1-LNAA-CO-26-002 Part I, General Project Information.pdf

PDF 381 KB Posted

Attached to
Cooling Tower Replacement
Solicitation number
US.258403
Issued by
Lehigh County, Pennsylvania

About this file

Summary

This is a technical provisions document for a construction contract issued by the Lehigh-Northampton Airport Authority (LNAA) for the Cooling Tower Replacement project at Lehigh Valley International Airport in Allentown, Pennsylvania. The project involves the one-for-one replacement of an existing roof-mounted cooling tower, replacement of the associated screen wall system, repairs to the existing rooftop mechanical penthouse (including man door replacement and wall louver removal), and replacement of an existing IT room air conditioning split system. The work is divided into three separate contracts: Contract 1 (General Contractor) for screen wall and penthouse modifications; Contract 2 (Mechanical Contractor) for cooling tower and IT room HVAC replacement; and Contract 3 (Electrical Contractor) for electrical disconnection/reconnection and lightning protection system replacement. A non-mandatory pre-bid conference will be held virtually on Tuesday, October 20, 2026, at 1:00 PM, with site inspections available by appointment only for pre-bid attendees. Questions must be submitted by 4:00 PM on Tuesday, October 27, 2026, via www.PennBid.net. Sealed bids are due by 2:00 PM on Friday, November 13, 2026, via www.PennBid.net, with public bid opening at 2:00 PM the same day at the Airport Authority Boardroom. The contract duration is 60 calendar days from the issuance of the Construction Notice to Proceed (CNTP), with award anticipated within 120 calendar days of bid opening.

Bidders must provide a certified check or bid bond equal to 10% of the total proposal price and, if awarded, a performance bond or irrevocable letter of credit equal to 100% of the proposal amount. Wage rates are required for bids exceeding $25,000 per the Pennsylvania Prevailing Wage Act of 1961. The contractor must achieve a minimum 50% self-performance goal and comply with all non-discrimination and affirmative action requirements under federal and state law, including Title VI of the Civil Rights Act of 1964, the Americans with Disabilities Act, and Pennsylvania's nondiscrimination provisions. Liquidated damages are assessed at $1,000 per calendar day for failure to substantially complete each phase or the overall project within specified durations, with an additional $250 per hour for any unauthorized service interruptions (power, communication, FAA, water, or sanitary). Special requirements include night/off-hours crane work coordinated with the Authority, Airport Security ID badging for key personnel, adherence to AC 150/5370-2 and FAR Part 77 regulations, and coordination with concurrent projects including roof replacement, parking garage structure work, and roadway rehabilitation. All contractors must obtain necessary permits and licenses at their own expense and maintain compliance with Airport Authority Rules and Regulations throughout the project.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL PROVISIONS

BID SUBMISSION

STANDARD PROCUREMENT

LNAA-CO-26-002

Cooling Tower Replacement

If indicated below (√) and not waived by the Authority, Bidders shall be required to provide the following:

√ A Bid Bond, in the amount of ten (10%) percent of the bid amount for construction contracts See “Bid Bonds – Section GP3.01” of the General Provisions for Bidding of Construction Contracts.

√ A Performance Bond for 100% of bid award on construction contracts and on contracts for services, supplies, or construction related services. See “Bid Bonds – Section GP3.01” of the General Provisions for Bidding of Construction Contracts.

Prepared by:

McFarland Johnson

LEHIGH-NORTHAMPTON AIRPORT AUTHORITY

LEHIGH VALLEY INTERNATIONAL AIRPORT

4th Edition July, 2026

LNAA-CO-26-002 TECHNICAL PROVISIONS

Cooling Tower Replacement PART I: GENERAL PROJECT INFORMATION at Lehigh Valley International Airport 10/13/2026

GI.2

TABLE OF CONTENTS

LNAA-CO-26-002

Part I General Project Information .......................................................................... GI.1 thru GI.15

Part II General Provisions for Bidding of Construction Contracts…………………...GP.1thru GP.32

Part III Technical Specifications Over TOC - (General Requirements – Division 1) ...... TS.1-TS.269

