1. Statement of Work.pdf
PDF 307 KB Posted
- Solicitation number
- 127EAW22R0004
- Issued by
-
Department of Agriculture Forest Service
About this file
This federal solicitation is for road maintenance services on 59 miles of paved roads and 14.5 miles of unpaved roads within the Eldorado National Forest in California, to address damage from the 2021 Caldor Fire. Work includes debris removal, ditch and shoulder reconditioning, road surface grading, drainage feature reconstruction, and installation of rolling dips, culverts, and riprap. The total small business set-aside contract value is estimated between $250,000 to $500,000.
The statement of work specifies a 90-calendar day period of performance beginning no later than March 28, 2022. A pre-bid site visit will be held on December 7, 2021 and questions are due by December 13, 2021. The selected contractor must begin work within 10 days of the January 31, 2022 notice to proceed. Performance will be inspected by the U.S. Forest Service and payment will be made through the Invoice Processing Platform system upon acceptance of completed work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Official Responses - 2.pdf | ||
| RFI Official Responses - 1.pdf | ||
| Amendment - A00001.pdf | ||
| RFI Official Responses - 3.pdf | ||
| 127EAW22R0004 - Caldor Fire BAER Road Maintenance - Phase 1.pdf | ||
| 4. Maps.pdf | ||
| 6. Roads List.pdf | ||
| 5. Plans.pdf | ||
| 3. FP14 FSSS - Caldor Fire Phase I Road Stormproofing.pdf | ||
| 8. RFI Form.docx | DOCX document | |
| 2. Fire Plan.pdf | ||
| 7. Davis-Bacon Act WD # CA20210007.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - STATEMENT OF WORK - SUPPLEMENTAL
C.1 Project Scope
This project is located int the state of California, El Dorado County, Eldorado National Forest. The purpose of this project is to provide post-fire road maintenance and drainage restoration on roads within or near the Caldor Fire perimeter on the Eldorado National Forest. Maintenance of these Forest Service roads includes:
• Furnish all labor, equipment and material to accomplish the work under this task order.
• Road reconditioning on 59 miles of paved roads. Paved road reconditioning consists of debris removal, ditch reconditioning and shoulder reconditioning. No pavement maintenance is included in this scope.
• Road reconditioning on 14.5 miles of unpaved roads. Unpaved road reconditioning consists of debris removal, ditch reconditioning, shoulder reconditioning and surface303 reconditioning in accordance with Section 303. This work includes watering and grading the road surface to match the existing roadway template.
• Unplug, clean, and reconstruction of roadway drainage features (rolling drainage dips, ditches, ditch relief and cross drainage culverts, and overside drains) to re-establish effective free flowing drainage of all raodway features, and reduce the potential of any culvert(s) becoming blocked during storm events.
• Install new rolling dips for roadway surface drainage where specified.
• Install culvert inlet end sections and risers wherespecified.
• Install rip rap for inlet and roadway protection where specified.
The Contractor should refer to the SCHEDULE OF ITEMS and project plans and specifications when making estimates of quantities or work.
C.2 Project Location & Description
Location: Project roads are located within Eldorado National Forest, El Dorado County, California.
Project roads are best accessed from CA HWY 50 or 88. A KML file and georeferenced pdf map with road locations will be provided to assist contractors with bidding and execution of work.
Maps included in Section J are general in nature and are not to be considered as definitively identifying locations.
C.3 Pre-Bid Tour/ Conference
A pre-bid tour of the closed areas within the scope of work shall be held on:
Contact: Rocio Espinoza – Civil Engineer rocio.espinoza@usda.gov 530-503-5089
Date: December 7th, 2021 mailto:rocio.espinoza@usda.gov
Caldor Fire BAER Road Maintenance, Phase 1 Eldorado National Forest
Time: 10:00 AM PST
Location: Placerville District Office
4260 Eight Mile Road
Questions may be directed to Alvin Sarmiento at alvin.sarmiento@usda.gov or (530) 708-1363
C.4 Estimated Start Date & Contract Time
Desired start work / NTP issuance date of January 31st, 2022 but work shall not start later than March 28th, 2021. Contract Period of Performance will be 90 days.
