1-Hi-Country Fire Hydrant Replacement Project Manual IFB 09.04.26 (1).docx
DOCX document 1 MB Posted
- Solicitation number
- RA27-112
- Issued by
- Salt Lake County, Utah
About this file
This is a Project Manual and Invitation for Bids (IFB) issued by the Hi-Country Estates Homeowners Association in Herriman, Utah, prepared by Sunrise Engineering, Inc., for the removal and replacement of fifteen fire hydrants within the Hi-Country Estates Phase 1 water distribution system. The project encompasses twenty bid items including fire hydrant assemblies, PVC pipe in various sizes (6-inch, 8-inch, and 10-inch), gate valves, tees for connections to existing mains, pipe zone backfill, trench backfill, asphalt removal and patching, road base installation, landscape restoration, and related construction services. Bids must be submitted in person at the Sunrise Engineering Office, 6875 S 900E Street, Midvale, Utah 84047, by 3:00 PM local time on Tuesday, September 29, 2026. A non-mandatory pre-bid conference is scheduled for Thursday, September 17, 2026, at 10:00 AM via Microsoft Teams. Prospective bidders are encouraged to conduct site visits and may submit questions to angela.xia@sunrise-eng.com until 5:00 PM on September 24, 2026. The successful bidder must substantially complete the work within 100 calendar days and achieve final completion within 130 calendar days from the contract commencement date.
The contract will be awarded on a lump sum basis with unit pricing for individual bid items. Bidders must submit a bid security equal to 5 percent of the maximum bid price in the form of a bid bond. The contractor must provide performance bonds, payment bonds, and insurance documentation as specified in the General Conditions. Progress payments will be made monthly at 95 percent of completed work value, with 5 percent retained until substantial completion. Upon substantial completion, payment will increase to 100 percent less a contingency for punch list items. Liquidated damages are assessed at $500 per calendar day for delays in achieving substantial completion and $100 per calendar day for delays in final completion. Bidders must demonstrate qualifications including proof of completing five similar projects within the last five years, valid state contractor licensing, evidence of authority to do business in Utah, and financial statements. The contract documents include the general conditions, supplementary conditions, Utah APWA reference specifications, Herriman City Standards and Specifications Manual (8th Edition, 2024), and Salt Lake County wage determinations for heavy and building construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-Hi-Country Fire Hydrant Replacement Plan Set IFB 09.04.26 (1).pdf | ||
| 3-Pre-bid Mtg Attendance Log ADA.docx | DOCX document | |
| 6-Addendum 2.docx | DOCX document | |
| 4-HCE1 Fire Hydrant Pre-Bid meeting Agenda and Notes .docx | DOCX document | |
| 5-Addendum 1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUNRISE
ENGINEERING
Hi-Country Estates Homeowners Association Fire Hydrant Replacement Project
PROJECT MANUAL
PROJECT MANUAL
for the
Hi-Country Estates Homeowners Association Fire Hydrant Replacement
Prepared by: Sunrise Engineering, Inc.
6875 S 900 E Midvale, Utah 84047 Tel: (801) 523-0100
TABLE OF CONTENTS
FOR
Hi-Country Estates Homeowners Association Fire Hydrant Replacement Project
CONTRACT DOCUMENTS AND SPECIFICATIONS FOR CONSTRUCTION
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
| C111 | Advertisement for Bids C200 | Instructions to Bidders C410 | Bid Form |
| C430 | Bid Bond (Penal Sum) C451 | Qualifications Statement C510 | Notice of Award |
| C520 | Agreement Between Owner and Contractor for Construction Contract C550 | Notice to Proceed | |
| C610 | Performance Bond C612 | Warranty Bond | |
| C615 | Payment Bond | ||
| C620 | Application for Payment | ||
| C625 | Certificate of Substantial Completion C626 | Notice of Acceptability | |
| C700 | General Conditions | ||
| C800 | Supplementary Conditions C940 | Work Change Directive C941 | Change Order |
| C942 | Field Order |
UTAH APWA (2026) REFERENCE SPECS
DIVISION 01 - GENERAL REQUIREMENTS
| 01 11 00 |
| Summary of Work |
| 01 25 00 |
| Product Options and Substitutions |
| 01 26 00 |
| Contract Modification Procedure |
| 01 29 00 |
| Payment Procedures |
| 01 31 13 |
| Coordination |
| 01 31 19 |
| Preconstruction Conference |
| 01 31 20 |
| Partnering |
| 01 32 16 |
| Progress Schedule |
| 01 33 00 |
| Submittal Procedure |
| 01 35 10 |
| Acceptance |
| 01 42 19 |
| References |
| 01 43 00 |
| Quality Assurance |
| 01 43 40 |
| Resident Superintendent |
| 01 45 00 |
| Quality Control |
| 01 55 26 |
| Traffic Control |
| 01 57 00 |
| Temporary Controls |
| 01 64 00 |
| Owner-furnished Products |
| 01 65 00 |
| Product Delivery and Handling |
| 01 66 00 |
| Product Storage and Protection |
| 01 71 13 |
| Mobilization and Demobilization |
| 01 71 23 |
| Construction Layout |
| 01 71 34 |
| Survey Referencing |
| 01 73 29 |
| Cutting and Patching |
| 01 74 13 |
| Progress Cleaning |
Sunrise Engineering, Inc.
