10-LNAA-CO-26-002 Part III, Technical Specifications.pdf
PDF 2 MB Posted
- Attached to
- Cooling Tower Replacement
- Solicitation number
- US.258403
- Issued by
- Lehigh County, Pennsylvania
About this file
This is a Technical Specifications document for a multiple prime contract cooling tower replacement project at Lehigh Valley International Airport (ABE) in Allentown, Pennsylvania, issued by the Lehigh Northampton Airport Authority. The project involves replacement of an existing cooling tower, removal and replacement of a cooling tower screen wall, structural repair to the existing mechanical penthouse, replacement of mechanical penthouse doors and louvers, and replacement of an existing IT room split system. The work is divided into three separate bid contracts: General Construction, Mechanical Construction, and Electrical Construction, each to be awarded as a lump sum contract. A non-mandatory pre-bid meeting was scheduled for October 20, 2026, via Microsoft Teams. Questions regarding the request for proposals were due by 4:00 p.m. on October 27, 2026, via www.PennBid.net. Sealed proposals were required to be submitted by 2:00 p.m. on November 13, 2026, via www.PennBid.net, with public opening at the Lehigh Northampton Airport Authority Boardroom on the same date. All proposals remain valid for 120 days. The work must accommodate the owner's continued occupancy of the existing building during the entire construction period, with extreme care required to avoid impacts to ongoing airport operations.
The project imposes significant coordination and scheduling requirements on all contractors, including mandatory weekly on-site review meetings, daily toolbox safety talks, daily work reports, and adherence to airport-specific safety policies and FAA-mandated crane procedures. Contractors must submit detailed Critical Path Method schedules within 21 days of award and are responsible for all premium time required to meet schedule milestones, temporary facilities, site cleanup, hazardous materials handling, and off-shift and weekend work when necessary to minimize disruption to airport operations. The General Construction Contractor bears additional responsibility for building permits, temporary toilet facilities for all trades, and costs associated with the project's field office. Each contractor must provide updated insurance certificates and personnel lists as required. The specifications do not identify any specific set-asides, pricing terms, or contract funding sources within the technical specifications document itself; such information would be contained in the bid documents and contract award materials available through www.PennBid.net.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LNAA-CO-002 TECHNICAL PROVISIONS
Cooling Tower Replacement PART III: TECHNICAL SPECIFICATIONS at Lehigh Valley International Airport October 13, 2026
TS.1
TECHNICAL PROVISIONS
PART III
TECHNICAL SPECIFICATIONS
TS.2
SECTION 011200
MULTIPLE CONTRACT SUMMARY
PART 1 GENERAL
1.01 PROJECT
A. Project Name: Cooling Tower Replacement at Lehigh Valley International Airport (ABE) B. Owner's Name: Lehigh Northampton Airport Authority C. The Project generally consists of the following work items:
Replacement of existing cooling tower.
Removal and replacement of existing cooling tower screen wall.
Structural repair to existing mechanical penthouse.
Replacement of existing mechanical penthouse door and louver.
Replacement of existing IT room split system.
1.02 CONTRACT DESCRIPTION
A. Contract Type: Multiple Prime contracts to include:
Bid Contract One – General Construction.
Bid Contract Two – Mechanical Construction.
Bid Contract Three – Electrical Construction.
B. The work of the prime contracts is identified in this section.
1.03 DESIGN/MANAGEMENT IDENTIFICATION
A. OWNER or SPONSOR
Lehigh Northampton Airport Authority 3311 Airport Road Allentown, PA 18109
B. ENGINEER
McFarland Johnson, Inc.
49 Court Street Binghamton, NY 13901
C. ARCHITECT
KTH Architects, Inc.
1741 Kiwanis Trail Dubois, PA 15801
1.04 DESCRIPTION OF ALTERATIONS WORK
A. Scope of demolition, removal and construction work is shown on drawings and described in the technical specifications.
B. The project includes the items identified in Section 1.01C of this specification.
at Lehigh Valley International Airport October 13, 2026
TS.3
1.05 OWNER OCCUPANCY
A. Owner intends to continue to occupy the existing building during the entire construction period.
C. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.
D. Schedule the Work to accommodate Owner occupancy.
1.06 CONTRACTOR USE OF SITE AND PREMISES
A. Construction Operations: Limited to areas noted on Drawings.
B. Arrange use of site and premises to allow:
1. Owner occupancy.
2. Work by Others.
3. Use of site and premises by the public.
C. Provide access to and from site as required by law and by Owner:
1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permit.
