SCC.
| 9 |
| Training Plan |
| Describes the approach, methodology, and activities for developing and delivering a training program for the various user groups of MCIS. Includes face-to-face training, webinar based training, online training, and recurring training for SCC staff and other external parties. |
| Prior to initiation of end user training activities |
| X |
Implementation: N/A O&M: N/A
· Clear entrance and exit criteria have been defined for training.
· Training roles and responsibility have been agreed to.
· The Training schedule has been agreed to.
· The Training Plan has been approved by SCC.
| 10 |
| Training Materials & Delivery |
| Includes the training materials that have been developed for each specific user group based on the unique needs of each group. |
| Prior to initiation of end user training activities |
| X |
| X |
| Implementation: N/A |
O&M: As needed to reflect system enhancements and changes, operational changes, and other solution changes that impact users
· An inventory of Training Materials has been developed.
· Training Materials targeted to each user group have been developed and approved.
· All Training entrance and exit criteria have been satisfied and documented.
· All user groups have completed training courses to SCC’s satisfaction.
· SCC has signed off on Training Materials and Delivery.
| 11 |
| System Security & Privacy Plan |
| Provides the security and privacy requirements of the system and describes the controls in place or planned for meeting those requirements. More specifically, the System Security & Privacy Plan addresses the following, at a minimum: |
· Describes security requirements and the management, operational, and technical controls to address those requirements. Security requirements and controls should include input from key stakeholders.
· Describes controls for protecting the security and privacy of sensitive data, particularly PHI/PII.
· Identifies improvements needed for the protection of information system resources.
· Describes roles and responsibilities for all elements of system security.
· Describes expected behavior of all users who access the system and the controls in place to ensure the integrity of the system and data.
Provides processes and procedures to meet security requirements and maintain controls.
| Prior to Solution Go-Live |
| X |
| X |
| Implementation: N/A |
O&M: Annually
· The Systems Security & Privacy Plan clearly addresses the items included in the deliverable description.
· All supporting procedures, tools, templates, etc. have been developed and signed off by SCC.
· The Systems Security & Privacy Plan has been approved by SCC.
· The Information Exchange Security Agreement is executed (if required).
| 12 |
| Operations & Maintenance and End User Support Plan |
| Describes the processes, procedures, tools, and other details for providing on-going O&M and end user support following go-live of the solution. |
| Prior to Solution Go-Live |
| X |
| X |
| Implementation: N/A |
O&M: As needed to reflect changes to O&M and end user support
· The Operations & Maintenance and End User Support Plan clearly addresses the items included in the deliverable description.
· All supporting procedures, tools, templates, etc. have been developed and signed off by SCC.
· The Operations & Maintenance and End User Support Plan has been approved by SCC.
| 13 |
| Solution Deployment, Go-Live and Acceptance Plan |
| Provides a step-by-step plan for the deployment and go-live of the solution. Describes the roles and responsibilities of all parties and stakeholders. Describes the criteria that will be used in evaluating deployment and go-live activities and in receiving the SCC’s formal acceptance of the deployed solution. |
| Prior to completion of UAT |
| X |
Implementation: N/A O&M: N/A
· A step-by-step deployment plan has been developed.
· Clear deployment and go-live entrance and exit criteria have been defined.
· Clear solution acceptance criteria have been documented.
· The Solution Deployment, Go-Live and Acceptance Plan has been approved by SCC.
| 14 |
| Implementation Phase Closeout Report |
| Provides a detailed disposition of all solution components and functionality following implementation and go-live. Documents any agreements between the SCC and the Supplier related to non-critical functionality that is being performed through workarounds and the action plans to achieve full functionality. Formally closes the Implementation Phase once accepted. |
| Within 1 month following Solution Go-Live |
| X |
Implementation: Monthly until acceptance of Solution O&M: N/A
· The Report clearly addresses the items included in the deliverable description.
· All open items related to the Implementation Phase have been addressed and documented with SCC’s approval.
· The Implementation Phase Closeout Report has been approved by SCC.
| 15 |
| System & Organization (SOC) 2 Report |
| Provides the formal results of SOC 2 Type 2 audits performed on the security, availability, processing integrity, confidentiality, and privacy of the solution. Describes the specific criteria used in the SOC 2 audits; the extent to which the solution meets the defined criteria; audit findings; and corrective action plans to address audit findings. |
| Prior to Solution Go-Live |
| X |
| X |
| Implementation: N/A |
O&M: Annually
· The SOC 2 Report clearly addresses the items included in the deliverable description.
· The SOC 2 Report has been demonstrably conducted by a qualified, independent third party.
· Remediation plans for all SOC 2 Report findings have been developed and approved by SCC.