Contract time includes delays, demobilization and remobilization for potential weather delays; locating and transporting supplies and materials; and final site cleanup.
C.5 Restrictions on Work
Work may be performed at any time during the period of the contract, except as outlined here. Nothing in this part shall be construed to take away any of the Government's rights under the Suspension of Work Clause (52.242-14). Restrictions are as follows:
1. In accordance with the fire plan, if included in Section J.
2. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
C.6 Licenses and Insurance
The contractor shall obtain the insurance and licenses listed here.
Worker’s Compensation Insurance: The Contractor shall provide evidence of Worker’s Compensation Insurance or a valid reason that exempts the Contractor from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.
If the contractor fails to provide the documentation within 10 calendar days after contract time begins, the contract may be terminated for cause in accordance with FAR 52.212-4.
MSPA Card (Form WH510): This contract [ ] does [X ] does not require the contractor to be registered with the US Department of Labor as a Farm Labor Contractor. The Contractor shall provide a current Form WH510 or legible copy.
C.7 Specifications and Drawings
In addition to the specifications which are part of the base contract, the following specifications and drawings apply:
a) Drawings/Plans for Caldor Fire BAER Road Maintenance, Phase 1.
b) Fire plan for construction contracts.
c) "Standard Specifications for Construction of Roads & Bridges of Federal Highway Projects" (FP-
14, U.S. Customary Units) are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made part of this solicitation and any resultant contract.
mailto:alvin.sarmiento@usda.gov
d) The Supplemental Project Specifications listed in the Supplemental Specification List are applicable to this contract and are physically included in this Section (C).
Note that the specification list includes the primary specifications applicable to this project. All specifications referenced to within these specifications (even though not specifically listed herein) are fully applicable to this task order and any resultant contract.
Forest Service Supplemental Specifications (FSSS) Spec. No.
101 Term, Format and Definition
102 Bid, Award and Execution of Contract
103 Scope of Work
104 Control of Work
105 Control of Material
106 Acceptance of Work
107 Legal Relations and Responsibility to the Public
108 Prosecution and Progress
109 Measurement and Payment
155 Schedule for Construction Contracts
156 Public Traffic
201 Clearing and Grubbing
204 Excavation and Embankment
303 Road Reconditioning
C.8 Product Submittals
Title Referenced Specification No.
Project Safety Plan FP-14 107
Traffic Control Plan FP-14 156
Riprap Composition FP-14 251
SECTION E. INSPECTIONS AND ACCEPTANCE
E.1 Government Inspections
Government inspections are for the purpose of satisfying the Government that the services are acceptable and do not relieve the Contractor of the responsibility for maintaining quality control.
The Contracting Officer's Representative or designated inspector will conduct all inspections. The Contractor (or designated representative) is encouraged to be present to observe inspections. Summary results will be made available on request.
Compliance Inspections. Visual compliance inspections will be made on a periodic basis. Such inspections are not final and do not constitute acceptance by the Government.
Final Inspections. Final (formal) inspections for payment will be made on completed sub-items only.
Contractor shall request final inspections in writing and give the Forest Service at least two working days advanced notice. Inspections will be completed within four working days after the notice is received. If the work is not ready for inspection at the time specified by the Contractor, the cost associated with the inspection attempt may be charged to the Contractor.
Disputed Inspection. The Contractor may request re-inspection without rework if the results are unacceptable. Re-inspection must be requested in writing within 48 hours after receiving written notice of the inspection results. Re-inspection will be accomplished within five working days after receipt of the contractor's written request.
The same sampling and inspection procedures will be used, but new samples will be taken. The inspection pattern will be shifted so that new samples will not overlap previously inspected samples.
Results will be rounded to the nearest whole percent.
If re-inspection results are within five percentage points of the first inspection, the original inspection result will be used in determining acceptability and payment. If re-inspection results are greater than five percentage points above or below the first inspection, the re-inspection results will be used.
If the re-inspection results are within five percentage points of the first inspection, the Contractor shall pay the actual costs of the re-inspection.