D. Existing building spaces may not be used for storage.
E. Utility Outages and Shutdown:
1. Limit disruption of utility services to hours the building is unoccupied.
2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Owner and authorities having jurisdiction.
3. Limit shutdown of utility services to 8 hours at a time, arranged at least 24 hours in advance with Owner.
4. Prevent accidental disruption of utility services to other facilities.
1.07 WORK SEQUENCE
A. Work of all trades within the construction area shall occur at the same time with coordination taking place between the prime contractors.
B. Coordinate construction schedule and operations with Owner.
1.08 SPECIFICATION SECTIONS APPLICABLE TO ALL CONTRACTS
Unless otherwise noted, all provisions of the sections listed below apply to all contracts.
Specific items of work listed under individual contract descriptions constitute exceptions.
A. Section 011200 – Multiple Contract Summary
B. Section 012500 – Substitution Procedures
C. Section 012600 – Contract Modification Procedures
D. Section 013100 – Project Management and Coordination
E. Section 013300 – Submittal Procedures
F. Section 013516 – Alteration Project Procedures
G. Section 014000 – Quality Requirements at Lehigh Valley International Airport October 13, 2026
TS.4
H. Section 015000 – Temporary Facilities and Controls
I. Section 017700 – Closeout Procedures
J. Section 017839 – Project Record Documents
PART II – DIVISION OF WORK
1.09 BID CONTRACT ONE – GENERAL CONSTRUCTION
A. GENERAL
1. The work of this project is separated into a number of Bid Packages, of which Package "General Construction" is the portion of work belonging to this Contractor. The Contractor will provide a final lump sum cost proposal for the "General Construction" that will include the work defined herein.
a. General Construction
1) Provide the necessary materials, labor, equipment, and supervision to perform the "General Construction" work as indicated in the Division of Work of this Section.
2) Provide and utilize the necessary equipment to perform the work in a safe and expeditious manner.
b. Perform the work under lump sum contract with Owner. Furnish all labor, materials, tools, equipment, supervision, layout, delivery, trucking, shop drawings, submittals, as-built drawings, etc. necessary to complete the work described in Division of Work for this Contract, whether specified above or not.
2. The following requirements apply to all bid items and must be included in bidding any or all of the bid items.
a. All existing conditions must be verified in the field. The Owner takes no responsibility for actual conditions found deviating from the drawings. If existing condition interferes with Contract Work, Contractor is responsible to eliminate the condition.
B. DIVISION OF WORK
1. Furnish and install all labor, material, supervision, engineering, administration, project management, equipment, layout, deliveries, trucking, hoisting, supplies, mock-ups, rigging, shop drawings, submittals, and all other items related and required to complete all Work in accordance with the Contract Documents and all applicable codes, laws, and regulations having jurisdiction.
2. The Contractor represents they have expertise in the performance of work for this trade and assure all systems to be complete, functional, and installed in accordance with the best practices consistent with premium quality material and workmanship. The Scope of Work includes, but is not limited to the following:
a. All work shown and described in the following drawing Series of the drawing set titled “Cooling Tower Replacement”:
1) Structural (S-series drawings)
2) Architectural (A-series drawings)
b. All work required and described in the following Specification Sections:
1) Division 2 – Existing Conditions in its entirety.
2) Division 4 – Masonry in its entirety.
at Lehigh Valley International Airport October 13, 2026
TS.5
3) Division 5 – Metals in its entirety.
4) Division 7 – Thermal and Moisture Protection in its entirety.
5) Division 8 – Openings in its entirety.
6) Division 9 – Finishes in its entirety.
7) Division 10 – Specialties in its entirety.
c. The work associated with this contract involves working on and immediately adjacent to the airport, which will remain operational during the project.
Extreme care must be taken so that the existing airport operations are not impacted. Any work that may affect the current facility operations will need to be scheduled and approved prior to commencing work.
d. Extreme care is to be taken to avoid any unplanned interruptions to the existing facilities operations. Any work to be performed that may impact the operations of the facility will be done on a planned basis utilizing off-shift and weekend hours at the cost of Contractor.
e. All equipment and materials, fuel, oil, and repairs for equipment utilized in this scope of work.
f. Provide daily clean-up of work, staging areas, and private and public roads.