· The SOC 2 Report has been approved by SCC.
| 16 |
| Transition Out & Turnover Plan |
| Documents the approach and process for the transition and turnover to the SCC or its designee of the responsibilities, duties, activities, and functions performed by the Supplier in supporting the MCIS. Describes the approach to transitioning work, knowledge, assets, and employees, as appropriate, from Supplier. Describes the approach to governance, oversight, communications, risk management, and security and privacy during the transition. Indicates the criteria that will be used to determine successful turnover. |
| Within 60 days of Solution Go-Live |
| X |
| Implementation: N/A |
O&M: As needed to reflect changes to transition out and turnover plans
· The Transition Out & Turnover Plan clearly addresses the items included in the deliverable description.
· All supporting procedures, tools, templates, etc. have been developed and signed off by SCC.
· Clear entrance and exit criteria have been defined for each major step in the transition and turnover process.
· The Transition Out & Turnover Plan has been approved by SCC.
| 17 |
| Disaster Recovery Plan (DRP) |
| Defines the approach and steps for recovery of technology components of the MCIS following a disaster. Provides contingency plans that are specific to various types of disasters, such as natural disasters, infrastructure failures, etc. |
The DRP must include, at a minimum:
· Procedures for the identification and declaration of a disaster.
· Procedures for communicating with stakeholders.
· Procedures for the orderly recovery of the solution and resumption of system availability.
· Back-up and protection procedures to include files, software, hardware and network connectivity.
· Description of any proposed alternate site(s), including a detailed schedule for back-up operations and any proposed clustering methodology for high availability.
· Recovery time objectives.
· Recovery point objectives.
· Risk analysis and risk mitigation for each business process.
· Processes and procedures for DRP testing and reporting the results of testing, to include failover/fallback functionality, back-up/recovery functionality, business continuity, and plan updates.
| Prior to Solution Go-Live |
| X |
| X |
| Implementation: N/A |
O&M: Annually
· The DRP clearly addresses the items included in the deliverable description.
· DRP processes, procedures, and roles and responsibilities have been clearly documented and signed off.
· DRP tests and exercises have been defined, documented, and planned.
· The DRP has been approved by SCC.
| 18 |
| Business Continuity Plan (BCP) |
| Defines the approach and steps for the recovery of business functions, business units, business processes, human resources, and operational components of the MCIS. |
The BCP must include, at a minimum:
· Documented and prioritized business functions.
· Enablers and systems that support each business function.
· Resources and supplies needed for each business function.
· Prioritized, step-by-step procedures for the recovery of business functions.
· Communication plans and procedures.
· Delegations of authority and decision-making processes.
· Processes and procedures for BCP testing and reporting the results of testing.
| Prior to Solution Go-Live |
| X |
| X |
| Implementation: N/A |
O&M: Annually
· The BCP clearly addresses the items included in the deliverable description.
· BCP processes, procedures, and roles and responsibilities have been clearly documented and signed off.
· BCP tests and exercises have been defined, documented, and planned.
· The BCP has been approved by SCC.
Table 2 – Deliverables Matrix
| RFP 2221 – Virginia Health Benefit Exchange Solution | Exhibit E: Milestones & Deliverables | |
| RFP SCC-26-030-BOI: BOI Information & Payment Processing System | Exhibit E: Milestones & Deliverables |
Proposed Implementation Schedule Offeror must provide with their response a proposed Implementation Schedule that incorporates and builds on the solution timeline, key milestones, and deliverables addressed in the preceding sections of this Exhibit. The proposed implementation schedule must clearly demonstrate Offeror’s approach to ensuring a successful, on-time delivery of the solution. The schedule should also provide the best possible balance between rapid implementation, cost effectiveness, and efficiency in the design, development, testing, and implementation of the solution. The solution should be implemented and services Commenced prior to June 30, 2028.
For the purposes of Offeror’s response to this RFP, the proposed implementation schedule should provide a “big-picture” perspective with sufficient detail to enable understanding of the timing, sequence, inter-relationships, and dependencies between key elements of the schedule. However, a full implementation schedule that includes detailed tasks and sub-tasks is neither required nor expected at this stage. A detailed Integrated Project Schedule deliverable will be developed by Supplier during the early stage of the Implementation Phase.
Offeror’s proposed implementation schedule should include the following, at a minimum, which should be prepared using a combination of visual and written elements:
· Phases
· Milestones
· Key Activities
· Deliverables
· Key Interdependencies
· Major Assumptions
· Major Risks
· Strategies to ensure successful, on-time implementation of the solution relative to:
· Other potential challenges or obstacles, based on Offeror’s experience, that could adversely impact the implementation timeline if not managed effectively.
The following page is provided for Offeror use in displaying the proposed implementation schedule, if needed.
| RFP 2221 – Virginia Health Benefit Exchange Solution | Exhibit E: Milestones & Deliverables | |
| RFP SCC-26-030-BOI: BOI Information & Payment Processing System | Exhibit E: Milestones & Deliverables |
< Page for Offeror use in displaying the proposed implementation schedule, if needed. Delete if not used. > image1.png