About this file

This is a Bid Proposal document from San Bernardino County's Project and Facilities Management Department for Project 10.10.1657, soliciting sealed bids for the Mojave River Forks Regional Park Restroom & Shower Replacement project located at 17891 CA-173 in Hesperia, California. The scope of work includes demolition of three existing bathroom structures and installation of three new prefabricated restroom/shower combination structures, along with construction of ADA-compliant pathways and parking. The bid opening is scheduled for March 18, 2026, at 1:00 p.m. Bidders must submit their proposals through San Bernardino County's Electronic Procurement Network (ePro) or in person, with a mandatory pre-bid meeting held on January 27, 2026. The contract performance period is 200 calendar days from the Notice to Proceed, with liquidated damages assessed at $1,500 per day for work not completed within the specified timeframe.

The total base bid includes a $35,000 allowance for hazardous materials abatement in accordance with the Asbestos-Containing Materials Report and applicable federal, state, and local regulations. Bidders must submit a bid security (bid bond) equal to ten percent of the base bid and, if successful, provide a Performance Bond and Labor and Material Payment Bond each equal to 100% of the contract price within ten calendar days of award. Bidders must possess a California State Contractor's Class B License and either hold specialty licenses for Mechanical (C-20), Electrical (C-10), and Plumbing (C-36) work or identify qualified subcontractors holding these licenses. Contractors and all subcontractors must be registered with the California Department of Industrial Relations and comply with prevailing wage requirements. The bid remains valid for 60 days following the bid opening, and the contract shall be awarded to the lowest responsive and responsible bidder. All contractors must demonstrate compliance with California Air Resources Board off-road diesel fleet regulations and maintain insurance coverage including General Liability and Auto Liability with limits of $3,000,000 per occurrence, Workers' Compensation insurance, and Course of Construction Builder's Risk insurance.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project 10.10.1657

Bid Proposal 1 of 9

Project No. 10.10.1657

BID PROPOSAL

PROJECT: Mojave River Forks Regional Park Restroom & Shower Replacement

LOCATION: 17891 CA-173, Hesperia, California

OWNER: San Bernardino County

BID OPENING: March 18, 2026 at 1:00 p.m.

BIDDER:

San Bernardino County Project and Facilities Management Department – Project Management 620 South E St San Bernardino, CA 92415-0184 https://pfm.sbcounty.gov/

In compliance with your invitation for bids, the undersigned has carefully examined the project Bid Documents, including the drawings and specifications, for the scope of work which is demolition of three existing bathroom structures (restroom/shower); Installation of three new prefabricated restroom/shower combination structures, and construction of ADA path of travel and parking in Hesperia, California, and fully understands the scope and meaning of the Bid Documents.

The undersigned hereby agrees to furnish all materials, labor, tools, equipment, apparatus, facilities, and transportation necessary to complete all work in strict conformity with the drawings and specifications, and to execute the contract to the satisfaction of the Project and Facilities Management Department – Project Management, at the following cost(s):

In case of discrepancy between the written bid set forth and the numerical bid set forth, the written bid shall prevail. In the case of a discrepancy between the written bid or numerical bid set forth on the bid proposal, and the numerical bid set forth in the ePro system, the information on the bid proposal shall prevail.

https://pfm.sbcounty.gov/

Bid Proposal 2 of 9

BASE BID

For the furnishing of the labor, materials, and equipment necessary to complete all work designated in the Plans and Specifications.

The LUMP SUM of _______________________________________ Dollars

Allowance for hazardous materials abatement, including removal and proper disposal of all identified hazardous materials, in accordance with the Asbestos-Containing Materials Report and applicable federal, state, and local regulations - $35,000

TOTAL BASE BID (Base Bid + $35,000 allowance for hazardous materials abatement):

The LUMP SUM of ________________________________________Dollars

The above-mentioned TOTAL BASE BID includes applicable California state sales tax, bonds, insurance and all other costs required to perform all the work described in the project drawings and specifications.

The lowest bid shall be the lowest bid price on the TOTAL BASE BID. A responsible and responsive bidder who submitted the lowest bid shall be awarded the contract, if it is awarded.

BID DEPOSIT (BID BOND)

There is enclosed herewith, a certified check or surety bond in the amount of ten percent (10%) of the BASE BID, or, more specifically, Dollars ($_______________________________), made payable to San Bernardino County. The undersigned agrees that in the event of the failure by the undersigned to execute the necessary contract and furnish the required contract bonds and insurance, the certified check or surety bond and the money payable thereon shall be, and remain, the property of San Bernardino County. If the bid is accompanied by a certified or cashier's check, the check shall be deposited by the Project and Facilities Management Department

– Project Management, and a County warrant for the full amount shall be issued to the undersigned approximately one month after Contract Award.