Place debris in containers provided by Contractor. Any hazardous debris shall be handled in strict accordance with all applicable laws and regulations by Contractor. Contractor must maintain a clean jobsite. Failure to maintain a clean jobsite may lead to a notice to remedy and potential back charges to cover costs incurred by others to perform cleanup efforts.
g. Contractor is responsible for all scaffolding, fall protection, hoisting, and any other labor, materials, or equipment necessary to complete this scope of work.
h. All labor and material to provide weather protection required to perform the work and protect the finished work within this scope.
i. Maintenance of all staging areas as it pertains to this scope of work.
j. Contractor must comply with all Airport and Contractor's own site-specific safety policies.
k. Contractor is responsible for all permits/inspections required to perform this scope of work.
l. Contractor is responsible for cleanup, trash removal, and cost of any hazardous materials, oil contaminated materials, spills, or leaks.
m. Contractor must protect their own work as well as the work of others when performing this scope of work.
n. Contractor will be required to correct all defective work as directed.
o. Contractor is responsible for adhering to all OSHA requirements for personal and job site safety pertaining to their specific scope of work.
p. Contractor will be required to submit a sequence and logistics plan for any activities and locations that may affect visibility of the existing apron, taxiways, runways, etc. for review and approval by the Airport and the FAA prior to the start of work.
q. The work in this contract is not limited to any particular drawings. All drawings should be reviewed to determine the scope of this contract.
at Lehigh Valley International Airport October 13, 2026
TS.6
r. Any dust control and street cleaning that may be required by the Contractor’s use of the site.
s. Contractor must comply with Airport site specific safety policies, including the project Construction Safety and Phasing Plan (CSPP). Contractor must complete, sign, and submit to the Engineer the Safety Plan Compliance Document (SPCD) prior to the issuance of the Notice to Proceed.
t. Contractor will be required to attend a pre-installation meeting as indicated in the project drawings and specifications or as required by the RPR.
u. Contractor is responsible for attending weekly project review meetings and others that may be deemed necessary. For this bid package, a weekly on-site review meeting will be necessary from award through completion of this contract’s work. Attendance is mandatory for the Contractor’s project manager and superintendent. Note that the Owner meetings in the Division 1 specifications are in addition to the weekly project review meetings.
v. Contractor will be required to supply a cellular phone for all onsite superintendents/foremen and project manager and will provide the RPR with the numbers.
w. Contractor is responsible to provide notification of any loads coming to or from the site which are permitted loads, over height, over length, over width, or over weight prior to leaving or arrival.
x. On-site storage for tools and materials will be provided by the Contractor. A Logistics plan for staging and storing will be developed between the Contractor and RPR. If the Contractor requires additional road access, lay down, or storage space beyond what is indicated on the Logistics drawings, it will be at their own expense.
y. Contractor shall provide all flagmen, traffic control, and coordinate deliveries around local peak traffic periods.
z. Contractor is required at all times to use the designated roads and gates when entering and exiting the jobsite.
aa. Contractor is required to make sure the Foreign Object Debris plans are followed and all materials are secure and not a threat to leave the project site.
ab. Contractor is responsible for maintaining all barricades and barriers per OSHA requirements as it pertains to this scope of work.
ac. All employees under this contract will be required to have a site-specific safety orientation prior to working on site. Contractor will conduct these sessions.
ae. Schedule milestones are provided for the purpose of bidding and for establishing a working schedule to meet the milestones. Schedule is a critical component of this project. Schedule milestones shall be strictly adhered to unless otherwise noted.
af. Contractor will be required to provide a detailed Critical Path Method schedule within 21 days of award that meets these milestones and provides coordination with other Contractors.
ag. Contractor is responsible for all premium time required to meet schedule milestones unless Owner receives in writing reasons that it should not be this contractor’s responsibility and such reasons are acceptable by Owner.
ah. Contractor is responsible for any costs incurred for off-site visits deemed necessary to verify quality/schedule of materials being produced off-site.
ai. Contractor will be responsible to repair any damage to site-specific erosion at Lehigh Valley International Airport October 13, 2026
TS.7
and sediment control measures as it relates to this contract.
aj. Contractor will provide all certified and calibrated test equipment as it relates to this scope of work.