Part IV Prevailing Wage Rates (17 Total Pages) .............................................. PWR.1 thru PWR.17

Part V Airport Authority Documents (77 Total Pages) ........................................ AAD.1 thru AAD.88

Part VI Agreement Between Airport Authority and Contractor…….. .......... …………SA.1 thru SA.16

Part VII Bid Book ........................................................................................................ BF.1 thru BF.16 at Lehigh Valley International Airport 10/13/2026

GI.3

PART I

General Project Information at Lehigh Valley International Airport 10/13/2026

GI.4

PART I

GENERAL PROJECT INFORMATION

LNAA-CO-26-002

GI-1.01 Contract Summary GI-1.02 Notice to Contractors GI-1.04 Description of Project GI-1.05 Special Construction Requirements GI-1.05.1 Phasing GI-1.05.2 Time Restrictions GI-1.05.3 Badging Process/Restrictions GI-1.05.4 Deliveries/Haul Route GI-1.05.5 Site Restrictions GI-1.05.6 Access to the Site GI-1.05.7 Staging Area GI-1.05.8 Load & Height Restrictions GI-1.05.9 Permits, Licensing, and Crane Height Restrictions GI-1.05.10 Contract Duration GI-1.05.11 Liquidated Damages GI-1.05.12 Project Coordination GI-1.05.13 Shop Drawings GI-1.05.14 Designated Subcontractors at Lehigh Valley International Airport 10/13/2026

GI.5

GI-1.01 Contract Summary

ITEM DESCRIPTION

Contract Title Cooling Tower Replacement

Contract Number LNAA-CO-26-002

AIP Contract Number N/A

Applicable Standard Provisions Standard Provisions, 2nd Edition, February 2022

Contractor Self-Performance Goal 50 %

Wage Rates Required* YES X NO

Project Location

ABE X

Queen City

Braden

Contract Drawings and Technical Provisions Cost N/A

Contract Duration 60 Calendar Days

Liquidated Damages See Section GI-1.05.11

Pre-Bid Conference

Tuesday, October 20, 2026 Virtual Conference Call at 1:00 PM Local Time

Invitation information to follow

Site Inspection Schedule with Ryan Rockovits by emailing rrockovits@flyabe.com

Questions Due Tuesday, October 27 ,2026 at 4:00 PM via www.PennBid.net

Bids Due Friday, November 13, 2026, no later than 2:00 PM via www.PennBid.net

Bid Opening Friday, November 13, 2026, no later than 2:00 PM. 2nd Floor, Main Terminal, Boardroom

*Wage Rates are required for bids in excess of $25,000 per the Pennsylvania Prevailing Wage Act of 1961) mailto:rrockovits@flyabe.com http://www.pennbid.net/ at Lehigh Valley International Airport 10/13/2026

GI.6

GI-1.02 Notice to Contractors

The Standard Provisions for Construction Contracts and the Technical Provisions are intended to describe and establish all requirements and standards for this construction Contract and shall be binding upon the parties’ signatory to the Contract. By submitting a bid for this Contract, the Contractor agrees to adhere to the requirements of all these Provisions. Lehigh-Northampton Airport Authority shall henceforth also be referred to as “The Airport Authority” or “LNAA”.

Sealed bids for the project entitled:

At

Lehigh-Valley International Airport

Construction Contract No. LNAA-CO- 26-002

Sealed bids will be received online via www.PennBid.net by:

Friday, November 13, 2026 at 2:00 PM Local Time

Positively no bids will be accepted after November 13, 2026 at 2:00 PM Local Time

Interested bidders need to register at the PennBid website. Once registered, bidders can obtain all project documents and submit and update their bids online.