If the bid is submitted through San Bernardino County Electronic Procurement Network (ePro) then scan the bid security (bid bond) and submit the scanned copy with your bid submittal in ePro, additionally, mail or submit the original bid security, in a separate sealed envelope labeled “Bid Bond” with the title of the work and the name of the bidder clearly marked on the outside, to: Project and Facilities Management Department – Project

Bid Proposal 3 of 9

Management, 620 South E St, San Bernardino, CA 92415-0184. Any mailed or submitted bid security must be received on or before the time set for the opening of the bids.

TIME OF COMPLETION

The undersigned agrees to complete the work within 200 calendar days from the date stipulated in the Notice to Proceed.

LIQUIDATED DAMAGES

Pursuant to the provisions of Government Code Section 53069.85 and in the event that all the Work called for in this Contract is not completed within the number of calendar days set forth, Contractor shall forfeit and pay to the County the sum of $1,500.00 per day for each calendar day the work remains incomplete, to be deducted from any payments due or to become due to the Contractor. (Reference General Conditions and Special Conditions)

ESCROW ACCOUNT

Pursuant to Section 22300 of the Public Contract Code, at the request and expense of the Contractor, the Contractor may substitute qualified securities in lieu of retention withheld by the County and/or establish an escrow account for retention payments.

REJECTION OF BIDS

The undersigned agrees that the County reserves the right to reject any or all bids, and reserves the right to waive informalities in a bid or bids, not affected by law, if to do so seems to best serve the public interest.

VALIDITY OF BIDS

The undersigned agrees that this bid will remain valid for sixty (60) days after the scheduled bid opening.

STATE LICENSES

The undersigned hereby certifies that he/she is currently the holder of a State Contractor's Class B License. The undersigned also certifies that all subcontractor(s) listed under the Designation of Subcontractors section of the Bid Proposal are currently the holder of valid contractor’s license(s) in the State of California and the license is the correct class of license for the work to be performed by the subcontractor(s). The undersigned agrees that if he/she does not list a subcontractor(s) under the Designation of Subcontractors section of this Bid Proposal to perform work in any of the following trades, in order to be found responsive and in order to perform that work himself/herself, the undersigned must possess the State specialty license for that trade: Mechanical (C-20); Electrical (C-10); and Plumbing (C-36).

Bid Proposal 4 of 9

INSURANCE

The undersigned agrees to furnish certified copies of all insurance policies and endorsements; all certificates of comprehensive, general and auto liability insurance;

Workers' Compensation insurance; and such other insurance that will protect him from claims for damages and personal injury, including death, which may arise from operations under the contract, whether such operation be by the undersigned or by any subcontractor of the undersigned, or anyone directly or indirectly employed by the undersigned or any subcontractor of the undersigned in accordance with Section 11.2 of the General Conditions. The undersigned agrees to provide the Project and Facilities Management Department – Project Management with Certificates of Insurance evidencing the required insurance coverage at the time Contractor executes the contract with the County. All policies (excluding Workers' Compensation) shall name San Bernardino County and its officers, employees, agents and volunteers as additional insureds. All coverages shall be subject to approval by the County for adequacy of protection.

BONDS

If this Bid is successful, the undersigned agrees to execute the required Standard Contract and will furnish a payment bond in an amount equal to one hundred percent (100%) of the contract price and a Faithful Performance Bond in an amount equal to one hundred percent (100%) of the contract price. These bonds shall be secured from a surety company or companies satisfactory to the County within ten (10) calendar days of the contract award and shall be on County approved bond forms. Bonds shall remain in full force and effect for a period of one year following the date of filing of Notice of Completion.

FORMER COUNTY OFFICIALS

Contractor agrees to provide or has already provided information on former San Bernardino County administrative officials (as defined below) who are employed by or represent Contractor. The information provided includes a list of former county administrative officials who terminated county employment within the last five years and who are now officers, principals, partners, associates or members of the business. The information also includes the employment with or representation of contractor. For purposes of this provision, “county administrative official” is defined as a member of the Board of Supervisors or such officer’s staff, Chief Executive Officer or member of such officer’s staff, county department or group head, assistant department or group head, or any employee in the Exempt Group, Management Unit or Safety Management Unit.

