Solicitation #140P1520Q0067
Point of Contact: Cecilia Mitchell, cecilia_mitchell@nps.gov
NPS SOLICITATION 140P1520Q0067
STATEMENT OF WORK
SCOPE: Water meter replacement services.
PERFORMANCE PERIOD: The work of this task order shall be provided from approximately 45 days from the notice to proceed.
I. GENERAL DESCRIPTION OF THE WORK:
This contract is for the replacement of a 16” propeller meter with a 16” mag meter and spool piece. The new water meter will be connected to a totalizer. All work performed will be coordinated by the Grand Canyon National Park (GRCA) staff.
II. SCOPE OF SERVICE REQUIREMENTS:
A. Water Meter Replacement:
This project is to remove and replace a 16” propeller meter with a government furnished 16” mag meter and spool piece. Contractor will supply and install a totalizer. Due to the inability for the park to completely valve off the meter, a wet installation will be necessary. The park will blow off fire hydrants to relieve the pressure. The last time the meter was replaced, a pump was needed to remove water from the meter pit and the fire hydrant blow offs were able to decrease the pressure to a safe pressure. The work will be performed at night. The contractor should arrive by 10 PM the day the work is to be performed and the work shall be completed by 4 AM the following morning. The contractor will provide all necessary lighting to accommodate the work site in a safe manner. The contractor’s supervisor will coordinate all work activity with the Grand Canyon utility.
The government will furnish the following:
16” Sensus Hydroverse meter (cut sheet provided) 16” X 2’-00.275” Fl X Fl spool piece 16” gaskets - 3 Bolt and nut packs for the 3 flanged connections (bolts marked “ A307B”)
The contractor will need to supply all equipment and machinery for the job. Contractor will provide all other necessary materials and supplies to complete the job.
Completion of this project shall be accepted when the water meter installed is identified as complying with all appropriate plumbing codes and standards, and when the water meter installed responds to the water meter totalizer.
Contractor is responsible for the proper off-site disposal of all water meter and parts removed as part of this project.
Attachments provided:
Existing water meter cut sheet New meter cut sheet Map of project location
B. MEETINGS:
Work Plan Meeting
This meeting will be scheduled within 2 weeks of the notice to proceed. At a minimum, the supervisor who will be onsite will need to be in attendance. A detailed work plan outlining the following will be submitted prior to the meeting:
Number of work personnel and roles Number and type of heavy machinery Safety plan Detailed work plan outlining steps to replace the meter
At this meeting, the scheduled work date will be coordinated with the park. A minimum of two weeks notice is required by the Park in order to send out notices of the scheduled work date.
Assume the meeting will take 1.5 hours.
Onsite Meeting
A half hour meeting will be held with GRCA staff to confirm the necessary steps and go over any safety briefings. All contractor personnel will be in attendance.
C. MISCELLANEOUS
Delivery
Prior to mobilizing the Contractor shall submit or perform the following:
Submit project schedule.
Product Shop Drawings - Product data for all proposed materials to be installed for review and approval.
Contractor’s Use of the Premises
Contractor must be accompanied by a designated NPS employee at all times during the course of replacement.
No on-site work shall be performed on weekends and federal holidays unless otherwise directed by the contracting officer (CO) and/or contracting officer’s representative (COR).
Noise at the various work site shall be kept to the minimum necessary to accomplish the work. Radios and/or music are not allowed.
Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
Contractor must confine storage of equipment and supplies to areas designated by the CO and/or COR.
Disposal
Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the park.
Accident Prevention
The Contractor is expected to ensure a safe environment for all personnel and visitors, and shall comply with all applicable sections of the Occupational Safety and Health Act (OSHA). In case of conflicts between federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites.
Contractor must meet the requirements of The National Institute for Occupational Safety and Health (NIOSH) and Mine Safety and Health Administration (MSHA) for personal protective equipment. Contractor must have a first-aid kit available at the work site. The Contractor shall report all accidents to the COR as soon as possible and assist the COR and other officials, as required, in the investigation of the accident.
Quality Assurance
The quality of all work shall be the responsibility of the Contractor. The Contractor shall inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
The Contractor shall inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
The Contractor shall stop work on any item or feature where deficiencies have been noted by the Contractor or the CO and/or COR, until such deficiencies have been corrected to the satisfaction of the CO and/or COR. Work shall not proceed on any feature of work containing uncorrected work.
Project Closeout
The Contractor shall request in writing a final inspection. Before requesting the final inspection, the Contractor shall remove all tools, equipment, surplus materials, and rubbish, and restore to original condition surfaces or structures that are damaged due to work of this contract. At the time of final inspection, the project shall be complete.
When work is determined to be substantially complete, the CO and/or COTR will prepare a list of deficiencies to be corrected before final acceptance. The Contractor shall complete the work described on the list of deficiencies within 5 calendar days, weather permitting. If the Contractor fails to complete the work within this time frame, the Contracting Officer may replace, repair, or remedy the work with an appropriate reduction in the contract price. If work is not determined to be substantially complete, Contracting Officer will notify Contractor in writing. After completing work, Contractor shall resubmit certification and request a new final inspection.