The proposals require a Certified Check or Bid Bond in the amount of ten percent (10%) of the total proposal price. Such proposal security shall be made payable to “Lehigh-Northampton Airport Authority” as a guarantee of good faith and is to secure the Lehigh-Northampton Airport Authority from any loss by failure to comply with any of the terms of the proposal, and is to become the property of the Lehigh-Northampton Airport Authority as just and liquidated damages in case the successful bidder refuses or fails to enter into such contract or fails or refuses to furnish a performance bond within twenty (20) days of the award. The Airport Authority has the right at its sole discretion to reject any or all bids. The award of each bid package, if it is to be awarded, shall be made within ninety (120) calendar days of the date specified for publicly opening proposals, unless otherwise specified herein. Award of each bid package shall be made by LNAA to the lowest, qualified bidder whose proposal conforms to the cited requirements of LNAA for each individual bid package. Bidders are not required to bid on all bid packages;

however, they are required to bid on all items in each bid package submitted. Where discrepancies in the unit bid prices occur, and where discrepancies in the product of the quantities and unit bid prices occur, and where discrepancies in the summation of the products occur, LNAA will make the necessary corrections and the corrected values will be used in LNAA’s consideration of proposals.

http://www.pennbid.net/ at Lehigh Valley International Airport 10/13/2026

GI.7

The successful bidder will be required to provide performance security in forms satisfactory to the Authority Solicitor consisting of either a performance bond or irrevocable letter of credit in the amount of 100% of the proposal. The Proposer shall be responsible for obtaining and maintaining the performance security in force from the date of execution until the date of the contract termination. All Bonds shall be secured by a guaranty or Surety Company listed in the latest edition of U.S. Treasury Circular 570, and the bond amount must be within the maximum amount specified for such company in Circular 570.

The work under this contract includes, but is not limited to the one-for-one replacement of an existing roof-mounted cooling tower and replacement of the associated screen wall system. Repairs to the existing roof top mechanical penthouse including man door replacement, removal of existing wall louver, and structural repairs are also included.

Additionally, the replacement of an existing IT room air conditioning split system is to be provided. See paragraph GI-1.04 for additional description.

Plans, Specifications and other contract documents may be secured electronically through the PennBid website.

A NON-MANDATORY Pre-Bid Virtual Conference Call will be held:

Tuesday, October 20, 2026, at 1:00 PM Local Time

Please Note: Only attendees attending the pre-bid will be allowed to schedule by appointment only a Site Inspection.

Your scheduled Site Inspection will be the only time to inspect the site. Please bring valid identification, either a driver’s license or passport.

Attendance at the Pre-Bid Conference and the Site Inspection is NOT mandatory.

Appropriate auxiliary aids and service for qualified individuals with disabilities will be provided upon request. Please call the Airport Authority Offices at least five business days in advance of the meeting. See PennBid for meeting login information.

GI-1.03 Non-Discrimination and Affirmative Action

The Bidder agrees, unless exempt, to comply with any applicable federal regulation pertaining to nondiscrimination and affirmative action (generally Part 60-1 of Title 41 of the Code of Federal Regulations), but not limited to the Equal Opportunity Clause (41 C.F.R. Paragraph 60-1.4). which is incorporated by reference, the Affirmative Action Clause for Handicapped Workers (41 C.F.R. Paragraph 60-741.4) which is incorporated by reference, and the Americans with Disabilities Act, 42 U.S.C., Section 12101 et seq.

and the applicable Federal regulations. Bidder further agrees, unless exempt, to comply with the Pennsylvania Nondiscrimination Clause (16 Pennsylvania Code Paragraph

49.101 (D), which is incorporated by reference. Pursuant to the provisions of Act No. 222, October 27, 1955, as amended by Act No. 19, February 28, 1961, and in accordance with at Lehigh Valley International Airport 10/13/2026

GI.8

the provisions of the Governor's Code of Fair Practice, effective June 6, 1963, and the Regulations of the Pennsylvania Human Relations Commission, as approved by the Public Works Project will contain the following items:

A. Bidder agrees that it will comply with the provisions of the Pennsylvania Human Relations Act in providing equal employment opportunities in connection with all work performed by the Bidder or any subcontractor or supplier at the job site pursuant to the Contract.

B. Bidder agrees that it will comply with the Non-Discrimination Policy of the Authority which provides that in the performance of the Contract, the Bidder will provide equal opportunity for all citizens regardless of race, color, religion, sex, sexual orientation, gender, gender expression, gender identity, national origin, or handicap/disability.