Re-inspection after Rework. Where rework after a failed inspection may improve the inspection results, the Contractor may rework the area and request (in writing) a second inspection. The Government will charge to the Contractor the cost of this additional inspection. Re-inspection will be accomplished within five working days after the notice is received. The results of the second inspection will be final, and no further rework will be permitted. Areas not ready for re-inspection at the time specified by the Contractor will not be re-inspected, and the results of the first inspection will be final.
F. DELIVERIES OR PERFORMANCE
F.1 Work Timing
The Contractor shall begin work within 10 calendar day after the effective date of the Notice to Proceed and shall prosecute the work at a rate that will result in completion of all work within the following time frame:
Item No. Est. Start Work Contract Time (Calendar Days)
1 March 28th, 2022 60
Failure to begin work on schedule will make the contract subject to immediate termination for default.
Delays due to normal adverse weather, weekends, and holidays have been included in the calculation of contract time. The Government reserves the right to set the priority of items or sub-items.
If this solicitation has more than one numbered item, award of more than one item to one contractor will not change the start work dates or the amount of contract time; times will run concurrently.
F.2 Winter Shutdown
When winter weather sets in and the continuation of work is impractical, the Contracting Officer may authorize a total suspension until such time as work can proceed. During the period of total suspension, the calendar days elapsed will not be charged against the contract time.
SECTION G. CONTRACT ADMINISTRATION DATA
G.1 Pre-work
Pre-work conference. Before work begins on service contracts, a pre-work conference is normally held to discuss the contract – especially the specifications, labor provisions, plan of work, and selected standard clauses. The pre-work meeting should be attended by an officer of the firm or someone designated in writing to act on behalf of the firm. The pre-work meeting may be waived at the discretion of the Contracting Officer.
Notice to Proceed.
A. [ x] No work may begin on this contract until the Contracting Officer has issued a Notice to Proceed.
G.2 Measurement
Methods of Measurement.
[X ] Linear measurements have been estimated from GIS
Re-measurement. Unless otherwise indicated by this contract, the contractor may request re-measurement of any quantities in Part B, when the units are acres or any linear measurement.
The request must be made in writing and must be made within 10 calendar days of completing work on the unit in question. If re-measurement indicates a variance of five percent or less from the stated quantity, the Contractor shall pay for the actual cost of re-measurement and no adjustment will be made in the quantity as stated in Part B. If re-measurement indicates a variance more than five percent from the stated quantity, payment will be based on the re-measured quantity, and the Contractor will not be liable for the costs of re-measurement. All re-measurements will be done by the Government. Re-measurement of acreage will be done with two people using a hand compass and ground measurement or by means of a Global Positioning System. This clause is not applicable to quantities listed as estimated quantities.
G.3 Payment
Payments and Deductions. Payment will be made for fully acceptable work at the prices bid in the schedule of items. In the event of extended non-work periods because of adverse weather, the Contracting Officer may authorize progress payments for partially completed sub-items on a case-by- case basis. In accordance with the inspection clause, payment may be made for less than fully acceptable work at a reduced price. Other exceptions are noted below:
Payment will be made in full after final inspection identifies 100 percent of the work meets contract requirements. No payment will be made if inspection results are less than 100 percent.
Contract Release. Before final payment will be made the Contractor shall sign a release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.
A Contract Release FS-6300-0016 must be uploaded with request/invoice for final payment in IPP, before final payment will be approved/completed.
A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C.
3727 and 41 U.S.C. 15).
G.3-1 Invoice Processing Platform (IPP)
All payment requests must be submitted electronically through the US Department of the Treasury’s Invoice Processing Platform System (IPP). “Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov. Under this contract, the following documents are required to be submitted as an attachment to the IPP Invoice:
Each invoice shall be submitted on the Contractor’s letterhead or invoice form with the following:
1. Invoice date and Government Contract Number.
2. Billing period specified with beginning and ending dates. The beginning date must not be later than the completion date or within any previous billing dates.