ak. All water, electric, phone, data, costs for wiring, equipment, piping, etc., are the responsibility of each individual Contractor for construction trailer services unless specifically noted. General Construction Contractor is responsible for all costs associated with the RPR’s field office.
al. Building Permit and any special permits are the responsibility of the General Contractor.
am. Contractor will be required to periodically submit a list of on-site employees as directed by the RPR.
an. Contractor and their subcontractors are required to provide up-to-date Insurance Certificates before starting work on site. Contractor is required to provide updated certificates prior to expiration or cancellation of the previous certificate.
ao. Unless otherwise specifically noted, Contractor is to provide all cutting and patching to allow for the completion of their work. All patching must restore the original finish to as good or better condition.
ap. Contractor is required to hold daily toolbox safety talks and turn over a copy of the agenda each week to the RPR.
aq. Temporary toilet facilities will be provided by the “General Construction” Contractor for use by all other contractors. Contractor’s employees are not allowed to use the existing airport facilities. Contractor is to direct their employees that they are not to deface, litter in, or otherwise damage temporary toilet facilities.
ar. Contractor is required to submit daily work reports on a daily basis as directed. Daily work reports shall include Contractor’s number of personnel working on site that day, any Subcontractors working on site and number of personnel, work completed, any issues that prevented work from being completed as scheduled, equipment on site, etc.
as. Provide general snow removal, salting, sanding, deicing, etc. within the contract work and staging areas throughout the winter season(s). Snow removal to keep clear paths to office trailers, for general site access, for access to working areas for all trades, etc. as required to continue operations throughout winter. Salt shall not be used on or adjacent to airfield work areas.
at. Specification section 015000 Temporary Facilities and Controls specifies additional items to be provided by the Contractor, all of which are to be included within this scope of work.
au. Contractor is responsible to disconnect, drain, cap, and otherwise make safe for demolition all utilities.
av. Costs associated with installation and removal of any required crane, boring rig, or other pads are to be included in this scope of work.
aw. Contractor will be required to adhere to all FAA-mandated crane identification and operational procedures to ensure the safe and efficient travel of air traffic and aircraft navigational aids.
1.10 BID CONTRACT TWO – MECHANICAL CONSTRUCTION
A. GENERAL
1. The work of this project is separated into a number of Bid Packages, of which at Lehigh Valley International Airport October 13, 2026
TS.8
Package "Mechanical Construction" is the portion of work belonging to this Contractor. The Contractor will provide a final lump sum cost proposal for the "Mechanical Construction" that will include the work defined herein.
a. Mechanical Construction
1) Provide the necessary materials, labor, equipment, and supervision to perform the "Mechanical Construction" work as indicated in the Division of Work of this Section.
2) Provide and utilize the necessary equipment to perform the work in a safe and expeditious manner.
b. Perform the work under lump sum contract with Owner. Furnish all labor, materials, tools, equipment, supervision, layout, delivery, trucking, shop drawings, submittals, as-built drawings, etc. necessary to complete the work described in Division of Work for this Contract, whether specified above or not.
2. The following requirements apply to all bid items and must be included in bidding any or all of the bid items.
a. All existing conditions must be verified in the field. The Owner takes no responsibility for actual conditions found deviating from the drawings. If existing condition interferes with Contract Work, Contractor is responsible to eliminate the condition.
B. DIVISION OF WORK
1. Furnish and install all labor, material, supervision, engineering, administration, project management, equipment, layout, deliveries, trucking, hoisting, supplies, mock-ups, rigging, shop drawings, submittals, and all other items related and required to complete all Work in accordance with the Contract Documents and all applicable codes, laws, and regulations having jurisdiction.
2. The Contractor represents they have expertise in the performance of work for this trade and assure all systems to be complete, functional, and installed in accordance with the best practices consistent with premium quality material and workmanship. The Scope of Work includes, but is not limited to the following:
a. All work shown and described in the following drawing Series of the drawing set titled “Cooling Tower Replacement”:
1) Mechanical (M-series drawings)
b. All work required and described in the following Specification Sections:
1) Division 23 – Hating, Ventilating, and Air-Conditioning (HVAC) in its entirety.
c. The work associated with this contract involves working on and immediately adjacent to the airport, which will remain operational during the project.