The Lehigh-Northampton Airport Authority must comply with the provisions of Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000d et seq) and implementing regulations (49 CFR part 21) including amendments thereto, the Airport and Airway Improvement Act of 1982 (49 U.S.C. § 47123), the Age Discrimination Act of 1975 (42 U.S.C. 6101 et seq.), Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. § 794 et seq.), the Americans with Disabilities Act of 1990 (42 U.S.C. § 12101, et seq.), U.S. Department of Transportation and Federal Aviation Administration (FAA) Assurances, and other relevant civil rights statutes, regulations, or authorities, including any amendments or updates thereto. LNAA thus notifies all Bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, Small Businesses will be afforded full opportunity to submit proposals in response to this request and will not be discriminated against on the grounds of race, color, religion, sex, or national origin in consideration for an award.

The requirements of 49 CFR Part 26 including any amendments thereto apply to this contract. It is the policy of the LNAA to practice nondiscrimination based on race, color, sex, or national origin in the award or performance of this contract. The Owner encourages participation by all firms qualifying under this solicitation regardless of business size or ownership.

Compliance with Regulations: The Contractor (hereinafter includes consultants) will comply with the Title VI List of Pertinent Nondiscrimination Acts and the Authority’s (latest edition), which are herein incorporated by reference and made a part of this contract.

Solicitations for Subcontracts, Including Procurements of Materials and Equipment: In all solicitations, either by competitive bidding, or negotiation made by the contractor for work to be performed under a subcontract, including procurements of materials, or leases of equipment, each potential subcontractor or supplier will be notified by the contractor of the contractor’s obligations under this contract and the Nondiscrimination Acts And Authorities on the grounds of race, color, or national origin.

at Lehigh Valley International Airport 10/13/2026

GI.9

Information and Reports: The Contractor will provide all information and reports required by the Acts, the Regulations, and directives issued pursuant thereto and will permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by the Authority to be pertinent to ascertain compliance with such Nondiscrimination Acts. Where any information required of a contractor is in the exclusive possession of another who fails or refuses to furnish the information, the Contractor will so certify to the Authority, as appropriate, and will set forth what efforts it has made to obtain the information.

Sanctions for Noncompliance: In the event of a Contractor’s noncompliance with the Non-discrimination provisions of the contract, the Authority will impose such contract sanctions as may be determined to be appropriate, including, but not limited to:

a. Withholding payments to the contractor under the contract until the contractor complies; and/or

b. Cancelling, terminating, or suspending a contract, in whole or in part.

Incorporation of Provisions: The Contractor will include the provisions included herein Section GI1.03 in every subcontract, including procurements of materials and leases of equipment, unless exempt by the Acts, the Regulations and directives issued pursuant thereto. The Contractor will take action with respect to any subcontract or procurement as the Authority may direct as a means of enforcing such provisions including sanctions for noncompliance. Provided, that if the Contractor becomes involved in, or is threatened with litigation by a subcontractor, or supplier because of such direction, the Contractor may request the Authority to enter into any litigation to protect the interests of the Authority. In addition, the Contractor may request the United States to enter into the litigation to protect the interests of the United States.

GI-1.04 Description of Project

The work under this Contract is comprised of the following items:

o Overall Project – This project consists of the one-for-one replacement of an existing roof mounted cooling tower and replacement of the associated screen wall system. Repairs to the existing roof top mechanical penthouse including man door replacement, removal of existing wall louver, and structural repairs are also included. Additionally, the replacement of an existing IT room air conditioning split system is to be provided.

o Contract 1 – GC – The work under this contract is generally comprised of the following items. The removal of an existing brick screen wall system and replacement with new metal wall system, replacement of an existing mechanical penthouse man door, and removal of existing wall louver and replacement with overhead door.

GI.10

o Contract 2 – MC – The work under this contract is generally comprised of the following items. The one-for-one replacement of an existing roof mounted cooling tower and the replacement of an existing IT room air conditioning split system.

o Contract 3 – EC – The work under this contract is generally comprised of the following items. The disconnection and reconnection of electrical power in support of the HVAC equipment replacement, replacement of existing variable frequency drives, and replacement of existing roof mounted lightning protection system.