INACCURACIES OR MISREPRESENTATIONS

If during the course of the bid proposal process or in the administration of a resulting Contract, the County determines that the contractor has made a material misstatement or misrepresentation or that materially inaccurate information has been provided to the County, the contractor may be terminated from the bid proposal process, or in the event a Contract has been awarded, the Contract may be immediately terminated. If a Contract

Bid Proposal 5 of 9 is terminated according to this provision, the County is entitled to pursue any available legal remedies.

VISITING THE SITES

The undersigned has visited the site and is familiar with the local conditions of the work site.

CALIFORNIA AIR RESOURCES BOARD (CARB) IN-USE OFF-ROAD DIESEL-FUELED

FLEETS REGULATION COMPLIANCE CERTIFICATION

This Project is subject to the California Air Resources Board (CARB) approved amendments relating to In-Use Off Road Diesel-Fueled Fleets found at California Code of Regulations Title 13, sections 2449, 2449.1, and 2449.2 (the “Regulations”). The Regulations require a Prime Contractor, bidding on a public works project to be awarded by any public works awarding body, to certify that the Contractors off-road diesel-fueled fleets comply with CARB regulations. Section 2249(b) includes a list of off-road diesel-fueled fleets subject to these regulations. It is the responsibility of the Contractor to verify if their fleet is subject to these regulations.

Contractor is required to obtain and submit Certificates of Reported Compliance from all subcontractors that are listed in the bid submission. Failure to provide Contractor’s CARB compliance number may constitute a material irregularity rendering their bid non-responsive and non-responsible, and subject to rejection for non-responsiveness.

No award shall be made to a Contractor that has failed to provide its CARB compliance certificates, unless the Contractor confirms that no equipment subject to the regulation will be used to execute the Contract Work. By submitting a bid, the Bidder hereby certifies that it is aware of the requirements set forth in Sections 2449, 2449.1, and 2449.2, Title 13, California Code of Regulations and any successful Bidder and its subcontractors shall comply with sections 2449, 2449.1, 2449.2 of Title 13 of the California Code of Regulations, including by providing Certificate(s) of Reported Compliance for In-Use Off- Road Diesel-Fueled Fleets for the fleet selected for the contract and their listed subcontractors, if applicable, with its bid.

Contractor shall not enter into a contract with a fleet for which it does not have a valid Certificate of Reported Compliance for the fleet and Contractor’s listed subcontractors, if applicable, prior to entering into a new or renewed contract with that fleet. Contractor shall only allow fleets with valid Certificates of Reported Compliance on Contractor’s job sites. The Certificates of Reported Compliance received by the Contractor for this Project must be retained for three (3) years after the Project’s completion. Upon request by CARB, these records must be provided to CARB within five (5) business days of the request. Between March 1 and June 1 of each year, Contractor must collect new valid Certificates of Reported Compliance for the current compliance year, as defined in Regulation Section 2449(n), from all fleets that have an ongoing contract with the Contractor as of March 1 of that year. Contractor must not write contracts to evade this requirement.

Bid Proposal 6 of 9

If Contractor discovers that any fleet intending to operate vehicles subject to the Regulation for Contractor does not have a valid Certificate of Reported Compliance, as defined in Regulation section 2449(n), or if Contractor observes any noncompliant vehicles subject to the Regulation on Contractor’s job site, then Contractor must report the required information to CARB within the time period contained in in the Regulations.

Upon request by CARB, Contractor must immediately disclose to CARB the name and contact information of each responsible party for all vehicles subject to the Regulation operating at the job site or for Contractor. If applicable, Contractor shall prominently display signage for any project where vehicles subject to the Regulation as provided and within the time period contained in the Regulation.

Situations in which prime contractors or public works awarding bodies, as applicable, are contracting for projects that are considered emergency operations, as defined in section 2449(c)(18), are exempt from the requirements in section 2449(i)(1)-(3), but must still retain records verifying vehicles subject to the regulation that are operating on the emergency operations project are actually being operated on the project for emergency operations only. These records must include a description of the emergency, the address or a description of the specific location of the emergency, the dates on which the emergency operations were performed, and an attestation by the fleet that the vehicles are operated on the project for emergency operations only.

Contractor shall complete and return the “California Air Resources Board (CARB) In-Use Off-Road Diesel-Fueled Fleets Certification of Compliance” form attached hereto as a condition to bidding this Project.

