About this file

This is a Special Provisions document for Contract MS-944 issued by Lemoyne Borough in Cumberland County, Pennsylvania, establishing contractual requirements for a paving project. The project involves roadway reconstruction with bituminous paving work and must be completed by October 6, 2026, with liquidated damages assessed at $250 per calendar day for delays beyond this deadline. The contractor must notify the municipality five working days prior to project start and is required to provide design specifications meeting Form 408 requirements to the municipality five days before work commences. All work must include traffic control and safety devices compliant with current MUTCD Publications 212 and 213, with the municipality reserving the right to limit work completion and procure materials best suited to their requirements.

The special provisions establish specific material and quality control requirements including delivery tickets for all materials, CS-4171 Certificates of Compliance and TR-465 Daily Bituminous Mixture Certifications, Bills of Lading for each bituminous shipment, and oil samples from each distributor truck collected twice daily and witnessed by municipality representatives. The contractor is responsible for defects occurring within one year of application and must complete all testing in accordance with Specification Form 408, including tack coat, prime coat, bituminous seal, and saw-cut or milled paving notch requirements. The contractor assumes full responsibility for incidental preparation and cleanup, roadway power brooming, and excess material removal, with the municipality retaining inspection authority throughout the project. Future contract awards will be based on the quality of work as determined by the borough, and a Final Completion Certificate and Notice of Completion are required upon project conclusion.

View the file

Other files

File Type Posted
3-Bid Bond.pdf PDF
7-Lemoyne Borough Pear Street Drainage Improvement Project Project Manual.pdf PDF
6-Attach 1A Special Prov.pdf PDF
4-FrontEnd-PWEmplymnt verificatnfm.pdf PDF
4-Employment Verification.pdf PDF
3-BID BOND.pdf PDF
5-MS944 Contract.pdf PDF
1-Anti-Collusion Aff.pdf PDF
1-Lemoyne Borough 10th St Retaining Wall Rehabilitation Project Manual.pdf PDF
6-MS944 SPECIAL PROVISIONS.pdf PDF
5-Proposal Contract.pdf PDF
2-Workmens Comp Aff.pdf PDF
7-MS944 Anti-Collusion Aff.pdf PDF
2-MS944 Workers Comp Aff.pdf PDF
2-FrontEnd-PWEmplymnt verificatnfm.pdf PDF
6-Lemoyne Borough 2026 Storm Sewer Lining Project Manual.pdf PDF
5-MS944 Anti-Collusion Aff.pdf PDF
3-Bid Bond.pdf PDF
4-MS944 Contract.pdf PDF
5-Bid Bond.pdf PDF
2-Anti-Collusion Aff.pdf PDF
3-Proposal Contract.pdf PDF
7-Apple St Phase 2 Improvements 2025-12-23.pdf PDF
4-FrontEnd-PWEmplymnt verificatnfm.pdf PDF
1-Workmens Comp Aff.pdf PDF
6-Attach 1A Special Prov.pdf PDF
4-Lemoyne Refuse Contract - Non-Collusion Affidavit -2025.docx DOCX document
10-Lemoyne Refuse Contract - Questionnaire -2025.docx DOCX document
2-Lemoyne Refuse Contract - Performance Bond - 2025.docx DOCX document
3-Lemoyne Refuse Contract - Payment Bond - 2025.docx DOCX document
8-Lemoyne Refuse Contract - Agreement- 2025.docx DOCX document
1-Lemoyne Refuse Contract - Specifications- 2025 revised.docx DOCX document
5-Lemoyne Refuse Contract - Instructions to Bidders-2025.docx DOCX document
6-Lemoyne Refuse Contract - Bid Proposal -2025.docx DOCX document
7-Lemoyne Refuse Contract - Bid Bond- 2025.docx DOCX document
9-Lemoyne Refuse Contract - General Conditions -2025.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(5-06)

SPECIAL PROVISIONS TO CONTRACT MS-944 (Attachment 1-A)

CONTAINS IMPORTANT INFORMATION FOR THE CONTRACTOR

The Prime Contractor and subcontractors must comply with all of the following provisions that are marked with an “X”

Traffic Control and Safety Devices to be provided by the Contractor (Maintenance and Protection of Traffic to comply with current MUTCD, Publication 212 and Publication 213.)

Delivery tickets for all materials.

CS-4171 Certificate of Compliance and/or TR-465 Daily Bituminous Mixture Certification required for all materials.

Notify the Municipality five working days prior to start of project.

Work to be completed by October 6, 2026 After October 6, 2026 liquidated damages apply at the rate of

$250 per calendar day.

Roadway to be power broomed by (contractor municipality ) prior to start of project.

Excess material to be removed by (contractor municipality ).

Municipality to inspect project.

Need Bill of Lading for each shipment of bituminous material per Section 702.1(c) of Specifications 408.

Tack Coat required per Section 460, or 409 for superpave, of Specifications 408 and is incidental to paving item unless noted otherwise.

Prime Coat require per Section 461 of Specifications 408.

Bituminous Seal on all abutting pavement and curbs required.

Saw cut or Milled Paving Notch required and incidental to paving item unless noted otherwise.

Scratch/Leveling Courses to be placed at the discretion of appointed inspector(s).

Full width pavement with one pass required.

Municipality reserves the right to limit work completed.

Taper pavement the last 3 feet to curb.

For FOB Source bids, hauling distance will determine selection of bid award.

Municipality reserves the right to procure material which best suits their requirements after all bids and items are reviewed.

Incidental Preparation and clean up required. (Project Construction Materials) The municipality reserves the right to make an award on the basis of the aggregate total for all like items on which quotations are received.

Provide design, which meets Specifications Form 408 to the municipality 5 days prior to start of work.

Contractor is responsible for defects that occur within one year of applications.

Contractor is required to review proposed project with Municipality’s Representative prior to bidding.

Oil samples required from each distributor truck by contractor (1) quart: A.M. & P. M. and witnessed by municipality and retained by municipality. (Oil samples must be placed in an approved type container that is compatible with oil sample.)

At least three random stone samples to be taken by contractor on project site witnessed by municipality and retained by municipality.

Complete all testing in accordance with Specification Form 408 Section 409 except for superpave volumetric testing.

Notice to Proceed will be the date of Contract acceptance.

Final Completion Certificate & Notice of Completion required.

Future award of Contract will be based on quality of work as determined by the municipality.

Contractor notify all residents of pending work to be performed.

My signature signifies that I have read and understand the above special provisions to this contract, and by being authorized by this company to act as their authorized representative, and on their behalf hereby agree to adhere to any and all of the provisions pertaining to this contract.

CONTRACTOR’S REPRESENTATIVE DATE MUNICIPALITY’S REPRESENTATIVE DATE