GI-1.05 Special Construction Requirements

A. All crane work must be performed at night/off-hours and be coordinated with the Authority.

GI-1.05.1 Phasing

The Contractor is required to submit a fully detailed schedule for the entire work that shall include all phase milestones and tasks required to achieve those milestones. This phasing schedule shall include specific descriptions of each phase, anticipated off-work hours, and any other information necessary to clearly describe and delineate the intention of work. The Contractor’s baseline schedule must be approved before CNTP is issued.

The Airport Authority will execute, and the contractor will receive an Administrative Notice to Proceed (ANTP) to initiate Project CPM Schedule development. After acceptance of these requirements, a Construction Notice to Proceed (CNTP) for construction of the project will be issued.

The plan described herein is not all-inclusive. The Contractor is required to submit a fully detailed schedule for the entire project as noted in Section GI-1.03 above. This schedule shall include time periods, anticipated night work, and other information necessary to clearly describe the prosecution and progress of the work. The Airport Authority reserves the right to interchange the sequence of phases as well as break out sub-phases for separate construction, without entitling the Contractor to additional costs. The Contractor is required to distinguish the project area from the rest of the secure area. Security fence as detailed in the plans is to be placed where shown on the phasing plans and where he/she decides are necessary, except where access is required.

Contractor shall follow the construction phases as indicated and shown on the contract drawings and these written specifications. Contract Durations are set for completion of the project based on the proposed milestones.

at Lehigh Valley International Airport 10/13/2026

GI.11

GI-1.05.2 Time Restrictions

Time restrictions are as shown on the contract drawings and are subject to change as required to accommodate airline, tenant, TSA and airport operations.

GI-1.05.3 Badging Process/Restrictions

This project is located within the Air Operations Area (AOA) and the successful bidder is required to obtain an ABE Airport Security ID Badge for key personnel. Since the area will be removed from requiring Security Identification Display Area (SIDA) badging, all contractors and subcontractors will not be required to obtain badging. However, all construction or project managers or supervisors who will be on-site and escorting during the duration of the project should be badged. Although all employees of the successful bidder will not require a Security ID badge, they are always required to be under escort by a badged individual. Escort requirements are as indicated in the plans and security specification.

A. Badging:

All personnel requesting unescorted access to the Airport Operations Area (AOA) must apply for and successfully complete a TSA Criminal History Record Check (CHRC) and participate in the required training to receive an Airport ID badge.

Badged individuals should be listed on the Emergency Contact list for the project;

however, if multiple workers are badged only the supervisor should be listed as an emergency contact. To begin the badging process, the individual responsible for the project coordination must complete the “Authorized Signatory Training and Acknowledgment” form and subsequent training. Once the Authorized signatory process has been completed, the contractor must submit a “No-Fly” list of all employees that will be part of the project to the Authority office. All employees that require a badge must go through the badging process in person at the Authority office and should have adequate personal identification upon visiting. All workers that will be badged must partake in Authority training videos (SIDA training and driver training); additional in-person training session is also required for those that will be driving within the AOA. This training must be scheduled and completed within the two-week period from the first visit to the actual distribution of badging.

Receiving a badge must be done in person.

B. Restrictions:

All persons working within the AOA must stay within the designated site boundaries and all non-badged individuals must always remain under the supervision of a badged individual while in the AOA. If site work requires access at Lehigh Valley International Airport 10/13/2026

GI.12

to the Aircraft Movement Area or Runway Safety Area (RSA), all persons must remain under Airport escort supervision for the entirety of this work.

In the case of an active haul route through the AOA fence/gate, a badged supervisor must also remain at the open gate/section for the entirety of relevant work. In this case, badged drivers may pass through the gate and proceed along haul route within the AOA, but non-badged drivers must remain under either Airport escort or vehicle escort by badged individuals with driving privileges.

All relevant forms and requirements for holding an Airport ID badge are included in Part V: Airport Authority Documents.