DESIGNATION OF SUBCONTRACTORS

In compliance with the provisions of Sections 4100-4108 of the Public Contract Code of the State of California, and any amendments thereof, the undersigned shall set forth below the name, location of the place of business and the California contractor license number of each subcontractor who will perform work (meaning the total amount of the subcontractor’s contract amount including all labor, materials, supplies and services) in excess of one-half of one percent (1/2 of 1%) of the total bid; and, the general category or the portion of the work to be performed by each subcontractor.

If the undersigned fails to specify a subcontractor(s) for any work to be performed under the Contract, the undersigned agrees to perform the work and shall not be permitted to subcontract that work except in cases of public emergency, and then only after written finding as public record by the Board of Supervisors. In order for the undersigned to perform the work in any of the following trades, the undersigned must possess the State specialty license for that trade: Mechanical (C-20); Electrical (C-10); and Plumbing.

The undersigned certifies that all subcontractor(s) listed below are currently the holder of valid contractor’s license(s) in the State of California and the license(s) is the correct class of license for the work to be performed by the subcontractor(s).

Bid Proposal 7 of 9

The undersigned certifies that it and all subcontractor(s) listed below have registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 (applicable for all bids submitted on or after March 1, 2015). The undersigned agrees that no contractor or subcontractor may be awarded a contract for public work or perform work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 (applicable for all contracts awarded on or after April 1, 2015).

The undersigned acknowledges that the project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

As required by Labor Code 1771.1(a) “A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”

Where a hearing is required for a decision on the substitution of subcontractors, pursuant to the provisions of Chapter 4, Part 1, Division 2, of the Public Contract Code, (commencing with Section 4100) by the awarding authority, or a duly appointed hearing officer, the Clerk of the Board of Supervisors shall prepare and certify a statement of costs incurred by the County for investigation, and to conduct the hearing, including the costs of any hearing officer and shorthand reporter appointed. For the purposes of a hearing for the substitution of subcontractors (pursuant to the Public Contract Code commencing with Section 4100) the awarding authority shall be the Director of the Project and Facilities Management Department, or his/her designee.

The statement of costs shall be sent to the undersigned, who shall reimburse the County for all costs. If not paid separately, such reimbursement shall be deducted from monies due and owing to the undersigned prior to acceptance of the project.

CONTRACTOR NAME:________________________________________________

Subcontractor’ s Name

Portion of Work Performe d

Location of Busines s

CA

Contractor’ s License

DIR

Registratio n No.

CARB

Certificate of Complianc e No.

Bid Proposal 8 of 9

ADDENDA

This bid includes Addendum No. dated

Addendum No. dated

Addendum No. dated

Addendum No. dated

Bidder must acknowledge all addendums above, regardless of any acknowledgement of addendums in ePro.

AFFIDAVIT

The undersigned has submitted with the bid proposal a non-collusion declaration, signed under penalty of perjury, for the principal contractor. The undersigned agrees to furnish the County non-collusion declarations for subcontractors signed under penalty of perjury, and states that this is a genuine proposal and is neither collusive nor made in the interest of any other person, and has not induced anyone to submit a sham bid or refrain from bidding.

The undersigned acknowledges it has registered with the ePro system prior to the date and time to receive sealed bids or it will be disqualified.

Bid Proposal 9 of 9

The undersigned declares: that the only person or parties interested in this proposal as principals are those named herein; that this bid is made without any connection with any other person or persons making a bid for the same work, except for another division of the undersigned which may submit an independent bid; that the bid is in all respects fair and without collusion or fraud; that the undersigned has read the Advertisement for Bids and the Instructions to Bidders and agrees to all the stipulations contained therein; that the undersigned has examined the form of contract (including the specifications, drawings, and other documents incorporated therein by reference); that in the event this bid as submitted, including the incorporated bidding documents, be accepted by the County, the undersigned shall execute a contract to perform the work as outlined herein.

If undersigned is a corporation, proposal must be signed by an authorized officer of the corporation.

If the bid proposal is submitted through ePro the undersigned acknowledges that its electronic signature is legally binding.

Check One: ( ) Sole Proprietor ( ) Partnership ( ) Corporation ( ) Other

Name of Bidder:

Address:

Phone:

Email: _________________________________________________________________

Contractor's License No.: Primary Class:

Expiration Date of Contractor's License

Contractor’s DIR Registration #_________________________________________ ___

Contractor's California Air Resources Board (CARB) In-Use Off-Road Diesel-Fueled Fleets Regulation Compliance No.:

I declare under penalty of perjury the above is true and correct.

Authorized Signature: Title:

Print Name: Date:

INACCURACIES OR MISREPRESENTATIONS

File details come from the government source that posted it. Updated .