This memorandum outlines liquidated damages terms for a design contract at Al Udeid Air Base. The contractor is required to complete all work by the contract completion date to avoid liquidated damages of up to 90 working days and 25% of the total contract award cost, after which the contract may be terminated. Damages are calculated at $437.63 per day for kickback or passing delays, and $353.05 per day for construction completion delays. Failure to meet the prescribed performance period may also result in liquidated damages. Timely base pass coordination is the contractor's responsibility. The importance of the project is emphasized, as the current facility's mold and safety issues need remediation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question and Answers.pdf | ||
| Solicitation Amendment FA570221R00050002 SF 30.pdf | ||
| Solicitation Amendment FA570221R00050001 SF 30.pdf | ||
| 11. 20-0033 LD Construction (signed).pdf | ||
| 3. AF Form 3000 Material Submittal.pdf | ||
| 6. AF Form 3065 Progress Report.pdf | ||
| 8. Past Performance Questionnaire.docx | DOCX document | |
| 9. Base Access Information.pdf | ||
| Solicitation - FA570221R0005.pdf | ||
| 1. 20-0033 Repair BPC Gym (B10550) SOW.pdf | ||
| 2. 20-0033 REPAIR BPC GYM (B10550) V6.pdf | ||
| 4. AF Form 66 Schedule of Material Submittals.xls | XLS spreadsheet | |
| 5. AF Form 3064 Progress Schedule.xlsx | XLSX spreadsheet | |
| 7. Construction Cost Estimate Breakdown.xls | XLS spreadsheet |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED//FOR OFFICIAL USE ONLY
DEPARTMENT OF THE AIR FORCE
UNITED STATES AIR FORCES CENTRAL COMMAND (USAFCENT)
379TH AIR EXPEDITIONARY WING
“The information herein is For Official Use Only (FOUO) which must be protected under the Freedom of Information Act of 1966 and Privacy Act of 1974, as amended. Unauthorized disclosure or misuse of this PERSONAL INFORMATION may result in criminal and/or civil penalties”
Mission ~ Airmen ~ Partners
UNCLASSIFIED//FOR OFFICIAL USE ONLY
ALUA 20-0033
1 April 2021
MEMORANDUM FOR 379 ECONS
FROM: 379 ECES/CENM
SUBJECT: Liquidated Damages; Design of ALUA 20-0033
1. It is understood by both parties, the US Government and the Contractor, that the prescribed performance period for the subject project is not to be violated, or Liquidated Damages will be imposed on the contractor by the US Government. Violation of the performance period is any work related to contract completion that has not been done within prescribed performance period. Base Pass Coordination is included within the Design Period of Performance, and any delays accrued due to incomplete passing will be accounted for in the calculation of the Liquidated Damages. In the event that the contractor fails to complete any or all work preventing completion of design, it is agreed upon that compensatory Liquidated Damages will be assessed to the contractor. Works not completed by the contractor by the contract completion date may be cause for the government to initiate the contract termination process. After initiating this process the Government will assess liquidated damages up to 90 working days and/or 25% of the total contract award cost at which point the contract will be terminated.
2. If this project is not provided, the facility will remain inadequate. Mold will continue to grow due to the facility’s poor ventilation, uneven surfaces from settling floor will continue to pose a tripping hazard, and all personnel will be at risk for outdoor sports related heat injuries.
3. Due to the importance of the project, a liquidated damages has been calculated and will consist of $437.63 (1,597.36 QAR) for each day of kickback and passing issues delay, and $353.05 (1,288.65 QAR) for each day of construction competition delays. In addition, the Liquidated Damages set forth herein are mutually agreed to be reasonably related to the actual damages that would be incurred by the US Government.
4. Please contact me at 455-1039 if you have questions.
BRIAN J FINK, 2D LT, USAF
Design Cell OIC
Attachment:
Liquidated Damages Calculations
“The information herein is For Official Use Only (FOUO) which must be protected under the Freedom of Information Act of 1966 and Privacy Act of 1974, as amended. Unauthorized disclosure or misuse of this PERSONAL INFORMATION may result in criminal and/or civil penalties”
Mission ~ Airmen ~ Partners
UNCLASSIFIED//FOR OFFICIAL USE ONLY
Total Cost
Pay Grade # PSNL Annual DOD Composite Rate*1 Hourly Rate Hrs/Day Total $49.85 O3 1 $155,063 $74.55 0.25 $18.64 O2 1 $129,848 $62.43 0.5 $31.21
Total Cost
Pay Grade # PSNL Annual DOD Composite Rate*1 Hourly Rate Hrs/Day Total $159.13 O3 2 $155,063 $74.55 0.5 $74.55 E5 2 $87,962 $42.29 1 $84.58
Total Cost
Pay Grade # PSNL Annual DOD Composite Rate*1 Hourly Rate Hrs/Day Total $84.58 E5 2 $87,962 $42.29 1 $84.58
Total Cost
Position # PSNL Grand Overburden Cost*2 Hourly Rate Hrs/Day Total $144.08 Engineer 1 $149,838 $72.04 1 $72.04
CM 1 $149,838 $72.04 1 $72.04
Total Cost
$437.63 $1,597.36 Total Cost
$353.05 $1,288.65
Liquidated Damages as Cost to Government (QAR) Grand Total Cost to Government: (CE + CONS + AMENTUM)
Liquidated Damages as Cost to Government (USD) Liquidated Damages as Cost to Government (QAR)
Liquidated Damages Calculation Military Personnel Costs to Government (379 Expeditionary Civil Engineer SQ)
Military Personnel Costs to Government (379 Expeditionary Contracting SQ)
Military Personnel Costs to Government (Unit Pass Coordinator)
AMENTUM Personnel Costs to Government
Kickback Cost to Government: (CE + CONS + UPC + AMENTUM) Liquidated Damages as Cost to Government (USD)
Note *1: The Annual DOD Composite Rate was calculated directly from the Military Composite Standard Pay and Reimbursement Rates, Department of the Air Force, For Fiscal Year 2020 section of the FY2020 Department of Defense (DoD) Military Personnel Standard Pay and Reimbursement Rates (Published 12 April 2019). The hourly rate, however, was deviated to reflect the standard practice of 2080 work hours per year.
Note *2: The Grand Overburden Cost was calculated directly from the AMENTUM Engineering Support Service Contract. The value was an average for all Design Engineers and Construction Managers working in the Engineering Flight. The hourly rate was adjuste to reflect the standard practice of 2080 work hours per year.