GI-1.05.4 Deliveries/Haul Route

The contractor shall have access to the site as shown on the contract drawings.

Deliveries and debris/trash removal shall occur only between the hours designated by the Airport Authority or Construction Manager.

The entire project site, including haul routes, shall always be kept free and clean of debris and shall be maintained in good repair by the Contractor. All damages to the project site caused by the actions of the Contractor or its agents shall be immediately repaired to the satisfaction of the Engineer.

GI-1.05.5 Site Restrictions

Contractor’s access to the work site may be adjusted by airport operations to coordinate with concurrent projects. Concurrent projects are noted on the General Project Layout.

GI-1.05.6 Access to the Site

All persons entering upon airport property must have the proper identification and vehicle registration specified in applicable articles of the Standard Provisions for Construction Projects and must adhere to the Lehigh-Northampton Airport Authority Rules and Regulations (See Part V: Airport Authority Documents for Airport Rules and Regulations).

The Contractor’s employees shall be required to park personal vehicles in the designated parking areas. Personal vehicles of employees and vehicles operated by vendors of goods or services will not be permitted beyond the Contractor’s designated parking area.

AOA access gates, staging areas, haul routes, and stockpile areas are noted on the General Project Layout.

at Lehigh Valley International Airport 10/13/2026

GI.13

GI-1.05.7 Staging Area

The Contractor will be given authorization to utilize an area or areas that will be available for the duration of this project as staging and mobilization areas. Staging area to be used shall be as shown on the contract drawings. Contractor must provide trailers for their personnel and the program and construction management team. Contractor will be required to relocate trailer staging and mobilization areas as directed by the Engineer.

The Contractor will be required to return all equipment to the appropriate Contractor’s staging area at the end of work each day, unless otherwise approved by the Engineer. All equipment booms shall be lowered at the close of each day’s work. All equipment will be parked in the staging area at the close of work each day and whenever it is not in use.

The Contractor (and his subcontractors) shall provide all necessary temporary fencing and gates to protect materials and equipment from pilferage. LNAA will not be responsible for any vandalized equipment or material stored on the airport property.

Any area occupied by the Contractor shall be maintained in a clean and orderly condition satisfactory to the Engineer. Particular attention shall be given to the elimination of combustible rubbish, debris, or bird attractants such as food scraps in the areas and none shall be left exposed overnight or at other periods of time when the work is shut down.

At the completion of the contract, all Contractor’s and subcontractor’s facilities will be removed promptly from the site in a workmanlike manner, the area left clean and free of all debris or surplus material, and the area returned to the condition as it existed prior to the start of the contract.

LNAA reserves the right to discontinue use of these staging areas at any time during the work.

GI-1.05.8 Load & Height Restrictions

The Contractor shall comply with all legal load restrictions imposed by the Pennsylvania Department of Transportation, the Airport Authority, or other authorities having jurisdiction, in the hauling of materials on public roadways and bridges beyond the limits of the work. Special permits will not relieve the Contractor of its liability for damages resulting in the moving of materials, spoil, or equipment.

GI-1.05.9 Permits, Licensing, and Crane Height Restrictions

The Contractor is required to meet all requirements of AC 150/5370-2 “Operations Safety on Airports during Construction,” current edition, and FAR Part 77 “Objects affecting Navigable Airspace,” current edition. The Contractor is required to obtain all permits and licenses required for the project work at his own expense.

GI.14

GI-1.05.10 Contract Duration

The duration for this contract shall be for a period of 60 calendar days from the date the Construction Notice to Proceed is issued. Contractor shall note that each phase and sub-phase, as shown in the construction documents, has its own corresponding duration. The Contractor shall be responsible for completing the work within the stated durations after

CNTP.

GI-1.05.11 Liquidated Damages

Failure by the Contractor to complete work on the Project within the time specified will impact airport operations and increase construction inspection costs. Therefore, the Contractor and his surety will be liable for liquidated damages as follows:

Pursuant to General Conditions of Bidding, commence Work on the date specified in the Notice to Proceed and complete the specified portions of the work within the contract durations specified above. In the event the Contractor fails to complete the specified Work within the specified number of days after the Notice to Proceed (either for the total Contract duration or any of the phase milestone duration, with the exception of extensions granted by Change Orders), liquidated damages (not as a penalty) will be assessed pursuant to General Provisions and as specified herein for each calendar day the completion of the specified work is delayed.