Project Manual for Hi-Country Estates Homeowners Association Fire Hydrant Replacement 2026 August XX, 2026 Table of Contents Page iii
01 75 16 Startup Procedures 01 78 23 Operation and Maintenance Data 01 78 39 Project Record Documents 01 78 50 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS
02 41 14 Pavement Removal 02 41 15 Curb and Trip Hazard Removal
DIVISION 03 - CONCRETE
03 30 04 Concrete 03 30 05 Concrete Testing 03 30 10 Concrete Finishing
DIVISION 31 - EARTH WORK
| 31 05 13 |
| Common Fill |
| 31 11 00 |
| Site Clearing |
| 31 23 16 |
| Excavation |
| 31 23 26 |
| Compaction |
| 31 25 00 |
| Erosion and Sedimentation Control |
| 31 41 00 |
| Shoring |
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base Courses 32 12 03 Asphalt Binder 32 12 05 Bituminous Concrete 32 12 13.13 Tack Coat 32 12 13.19 Prime Coat 32 16 13 Driveway, Sidewalk, Curb, Gutter 32 17 23 Pavement Markings 32 92 00 Turf and Grass
DIVISION 33 – UTILITIES
| 33 05 14 |
| Utility Grade Adjustment |
| 33 05 20 |
| Backfilling Trenches |
| 33 05 25 |
| Pavement Restoration |
| 33 08 00 |
| Commissioning of Water Utilities |
| 33 11 00 |
| Water Distribution and Transmission |
| 33 12 16 |
| Water Valves |
| 33 12 19 |
| Hydrants |
SPECIAL PROVISIONS
02 41 20 SP Utility Investigation 32 94 00 SP Landscaping
HERRIMAN CITY STANDARDS & SPECIFICATIONS MANNUAL (8TH EDITION, 2024)
SALT LAKE CO WAGE DETERMINATIONS (HEAVY & BUILDING) 2ND ROUND REDERAL BOILERPLATE
General Notice
ADVERTISEMENT FOR BIDS
HI-COUNTRY ESTATES HOMEOWNERS ASSOCIATION HERRIMAN, UT
Hi-Country Fire Hydrant Replacement 2026
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
The Hi-Country Estates Homeowners Association (Owner) is requesting Bids for the construction of the following Project:
Hi-Country Fire Hydrant Replacement 2026
Bids for the construction of the Project will be received at the Sunrise Engineering Office located at 6875 S 900E St, Midvale, UT 84047, until Tuesday, September 29, 2026 at 3:00 PM local time. At that time, the Bids received will be publicly opened and read. Electronic bids will not be accepted.
The Project includes the following Work:
Removal and replacement of fifteen (15) fire hydrants within the Hi-Country Estates Phase 1 water distribution system.
Obtaining the Bidding Documents Information and Bidding Documents for the Project can be found at the State Division of Purchasing website.