3. An accounting (bulleted list, for example) of charges claimed and amounts due.
4. Total amount due for the billing period.
A Progress Report shall be submitted to support each invoice and shall include a summary of work performed during the period of performance identified on the invoice, which at a minimum must include:
1. Description of the previous month’s project activities and the planned activities for the next month.
2. For each deliverable: identify the items supplied during the month and the cumulative items delivered.
3. Reconcile progress of each deliverable with the schedule identified for each.
4. Identify issues and/or concerns that may affect the project or schedule.
5. Any other information required in the Contract to be included in the Progress Report.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 – 5 business days of award or the system implementation date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131. If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
G.4 CONTRACTING OFFICER’S REPRESENTATIVE
Name: Alvin Sarmiento
The Contracting Officer designates the Contracting Officer's Representative (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the
Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task https://www.ipp.gov/ assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms, the Contractor must communicate with the
Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
SECTION H. SPECIAL CONTRACT REQUIREMENTS
H.1 Emergencies
Fire Plan. See attached Fire Plan.
H.2 Archaeological and Historic Sites
Location of known archaeological, historic, or prehistoric materials – such as Native American sites or artifacts and/or historic mining, logging, or fur trapping remains protected by the American Antiquities Act (16 USC 433)--will be identified for the contractor before work commences.
H.3 Spill Plan
If the total oil or oil products storage exceeds 1,320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare and implement a Spill Prevention and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112), including certification by a registered professional engineer. The Contractor, under the direction of the Contracting Officer, or in the absence of said officer, acting independently, shall immediately take action to contain and clean up, without expense to the Government, all petroleum products spills on or in the vicinity of the project which are caused by the Contractor's employees directly or indirectly as a result of contract operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government for the containment and cleanup of petroleum products spills caused by Contractor's employees or resulting from contract operations. The Contractor shall immediately report all petroleum products spills to the Contracting Officer.
H.4 Equipment Cleaning
All off-road equipment used on this project shall be washed before moving into the project area so that the equipment is free of soil, seeds, vegetative material, or other debris that could contain or hold seeds of noxious weeds. “Off-road equipment” includes all logging and construction equipment and such brushing equipment as brush hogs, masticators, and chippers; it does not include log trucks, chip vans, service vehicles, water trucks, pickup trucks, and similar vehicles not intended for off-road use.
Equipment will be considered clean when visual inspection does not reveal soil, seeds, plant material, or other such debris. Disassembly of equipment components or specialized inspection equipment is not required. Contractor shall notify the Contracting Officer at least five days in advance of moving equipment in so that arrangements can be made for inspection.
If the project area is known to contain noxious weeds, the equipment shall be cleaned before moving to other Forest Service system lands which do not contain noxious weeds.
H.5 Final cleanup
Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.
H.6 Public officials not personally liable
There shall be no personal liability upon the Contracting Officer or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.
H.7 Designation of Contracting Officer’s Representative
The Contracting Officer designates the Contracting Officer's Representative (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
H.8 Approval of Subcontracting
The Contractor shall request approval from the Contracting Officer prior to entering into any subcontract arrangement. The subcontractor shall have the experience and be equipped for such work. The written notification shall include as a minimum:
1. The name, address and telephone number of the subcontractor;
2. The date upon which the subcontract was entered into and its duration;
3. A detailed description of the work being subcontracted including a listing of contract items, units, etc., as appropriate;
4. Documentation of the subcontractor's representative authority.
Subcontracting any portion of the contract shall not relieve the Prime Contractor of any responsibility under this contract. Any subcontract agreement shall contain all terms and conditions of the prime contract.
H.9 Certification of Compliance
Contractor shall certify compliance with specific fire precautionary measures included in the attached Fire Protection and Suppression Forms. The certification shall be made prior to commencement of work and shall be updated if at any time during performance the conditions change. The Government may conduct verification inspections to ensure Contractor's compliance.
H.10 Camping
Camping is not permitted in US Forest Service campgrounds. Contractor [ ] will [ X] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit. Any non-compliance will result in suspension of work until compliance is achieved.
SECTION J. LIST OF ATTACHMENTS
The following attachments are made a part of this solicitation and any resultant contract.
TITLE DESCRIPTION # OF PAGES
Fire Plan 9
Forest Service Supplemental Specifications (FSSS) 36
Caldor Fire BAER Road Maintenance Plans 17
Caldor Fire BAER Maintenance Phase 1 Road List 1
Caldor Fire Roads Contract Phase 1 KMZ 1