For failure to substantially complete each milestone within the defined Durations, the Contractor and his Surety will be liable for liquidated damages in the amount of shown in the below table. Liquidated Damages will also be assessed for any operational impacts (outages) to the Service interruptions (e.g. power, communication, FAA, water, or sanitary) that have not been previously identified or approved by the Construction Manager/LNAA in the amount of $250 for each hour an outage occurs.

1. For failure to substantially complete each phase, sub-phase, or the Project within the defined Durations, the Contractor and his Surety will be liable for liquidated damages in the amount of $1,000 for each calendar day.

GI-1.05.12 Project Coordination

Contractor shall not mobilize until necessary shop drawings, cut sheets, etc. are approved or as directed / approved by the engineer. Preparatory meetings as dictated in each contractor’s approved QC plan shall be held prior to each major work activity with all four prime contractors represented. This meeting will confirm that all required shop drawings are approved, and that each contractor has a clear plan for the work activities that does not conflict with the activities of each of the other contractors. Attendance at each meeting is mandatory for all prime contractors and the major subcontractors involved in the at Lehigh Valley International Airport 10/13/2026

GI.15

activities. The list of preparatory meetings will be as approved in each contractor’s QC plan.

Coordinate scheduling between all four prime contractors prior to starting work, submittals and coordination of all long-lead materials, and Work of the various Sections of the Technical Specifications to assure timely and orderly sequence of installation of interdependent construction elements.

Where scale of Contract Drawings is too large to show details clearly prepare small scale coordination drawings and submit to the Engineer for approval.

Coordinate completion and cleanup of the work of separate Sections in preparation of the Final Acceptance Review Inspection.

The Contractor shall cooperate and coordinate its work with all tenants, other contractors, and utilities companies as necessary.

Other construction contracts may be underway during the life of this project. These other projects may occur adjacent to and, at times, within the Contract limit of work for this project. These projects include but are not limited to:

1. Roof replacement

2. Parking Garage Structure

3. Roadway Rehab Projects

GI-1.05.13 Shop Drawings

The Contractor shall submit complete shop drawing packages for each item of work as required in the applicable Technical Specification Sections. Delays caused by incomplete submittals by the Contractor will not be accepted and the Contractor will be required to recover lost time at no expense to the LNAA.

GI-1.05.14 Designated Subcontractors

A portion of the work under this contract may involve modifications to or extensions of existing systems that are maintained by designated contractors under contract to the Authority. The bidder is required to solicit a bid from and, if awarded the contract, to contract with these firms as Subcontractors to the Contract for work involving these systems. Work to be performed by these Subcontractors is indicated in the Specifications and on the Drawings. Systems work to be performed by designated Subcontractors includes the following systems work affected by the work of this Contract:

N/A

GI.16

THIS PAGE INTENT IONALLY LEFT BLANK

LNAA-CO-26-002
GI-1.01 Contract Summary
GI-1.02 Notice to Contractors
GI-1.03 Non-Discrimination and Affirmative Action
GI-1.04 Description of Project
GI-1.05 Special Construction Requirements
GI-1.05.1 Phasing
GI-1.05.2 Time Restrictions
GI-1.05.3 Badging Process/Restrictions
GI-1.05.4 Deliveries/Haul Route
GI-1.05.5 Site Restrictions
GI-1.05.6 Access to the Site
GI-1.05.7 Staging Area
GI-1.05.8 Load & Height Restrictions
GI-1.05.9 Permits, Licensing, and Crane Height Restrictions
GI-1.05.10 Contract Duration
GI-1.05.11 Liquidated Damages
GI-1.05.12 Project Coordination
GI-1.05.13 Shop Drawings
GI-1.05.14 Designated Subcontractors
THIS PAGE INTENTIONALLY LEFT BLANK