Bidding Documents may be downloaded from the designated website. Prospective Bidders are urged to register with the designated website as a plan holder, even if Bidding Documents are obtained from a plan room or source other than the designated website in either electronic or paper format. The designated website will be updated periodically with addenda, lists of registered plan holders, reports, and other information relevant to submitting a Bid for the Project. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website.
Pre-bid Conference A optional pre-bid conference for the Project will be held on Thursday, September 17, 2026 at 10:00 AM at https://teams.microsoft.com/meet/247086321008178?p=QPQqOWrbZ347dUeSH7. Meeting ID: 247 086 321 008 178 Passcode: LN22HN9Z Attendance at the pre-bid conference is encouraged but not required.
Instructions to Bidders.
For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.
This Advertisement is issued by:
Owner: Hi-Country Estates Homeowners Association
| By: | Paul Dahle |
| Title: | Vice President |
| Date: | September 04, 2026 |
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
| Article 1— Defined Terms | 1 |
| Article 2— Bidding Documents | 1 |
| Article 3— Qualifications of Bidders | 2 |
| Article 4— Pre-Bid Conference | 3 |
| Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program; Other Work at the Site | 3 |
| Article 6— Bidder’s Representations and Certifications | 5 |
| Article 7— Interpretations and Addenda | 5 |
| Article 8— Bid Security | 6 |
| Article 9— Contract Times | 6 |
| Article 10— Substitute and “Or Equal” Items | 6 |
| Article 11— Subcontractors, Suppliers, and Others | 7 |
| Article 12— Preparation of Bid | 8 |
| Article 13— Basis of Bid | 9 |
| Article 14— Submittal of Bid | 9 |
| Article 15— Modification and Withdrawal of Bid | 9 |
| Article 16— Opening of Bids | 10 |
| Article 17— Bids to Remain Subject to Acceptance | 10 |
| Article 18— Evaluation of Bids and Award of Contract | 10 |
| Article 19— Bonds and Insurance | 11 |
| Article 20— Signing of Agreement | 12 |
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
TOC Page1 of 1
ARTICLE 1—DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.
2.04 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents, or make them available for examination. Those prospective bidders that obtain an electronic (digital) copy of the Bidding Documents from a plan room are encouraged to register as plan holders from the Bidding Documents Website or Issuing Office. Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.
2.05 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader Version 11.0 or later. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.05.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.
ARTICLE 3—QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within 10 days of Owner’s request, Bidder must submit the following information:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Bidder’s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
F. Proof of completing five similar projects in size and scope within the last five years.
3.02 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Bidder’s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
3.03 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.04 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A non mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project.
4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
5.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:
a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.
b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.
c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion
Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
5.03 Other Site-related Documents
A. In addition to the documents regarding existing Site conditions referred to in Paragraph 5.02.A, the following other documents relating to conditions at or adjacent to the Site are known to Owner and made available to Bidders for reference:
1. None Owner will make copies of these other Site-related documents available to any Bidder on request.
B. Owner has not verified the contents of these other Site-related documents, and Bidder may not rely on the accuracy of any data or information in such documents. Bidder is responsible for any interpretation or conclusion Bidder draws from the other Site-related documents.
C. The other Site-related documents are not part of the Contract Documents.
D. Bidders are encouraged to review the other Site-related documents, but Bidders will not be held accountable for any data or information in such documents. The requirement to review and take responsibility for documentary Site information is limited to information in (1) the Contract Documents and (2) the Technical Data.
E. No other Site-related documents are available.
5.04 Site Visit and Testing by Bidders
A. Bidder is encouraged to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.
B. Bidders visiting the Site are required to arrange their own transportation to the Site.
C. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner or Engineer contact for visiting the Site: hce1dahle@gmail.com. Bidder are must conduct the optional Site visit during normal working hours.
D. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.
E. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.
F. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
G. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
5.05 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.
5.06 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
ARTICLE 7—INTERPRETATIONS AND ADDENDA
7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows:
A. Question shall be submitted in writing via email to angela.xia@sunrise-eng.com.
B. Phone: (385)-232-4657
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received after September 24th, 2026 at 5:00 pm, may not be answered.
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.
ARTICLE 8—BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of five (5) percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
ARTICLE 9—CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment are set forth in the Agreement.
9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
10.02 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders. Bidders cannot rely upon approvals made in any other manner.
