This statement of work outlines a roof replacement construction project at Pittsburgh Air Reserve Station in Pennsylvania. The selected contractor will remove and replace the existing metal roofing system and three ventilation units on Building 411. The work includes supply of all necessary materials, labor, equipment, and disposal of construction debris. The project must be completed within 180 calendar days of the notice to proceed. The contractor will be responsible for verifying existing conditions, complying with all safety regulations, and cleaning the work area daily. The statement of work provides specifications and requirements for the construction work.

The related federal contract opportunity is a solicitation from the Department of the Air Force Reserve Command seeking to award a contract to replace the roof on Building 411 at Pittsburgh Air Reserve Station, as outlined in the statement of work.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project JLSS 21-0005

REPLACE ROOF

Building 411

Construction

911 AIRLIFT WING

PITTSBURGH AIR RESERVE STATION

MOON TWP, PENNSYLVANIA 15108-4495

OPR: 911 AW/MSG/CE

Engineering Flight

DSN: 277-8583

CML: (412) 474-8583

luis.barrios@us.af.mil

July 2023 mailto:luis.barrios@us.af.mil

PROJECT JLSS 21-0005

I. TITLE and DESCRIPTION:

A. Summary. “Roof Replacement, B411” is a construction contract at Pittsburgh ARS, PA.

This work consists of performing all construction work which includes providing all materials, labor, and equipment necessary to provide a useful and operable roofing system and ventilation units in accordance with this statement of work.

B. Repair Work. Remove and replace existing metal roofing system and ventilation units.

Replace flashing/sealing along the windows and lower roof section on North side. Verify insulation integrity and replace/upgrade as required to address damaged insulation and current building codes/UFCs. Dispose of construction debris at approved off base disposal site.

C. Site Plans. Attached are drawings that show the current layout of the work area associated with this project.

II. PERFORMANCE TIME: Work is to be completed within 180 calendar days after NTP is approved, during normal duty hours from 0730 to 1600, and weekdays Monday through Friday, with no work on federal holidays. Any deviations from the normal working hours must be approved 72 hours in advance by the Contracting Officer. Typically work will not be allowed during training weekends, usually the first weekend of the month.

III. CONSTRUCTION;

A. Contractor Responsibilities: Verify exact location of new work. Verify conditions and dimensions at the site before ordering or delivery of material. Provide all tools, equipment, materials, transportation, and labor to accomplish work. Contractor shall maintain a normal safe work area and remove all debris from Pittsburgh Air Reserve Station when work is completed.

Excess materials and waste will be disposed of in accordance with local and state ordinances.

Any damage to existing facilities or appurtenances shall be repaired or replaced, in kind, by the contractor at no additional cost to the Government.

B. Construction: The construction contractor will furnish all labor, equipment, and materials and perform all operations in accordance with plans, specifications, and contract terms to provide a complete project, ready for use. Contractor will work under Air Force Occupational Safety and Health (AFOSH) and OSHA regulations.

C. General:

The work shall mean to remove and replace existing standing seam metal roofing system and ventilation units to the government. This work includes panels, translucent panels, joint sealants, insulation, downspouts, gutters, air vents, and all components associated with the system. Match existing color and specifications.

No on-site work shall begin until government approval of shop drawings and material submittals.

The contractor shall provide separation dust and construction barriers between occupied spaces during demolition and construction. The work area is to be cleaned on a daily basis along with any dust/debris that is transmitted into the corridor/shared areas of the facility and excess/ demolished materials are to be removed from Pittsburgh ARS to an approved landfill as part of this contract in contractor provided containers/trucks/trailers. Associated facility will be occupied by 911 personnel during construction.

D. Contractor Responsibilities: Verify all existing conditions, dimensions, and assemblies.

Include necessary exploratory work to verify concealed components. Repair and patch exploratory work as necessary.

E. Schedule: Provide a Work schedule showing area to be worked in, dates of work, and estimated time for completion of the project. Submit schedule to the Contracting Officer (CO) for approval and coordination. Coordinate proposed schedule 7 days in advance of work to be accomplished with the Construction Manager, who will make arrangements with the using agency. Work is to be performed to the satisfaction of the CO.

F. Contracting Officer’s Technical Representative: The Base Civil Engineer, 911 Airlift Wing, or his designated representative, is designated the Technical Representative of the Contracting Officer for the purpose of technical supervision, inspection, and acceptance of services to be rendered under this contract.

G. Construction On-site Start: The Government must specifically approve, in writing, any on –site construction activities to begin before Government approval.

J. Construction Specifications: The following attached specifications will be followed by the contractor during all construction work.

01 14 00 Work Restrictions

01 32 00 Construction Progress Documentation

01 34 00 Submittal Procedures

01 40 00 Quality Requirements

01 41 00 Environmental Protection

01 50 00 Temporary Facilities and Controls

01 59 50 Safety Requirements

01 73 00 Closeout Procedures

01 73 89 Cutting and Patching

02 41 19 Selective Demolition

BASE LOCATION MAP

***END OF STATEMENT OF WORK***