Extreme care must be taken so that the existing airport operations are not impacted. Any work that may affect the current facility operations will need to be scheduled and approved prior to commencing work.
d. Extreme care is to be taken to avoid any unplanned interruptions to the existing facilities operations. Any work to be performed that may impact the operations of the facility will be done on a planned basis utilizing off-shift and weekend hours at the cost of Contractor.
e. All equipment and materials, fuel, oil, and repairs for equipment utilized in this scope of work.
f. Provide daily clean-up of work, staging areas, and private and public roads.
at Lehigh Valley International Airport October 13, 2026
TS.9
Place debris in containers provided by Contractor. Any hazardous debris shall be handled in strict accordance with all applicable laws and regulations by Contractor. Contractor must maintain a clean jobsite. Failure to maintain a clean jobsite may lead to a notice to remedy and potential back charges to cover costs incurred by others to perform cleanup efforts.
g. Contractor is responsible for all scaffolding, fall protection, hoisting, and any other labor, materials, or equipment necessary to complete this scope of work.
h. All labor and material to provide weather protection required to perform the work and protect the finished work within this scope.
i. Maintenance of all staging areas as it pertains to this scope of work.
j. Contractor must comply with all Airport and Contractor's own site-specific safety policies.
k. Contractor is responsible for all permits/inspections required to perform this scope of work.
l. Contractor is responsible for cleanup, trash removal, and cost of any hazardous materials, oil contaminated materials, spills, or leaks.
m. Contractor must protect their own work as well as the work of others when performing this scope of work.
n. Contractor will be required to correct all defective work as directed.
o. Contractor is responsible for adhering to all OSHA requirements for personal and job site safety pertaining to their specific scope of work.
p. Contractor will be required to submit a sequence and logistics plan for any activities and locations that may affect visibility of the existing apron, taxiways, runways, etc. for review and approval by the Airport and the FAA prior to the start of work.
q. All drawings should be reviewed to understand the full scope of work for this contract.
r. Any dust control and street cleaning that may be required by the Contractor’s use of the site.
s. Contractor must comply with Airport site specific safety policies, including the project Construction Safety and Phasing Plan (CSPP). Contractor must complete, sign, and submit to the Engineer the Safety Plan Compliance Document (SPCD) prior to the issuance of the Notice to Proceed.
t. Contractor will be required to attend a pre-installation meeting as indicated in the project drawings and specifications or as required by the RPR.
u. Contractor is responsible for attending weekly project review meetings and others that may be deemed necessary. For this bid package a weekly on-site review meeting will be necessary from award through completion of this contract’s work. Attendance is mandatory for the Contractor’s project manager and superintendent. Note that the bi-monthly Owner meetings in the Division 1 specifications are in addition to the weekly project review meetings.
v. Contractor will be required to supply a cellular phone for all onsite superintendents/foremen and project manager and will provide the RPR with the numbers.
w. Contractor is responsible to provide notification of any loads coming to or from the site which are permitted loads, over height, over length, over width, at Lehigh Valley International Airport October 13, 2026
TS.10
or over weight prior to leaving or arrival.
x. On-site storage for tools and materials will be provided by the Contractor. A
Logistics plan for staging and storing will be developed between the Contractor and RPR. If the Contractor requires additional road access, lay down, or storage space beyond what is indicated on the Logistics drawings, it will be at their own expense.
y. Contractor shall provide all flagmen, traffic control, and coordinate deliveries around local peak traffic periods as it relates to this scope of work.
z. Contractor is required at all times to use the designated roads and gates when entering and exiting the jobsite.
aa. Contractor is required to make sure the Foreign Object Debris plans are followed and all materials are secure and not a threat to leave the project site.
ab. Contractor is responsible for maintaining all barricades and barriers per OSHA requirements as it pertains to this scope of work.
ac. All employees under this contract will be required to have a site-specific safety orientation prior to working on site. Contractor will conduct these sessions.
ae. Schedule milestones are provided for the purpose of bidding and for establishing a working schedule to meet the milestones. Schedule is a critical component of this project. Schedule milestones shall be strictly adhered to unless otherwise noted.
af. Contractor will be required to provide a detailed Critical Path Method schedule within 21 days of award that meets these milestones and provides coordination with other Contractors.
ag. Contractor is responsible for all premium time required to meet schedule milestones unless Owner receives in writing reasons that it should not be this contractor’s responsibility and such reasons are acceptable by Owner.
ah. Contractor is responsible for any costs incurred for off-site visits deemed necessary to verify quality/schedule of materials being produced off-site.