10.03 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the Work within five days after Bid opening.
11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.
ARTICLE 12—PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents.
A. All blanks All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.”
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.
12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.
12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.
12.06 A Bid by an individual must show the Bidder’s name and official address.
12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.08 All names must be printed in ink below the signatures.
12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.
ARTICLE 13—BASIS OF BID
13.01 Lump Sum
A. Bidders must submit a Bid on a lump sum basis as set forth in the Bid Form.
13.02 Base Bid with Alternates
A. Bidders must submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form. The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.
B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.
13.03 Unit Price
A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
13.04 Allowances
A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
ARTICLE 14—SUBMITTAL OF BID
14.01 All bids must be submitted, to the Sunrise Engineering Office, on or before the day and hour set forth in the Advertisement to Bid. Bids will not be accepted after that time.
14.02 Electronic bids will not be accepted.
ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID
15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.
15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.
15.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.
ARTICLE 16—OPENING OF BIDS
16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE
17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.
18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.
18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.
18.05 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.
B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form. To determine the Bid prices for purposes of comparison, Owner will announce to all bidders a “Base Bid plus alternates” budget after receiving all Bids, but prior to opening them. For comparison purposes alternates will be accepted, following the order of priority established in the Bid Form, until doing so would cause the budget to be exceeded. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and any combination of its additive alternate Bids for which Owner determines funds will be available at the time of award.
C. For determination of the apparent low Bidder(s) when sectional bids are submitted, Bids will be compared on the basis of the aggregate of the Bids for separate sections and the Bids for combined sections that result in the lowest total amount for all of the Work.
D. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
E. For the determination of the apparent low Bidder when cost-plus-fee bids are submitted, Bids will be compared on the basis of the Guaranteed Maximum Price set forth by Bidder on the Bid Form.
F. Bid prices will be compared after adjusting for differences in time of Substantial Completion (total number of calendar days to substantially complete the Work) designated by Bidders. The adjusting amount will be determined at the rate set forth in the Agreement for liquidated damages for failing to achieve Substantial Completion, or such other amount that Owner has designated in the Bid Form.
1. The method for calculating the lowest bid for comparison will be the summation of the Bid price shown in the Bid Form plus the product of the Bidder-specified time of Substantial Completion in calendar days times the rate for liquidated damages $500.00 in dollars per day.
2. This procedure is only used to determine the lowest bid for comparison and contractor selection purposes. The Contract Price for compensation and payment purposes remains the Bid price shown in the Bid Form.
18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 19—BONDS AND INSURANCE
19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.
ARTICLE 20—SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
BID FORM FOR CONSTRUCTION CONTRACT
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
I. OWNER AND BIDDER
a. This Bid is submitted to: Hi-Country Estates Homeowners Association 5355 W Main Herriman, UT 84096
b. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
II. ATTACHMENTS TO THIS BID
a. The following documents are submitted with and made a condition of this Bid:
i. Required Bid security;
ii. List of Proposed Subcontractors;
iii. List of Proposed Suppliers;
iv. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids;
v. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids;
vi. Required Bidder Qualification Statement with supporting data; and
vii. Form C-410a – Bid Schedule
III. BASIS OF BID—LUMP SUM BID AND UNIT PRICES
i. Bidder will complete the Work at the indicated unit prices:
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
| BID ITEM |
| DESCRIPTION |
| BID UNIT |
| BID QUANTITY |
| UNIT PRICE |
| BID AMOUNT |
| 1 |
| Fire Hydrant Assembly |
| EA |
| 15 |
| 2 |
| 6" PVC C900 Hydrant Lateral Pipe |
| LF |
| 510 |
| 3 |
| 6" Gate Valve & Assembly |
| EA |
| 15 |
| 4 |
| 6" x 6" Tee (connection to ex main) |
| EA |
| 7 |
| 5 |
| 6" C900 PVC Pipe |
| LF |
| 280 |
| 6 |
| 8" x 6" Tee (connection to ex main) |
| EA |
| 6 |
| 7 |
| 8" C900 PVC Pipe |
| LF |
| 240 |
| 8 |
| 10" x 6" Tee (connection to ex main) |
| EA |
| 2 |
| 9 |
| 10" C900 PVC Pipe |
| LF |
| 80 |
| 10 |
| Pipe Zone Backfill (3/8" Bedding Sand) |
| TONS |
| 344 |
| 11 |
| Trench Backfill (2" Minus A-1-a) |
| TONS |
| 518 |
| 12 |
| Asphalt Removal |
| SY |
| 450 |
| 13 |
| Asphalt Patch (1/2", PG58-28) |
| TON |
| 98 |
| 14 |
| APWA Road Base (8" THK) |
| TON |
| 235 |
| 15 |
| Landscape Restoration |
| EA |
| 15 |
| 16 |
| Ex Fire Hydrant Removal |
| EA |
| 15 |
| 17 |
| Quality Control |
| LS |
| 1 |
| 18 |
| Mobilization |
| LS |
| 1 |
| 19 |
| Subsurface Investigation |
| HRS |
| 42 |
| 20 |
| Traffic Control |
| LS |
| 1 |
ii. Bidder acknowledges that:
1. Each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and
2. Estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.
iii. Measurement and Payment
1. FIRE HYDRANT ASSEMBLY, Bid Item No. 1
a. Measurement will be made by actual count per each installed (EA).
b. Payment covers furnishing all labor, equipment, and all incidental materials necessary for a complete fire hydrant assembly installation as shown on the plans and specified in the contract documents, including concrete pad, sewer rock, geotextile fabric thrust block, geotextile wrap, bends and poly wrap. (Refer to Section 33 12 19, Hydrants, and Herriman City Engineering Detail CW-15)
2. 6-INCH PVC C900 HYDRANT LATERAL PIPE, Bid Item No. 2
a. Measurement will be made by linear foot (LF) with no deduction for fittings, valves, or appurtenances.
b. Payment covers furnishing and installing pipe, tracer wire, magnetic marker tape, transportation, laying, jointing, restraint systems, fittings not paid for separately, and all labor, materials, and equipment required for a complete installation unless otherwise specified. (Refer to Section 33 11 00, Water Distribution and Transmission.)
3. 6-INCH GATE VALVE & ASSEMBLY, Bid Item No. 3
a. Measurement will be made by actual count per each installed (EA).
b. Payment covers furnishing and installing the gate valve, valve box, extension stem (if required), restraints, thrust block, foundation preparation, adjustment to final grade, and all labor, materials, and equipment necessary for a complete installation. (Refer to Section 33 12 16, Water Valves, and Herriman City Engineering Detail CW-08)
4. 6-INCH x 6-INCH TEE (CONNECTION TO EXISTING MAIN), Bid Item No. 4
a. Measurement will be made by actual count per each installed (EA).
b. Payment covers furnishing and installing tee fittings, connection to existing water main, romac coupling, tracer wire, magnetic marker tape, restraints, thrust blocking, dewatering, fittings, couplings and all labor, materials, and equipment necessary to complete the connection. (Refer to Section 33 11 00, Water Distribution and Transmission, Herriman City Engineering Detail CW-15 and detail A sheet C-1)
5. 6” C900 PVC PIPE, Bid Item No. 5
a. Measurement will be made by linear foot (LF) of pipe installed and accepted, measured along the centerline of the pipe, with no deduction for fittings, valves, or appurtenances
b. Payment covers furnishing and installing 6-inch C900 PVC pipe, including, laying, jointing, fittings, couplings, tracer wire, locator tape, excavation, dewatering, thrust restraint, poly wrap where required, and all labor, materials, tools, and equipment necessary for a complete installation. Payment also includes all incidental work required to place the pipeline into service, including retesting, additional flushing, and corrective work required due to failure to meet contract requirements. (Refer to Section 33 11 00, Water Distribution and Transmission.)
6. 8-INCH x 6-INCH TEE (CONNECTION TO EXISTING MAIN), Bid Item No. 6
a. Measurement will be made by actual count per each installed (EA).
b. Payment covers furnishing and installing tee fittings, connection to existing water main, romac coupling, tracer wire, magnetic marker tape, restraints, thrust blocking, dewatering, fittings, couplings and all labor, materials, and equipment necessary to complete the connection. (Refer to Section 33 11 00, Water Distribution and Transmission, Herriman City Engineering Detail CW-15 and detail A sheet C-1)
7. 8” C900 PVC PIPE, Bid Item No. 7
a. Measurement will be made by linear foot (LF) of pipe installed and accepted, measured along the centerline of the pipe, with no deduction for fittings, valves, or appurtenances
b. Payment covers furnishing and installing 8-inch C900 PVC pipe, including, laying, jointing, fittings, couplings, tracer wire, locator tape, excavation, dewatering, thrust restraint, poly wrap where required, and all labor, materials, tools, and equipment necessary for a complete installation. Payment also includes all incidental work required to place the pipeline into service, including retesting, additional flushing, and corrective work required due to failure to meet contract requirements. (Refer to Section 33 11 00, Water Distribution and Transmission.)
8. 10-INCH x 6-INCH TEE (CONNECTION TO EXISTING MAIN), Bid Item No. 8
a. Measurement will be made by actual count per each installed (EA).
b. Payment covers furnishing and installing tee fittings, connection to existing water main, romac coupling, tracer wire, magnetic marker tape, restraints, thrust blocking, dewatering, fittings, couplings and all labor, materials, and equipment necessary to complete the connection. (Refer to Section 33 11 00, Water Distribution and Transmission, Herriman City Engineering Detail CW-15 and detail A sheet C-1)
9. 10” C900 PVC PIPE, Bid Item No. 9
a. Measurement will be made by linear foot (LF) of pipe installed and accepted, measured along the centerline of the pipe, with no deduction for fittings, valves, or appurtenances
b. Payment covers furnishing and installing 10-inch C900 PVC pipe, including, laying, jointing, fittings, couplings, tracer wire, locator tape, excavation, dewatering, thrust restraint, poly wrap where required, and all labor, materials, tools, and equipment necessary for a complete installation. Payment also includes all incidental work required to place the pipeline into service, including retesting, additional flushing, and corrective work required due to failure to meet contract requirements. (Refer to Section 33 11 00, Water Distribution and Transmission.)
10. PIPE ZONE BACKFILL (3/8” BEDDING SAND), Bid Item No. 10
a. Measurement will be made by tons (TONS) of material installed and accepted.
b. Payment covers furnishing, hauling, placement, moisture conditioning, compaction, and testing of approved pipe zone backfill material within the limits shown on the plans. No payment will be made for material placed outside the specified pipe zone limits. (Refer to Section 33 05 20, Backfilling Trenches, and Herriman City Engineering Detail CW-02)
11. TRENCH BACKFILL (2” MINUS A-1-a), Bid Item No. 11
a. Measurement will be made by tons (TONS) of material installed and accepted.
b. Payment covers furnishing, hauling, placement, moisture conditioning, compaction, testing, and all labor, materials, and equipment required for trench backfill above the pipe zone to finished subgrade. (Refer to Section 33 05 20, Backfilling Trenches, and Herriman City Engineering Detail CW-02)
12. ASPHALT REMOVAL, Bid Item No. 12
a. Measurement will be made by square yard (SY) of asphalt removed.
b. Payment covers saw-cutting, removal, loading, hauling, disposal of asphalt pavement, surface preparation, and all labor, materials, and equipment necessary to complete the work. (Refer to Section 02 41 14, Pavement Removal, and Herriman City Engineering Detail CW-02)
13. ASPHALT PATCH (1/2”, PG58-28), Bid Item No. 13
a. Measurement will be made by tons (TON) of asphalt placed and accepted.
b. Payment covers furnishing asphalt materials, tack coat, hauling, placement, compaction, testing, and all labor, materials, and equipment required to restore pavement sections to the dimensions and thickness shown on the plans. (Refer to Section 33 05 25, Pavement Restoration, and Herriman City Engineering Detail CW-02)
c. Asphalt restoration is anticipated to consist of trench patching. If field conditions require a full-depth T-patch and such work is approved by the OWNER and ENGINEER, payment will be made for the actual quantity of asphalt furnished, placed, and accepted. No distinction in measurement will be made between trench patch and T-patch restoration.
14. APWA ROAD BASE (8”THK),…