ai. Contractor will be responsible to repair any damage to site-specific erosion and sediment control measures as it relates to this contract.
aj. Contractor will provide all certified and calibrated test equipment as it relates to this scope of work.
ak. All water, electric, phone, data, costs for wiring, equipment, piping, etc., are the responsibility of each individual Contractor for Contractor’s construction trailer services unless specifically noted. General Construction Contractor is responsible for all costs associated with the RPR’s field office.
al. The building permit will be provided by others. Any special permits are the responsibility of the Contractor.
am. Contractor will be required to periodically submit a list of on-site employees as directed.
an. Contractor and their subcontractors are required to provide up-to-date Insurance Certificates before starting work on site. Contractor is required to provide updated certificates prior to expiration or cancellation of the previous certificate.
ao. Unless otherwise specifically noted, Contractor is to provide all cutting and patching to allow for the completion of their work. All patching must restore the original finish to as good or better condition.
ap. Contractor is required to hold weekly toolbox safety talks and turn over a at Lehigh Valley International Airport October 13, 2026
TS.11
copy of the agenda each week to the RPR.
aq. Temporary toilet facilities will be provided by the General Construction
Contractor for use by all other contractors. Contractor’s employees are not allowed to use the existing airport facilities. Contractor is to direct their employees that they are not to deface, litter in, or otherwise damage temporary toilet facilities.
ar. Contractor is required to submit daily work reports on a daily basis as directed. Daily work reports shall include Contractor’s number of personnel working on site that day, any Subcontractors working on site and number of personnel, work completed, any issues that prevented work from being completed as scheduled, equipment on site, etc.
as. Specification section 015000 Temporary Facilities and Controls specifies additional items to be provided by the Contractor, all of which are to be included within this scope of work.
at. Costs associated with installation and removal of any required crane, boring rig, or other pads are to be included in this scope of work.
au. Contractor will be required to adhere to all FAA-mandated crane identification and operational procedures to ensure the safe and efficient travel of air traffic and aircraft navigational aids.
av. Coordination with “General Construction” Contractor for excavation and backfill of this scope.
aw. Provide temporary power stations throughout temporary building for all trades and connection and disconnection of specialty equipment for other trades such as welders.
ax. Provide temporary lighting and removal to meet all OSHA requirements and provide sufficient light for completion of work by all trades.
ay. Sub-metering for all temporary electric used during construction.
az. Coordination with all other Contractors for electrical requirements to all equipment. This Contractor will be responsible for correcting power and data rough-ins in the event the proper coordination is not completed.
1.10 BID CONTRACT THREE – ELECTRICAL CONSTRUCTION
A. GENERAL
1. The work of this project is separated into a number of Bid Packages, of which Package "Electrical Construction" is the portion of work belonging to this Contractor. The Contractor will provide a final lump sum cost proposal for the "Electrical Construction" that will include the work defined herein.
a. Electrical Construction
1) Provide the necessary materials, labor, equipment, and supervision to perform the "Electrical Construction" work as indicated in the Division of Work of this Section.
2) Provide and utilize the necessary equipment to perform the work in a safe and expeditious manner.
b. Perform the work under lump sum contract with Owner. Furnish all labor, materials, tools, equipment, supervision, layout, delivery, trucking, shop drawings, submittals, as-built drawings, etc. necessary to complete the work described in Division of Work for this Contract, whether specified above or not.
2. The following requirements apply to all bid items and must be included in bidding at Lehigh Valley International Airport October 13, 2026
TS.12
any or all of the bid items.
a. All existing conditions must be verified in the field. The Owner takes no responsibility for actual conditions found deviating from the drawings. If existing condition interferes with Contract Work, Contractor is responsible to eliminate the condition.
B. DIVISION OF WORK
1. Furnish and install all labor, material, supervision, engineering, administration, project management, equipment, layout, deliveries, trucking, hoisting, supplies, mock-ups, rigging, shop drawings, submittals, and all other items related and required to complete all Work in accordance with the Contract Documents and all applicable codes, laws, and regulations having jurisdiction.
2. The Contractor represents they have expertise in the performance of work for this trade and assure all systems to be complete, functional, and installed in accordance with the best practices consistent with premium quality material and workmanship. The Scope of Work includes, but is not limited to the following:
a. All work shown and described in the following drawing Series of the drawing set titled “Installation of New Passenger Boarding Bridge”:
1) Electrical (E-series drawings)
b. All work required and described in the following Specification Sections:
1) Division 26 – Electrical in its entirety.
c. The work associated with this contract involves working on and immediately adjacent to the airport, which will remain operational during the project.
Extreme care must be taken so that the existing airport operations are not impacted. Any work that may affect the current facility operations will need to be scheduled and approved prior to commencing work.
d. Extreme care is to be taken to avoid any unplanned interruptions to the existing facilities operations. Any work to be performed that may impact the operations of the facility will be done on a planned basis utilizing off-shift and weekend hours at the cost of Contractor.
e. All equipment and materials, fuel, oil, and repairs for equipment utilized in this scope of work.
f. Provide daily clean-up of work, staging areas, and private and public roads.
Place debris in containers provided by Contractor. Any hazardous debris shall be handled in strict accordance with all applicable laws and regulations by Contractor. Contractor must maintain a clean jobsite. Failure to maintain a clean jobsite may lead to a notice to remedy and potential back charges to cover costs incurred by others to perform cleanup efforts.
g. Contractor is responsible for all scaffolding, fall protection, hoisting, and any other labor, materials, or equipment necessary to complete this scope of work.
h. All labor and material to provide weather protection required to perform the work and protect the finished work within this scope.
i. Maintenance of all staging areas as it pertains to this scope of work.
j. Contractor must comply with all Airport and Contractor's own site-specific safety policies.
k. Contractor is responsible for all permits/inspections required to perform this scope of work.
l. Contractor is responsible for cleanup, trash removal, and cost of any at Lehigh Valley International Airport October 13, 2026
TS.13
hazardous materials, oil contaminated materials, spills, or leaks.
m. Contractor must protect their own work as well as the work of others when performing this scope of work.
n. Contractor will be required to correct all defective work as directed.
o. Contractor is responsible for adhering to all OSHA requirements for personal and job site safety pertaining to their specific scope of work.
p. Contractor will be required to submit a sequence and logistics plan for any activities and locations that may affect visibility of the existing apron, taxiways, runways, etc. for review and approval by the Airport and the FAA prior to the start of work.
q. All drawings should be reviewed to understand the full scope of work for this contract.
r. Any dust control and street cleaning that may be required by the Contractor’s use of the site.
s. Contractor must comply with Airport site specific safety policies, including the project Construction Safety and Phasing Plan (CSPP). Contractor must complete, sign, and submit to the Engineer the Safety Plan Compliance Document (SPCD) prior to the issuance of the Notice to Proceed.
t. Contractor will be required to attend a pre-installation meeting as indicated in the project drawings and specifications or as required by the RPR.
u. Contractor is responsible for attending weekly project review meetings and others that may be deemed necessary. For this bid package a weekly on-site review meeting will be necessary from award through completion of this contract’s work. Attendance is mandatory for the Contractor’s project manager and superintendent. Note that the bi-monthly Owner meetings in the Division 1 specifications are in addition to the weekly project review meetings.
v. Contractor will be required to supply a cellular phone for all onsite superintendents/foremen and project manager and will provide the RPR with the numbers.
w. Contractor is responsible to provide notification of any loads coming to or from the site which are permitted loads, over height, over length, over width, or over weight prior to leaving or arrival.
x. On-site storage for tools and materials will be provided by the Contractor. A Logistics plan for staging and storing will be developed between the Contractor and RPR. If the Contractor requires additional road access, lay down, or storage space beyond what is indicated on the Logistics drawings, it will be at their own expense.
y. Contractor shall provide all flagmen, traffic control, and coordinate deliveries around local peak traffic periods as it relates to this scope of work.
z. Contractor is required at all times to use the designated roads and gates when entering and exiting the jobsite.
aa. Contractor is required to make sure the Foreign Object Debris plans are followed and all materials are secure and not a threat to leave the project site.
ab. Contractor is responsible for maintaining all barricades and barriers per OSHA requirements as it pertains to this scope of work.
at Lehigh Valley International Airport October 13, 2026
TS.14
ac. All employees under this contract will be required to have a site-specific safety orientation prior to working on site. Contractor will conduct these sessions.
ae. Schedule milestones are provided for the purpose of bidding and for establishing a working schedule to meet the milestones. Schedule is a critical component of this project. Schedule milestones shall be strictly adhered to unless otherwise noted.
af. Contractor will be required to provide a detailed Critical Path Method schedule within 21 days of award that meets these milestones and provides coordination with other Contractors.
ag. Contractor is responsible for all premium time required to meet schedule milestones unless Owner receives in writing reasons that it should not be this contractor’s responsibility and such reasons are acceptable by Owner.
ah. Contractor is responsible for any costs incurred for off-site visits deemed necessary to verify quality/schedule of materials being produced off-site.
ai. Contractor will be responsible to repair any damage to site-specific erosion and sediment control measures as it relates to this contract.
aj. Contractor will provide all certified and calibrated test equipment as it relates to this scope of work.
ak. All water, electric, phone, data, costs for wiring, equipment, piping, etc., are the responsibility of each individual Contractor for Contractor’s construction trailer services unless specifically noted. General Construction Contractor is responsible for all costs associated with the RPR’s field office.
al. The building permit will be provided by others. Any special permits are the responsibility of the Contractor.
am. Contractor will be required to periodically submit a list of on-site employees as directed.
an. Contractor and their subcontractors are required to provide up-to-date Insurance Certificates before starting work on site. Contractor is required to provide updated certificates prior to expiration or cancellation of the previous certificate.
ao. Unless otherwise specifically noted, Contractor is to provide all cutting and patching to allow for the completion of their work. All patching must restore the original finish to as good or better condition.
ap. Contractor is required to hold weekly toolbox safety talks and turn over a copy of the agenda each week to the RPR.
aq. Temporary toilet facilities will be provided by the General Construction Contractor for use by all other contractors. Contractor’s employees are not allowed to use the existing airport facilities. Contractor is to direct their employees that they are not to deface, litter in, or otherwise damage temporary toilet facilities.
ar. Contractor is required to submit daily work reports on a daily basis as directed. Daily work reports shall include Contractor’s number of personnel working on site that day, any Subcontractors working on site and number of personnel, work completed, any issues that prevented work from being completed as scheduled, equipment on site, etc.
as. Specification section 015000 Temporary Facilities and Controls specifies additional items to be provided by the Contractor, all of which are to be included within this scope of work.
at Lehigh Valley International Airport October 13, 2026
TS.15
at. Costs associated with installation and removal of any required crane, boring rig, or other pads are to be included in this scope of work.
au. Contractor will be required to adhere to all FAA-mandated crane identification and operational procedures to ensure the safe and efficient travel of air traffic and aircraft navigational aids.
av. Coordination with “General Construction” Contractor for excavation and backfill of this scope.
aw. Provide temporary power stations throughout temporary building for all trades and connection and disconnection of specialty equipment for other trades such as welders.
ax. Provide temporary lighting and removal to meet all OSHA requirements and provide sufficient light for completion of work by all trades.
ay. Sub-metering for all temporary electric used during construction.
az. Coordination with all other Contractors for electrical requirements to all equipment. This Contractor will be responsible for correcting power and data rough-ins in the event the proper coordination is not completed.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
END OF SECTION 011000
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 0013300 "SUBMITTAL PROCEDURES" for products submittals.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory at Lehigh Valley International Airport October 13, 2026
TS.16
changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use facsimile of form provided in Project Manual.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.
h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.
j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate at Lehigh Valley International Airport October 13, 2026
TS.17
for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor, through the Engineer of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or
Architect's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
1.7 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is at Lehigh Valley International Airport October 13, 2026
TS.18
uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Not allowed.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 012500
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Architect will issue, through the Engineer, supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on a standard form.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Architect and/or Engineer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Architect and Engineer are not instructions either to stop work in progress or to execute the proposed change.
2. Within 15 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
TS.19
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
e. Quotation Form: Use standard form.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to the Architect and Engineer.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use form acceptable to Architect and Engineer.
1.5 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Change Proposal Request, the Engineer will issue a Change Order for signatures of Owner and Contractor on standard form.
1.6 FIELD WORK DIRECTIVE
A. Field Work Directive: Architect and/or Engineer may issue a Field Work Directive on a standard form. Field Work Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Field Work Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum at Lehigh Valley International Airport October 13, 2026
TS.20
or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
END OF SECTION 012600
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Section includes administrative provisions for coordinating construction operations on
Project, including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Web-based Project management software package.
6. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
C. Related Requirements:
1. Section 011200 "Multiple Contract Summary" for a description of the division of work among separate contracts and…