1. Statement of Work.pdf

PDF 916 KB Posted

Attached to
127EAW26Q0050 - Ash Creek Helispot Construction
Solicitation number
127EAW26Q0050
Issued by

About this file

Summary

This is a Statement of Work (SOW) for the Ash Creek Helispot Project – Phase 1, issued by the USDA Forest Service for the Shasta-Trinity National Forest in California. The project involves construction of Phase 1 elements of a permanent helipad at the Ash Creek Guard Station within the McCloud Ranger District to support wildfire response operations and improve aviation safety. The work scope includes clearing and grubbing, over-excavation, soil screening and recompaction, borrow excavation, fill placement, grading, aggregate base surfacing, reinforced concrete helipad construction (4000 psi PCC), water system modifications including 3" Schedule 80 PVC pipe installation, fire hydrant lateral installation with valves, electrical and telecommunications duct bank installation, and associated site preparation tasks. The contract performance period extends from September 1, 2026, to June 1, 2027, totaling 273 calendar days. Work hours are limited to Monday–Friday, 0700–1900 hours, with compliance required to applicable federal and state codes including California Building Code, Caltrans standards, and FP-14/24 specifications. The contractor must hold a valid California Class A General Contractor license and designate key personnel including a project manager, superintendent, safety officer, and qualified mechanical/plumbing personnel with demonstrated experience in heavy civil construction, waterline installation, concrete helipad construction, and AWWA testing procedures.

The contractor is responsible for all labor, materials, equipment, permits (except the Caltrans Right-of-Way permit provided by the government), mobilization, demobilization, and transportation. The work includes mandatory sediment control device installation, traffic control on Highway 89 per FP-14 Section 635, Caltrans Right-of-Way permit compliance, and compliance with the project Fire Plan. Deliverables required include baseline construction schedule, monthly schedule updates, submittal register, product submittals, construction work plan, health and safety plan, quality control plan, monthly progress reports, inspection and test reports, as-built drawings, operation and maintenance manuals, and warranty documentation. The project site is located near McCloud, California at coordinates 41.263417, -121.950764, accessible from Highway 89. Option tasks available include Class 2 Aggregate Base placement for the loop road and electrical and communications duct bank installation under the loop road. No security clearance is required, and all project documentation becomes government property upon completion.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

US Department of Agriculture (USDA)

U.S. Forest Service

Statement of Work

Ash Creek Guard Station – McCloud Ranger District

Ash Creek Helispot Project – Phase 1

Shasta-Trinity National Forest, Redding, CA

July 2026

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

Contents Project

General Information

1.0 Scope of Work

2.0 Background

3.0 Location

4.0 Estimated Start Date / Period of Performance

5.0 Drawings and Specifications

6.0 Restrictions on Work

6.0 Camping and Housing

7.0 Required Submittals

Contractor Requirements

8.0 Technical Requirements / Tasks

9.0 Government Furnished

10.0 Deliverables / Schedule

11.0 Travel

12.0 Contractor’s Key Personnel

13.0 Security Requirements

14.0 Data Rights

15.0 Site Visit

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

Project Ash Creek Helispot - Phase 1

General Information

1.0 Scope of Work

The contractor shall construct the Phase 1 elements of the Ash Creek Helispot located within the McCloud Ranger District, Shasta-McCloud Management Unit, Shasta-Trinity National Forest. Work includes clearing and grubbing, over-excavation, screening in-situ soils, re-compaction, borrow excavation, fill placement, grading, aggregate surfacing, construction of reinforced concrete helipad, water system modifications, potential electrical and telecom duct installation, and associated tasks described in the Project Plans.

Contractor shall provide all labor, materials, equipment, documentation, notifications, and transportation required for completing the work, including demolition, disposal, and installation unless specifically noted otherwise. Contractor shall comply with USFS-provided Caltrans Right-of-Way (ROW) permit for waterline construction. Electrical modifications may require coordination and a possible permit with Pacific Power. The Contractor is responsible for obtaining any additional permits that may be required during construction, although no additional permits have been identified for this project.

2.0 Background

The Forest Service is developing a permanent helipad at Ash Creek to support wildfire response operations and improve aviation safety. Phase 1 involves ground preparation, foundation construction, waterline upgrades, and initial utility placement needed prior to final build-out. Existing waterline infrastructure, Caltrans right-of-way requirements, and coordination with nearby campgrounds affect project planning and execution.

3.0 Location

From Redding, CA:

Take Interstate 5 north ~58 miles to the Hwy 89 exit toward McCloud. Continue ~25 miles east on Hwy 89. Project site is located just north of Hwy 89 at 41.263417, -121.950764, across from the Ash Creek Guard Station, and near Cattle Camp Campground. Please note that when searching Google Maps for the Ash Creek Guard Station, it will show in the McCloud townsite instead of the correct location east of town. The site is currently a field accessible from the highway as shown in the Google Street View image below.

Coordinates and specific layout shown on Project Plans (Attachments 1–2). The project site is subject to seasonal hazards, including wildfire activity and smoke in the spring and fall, and snow and freezing temperatures in the winter.

The soil conditions onsite are volcanic in nature.

https://maps.app.goo.gl/ghJ3Ck97nLLUDNPq8

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

4.0 Estimated Start Date / Period of Performance

All work shall be completed between September 1, 2026, and June 1, 2027, totaling 273 calendar days after Notice to Proceed. The helispot should be ready for use in the 2027 fire season.

5.0 Drawings and Specifications

Drawings and specifications include:

• Attachment 3 – Project Plans (9 Sheets)

• Attachment 4 – Project Maps

• Attachment 5 – Forest Service Supplemental Specifications (FSSS)

• Attachment 6 – Utility Supplemental Technical Specifications

• Attachment 7 – Borrow Excavation Exhibit

• Attachment 8 – Fire Plan

• Attachment 9 – Wage Determination CA20260007 Mod 4 (May 18, 2026)

6.0 Restrictions on Work

• Work hours are limited to non-holiday weekdays, Monday – Friday, 0700 – 1900, unless permission granted by the Contracting Officer for an alternative schedule.

• Comply with the USFS Fire Plan in Attachment 6.

• When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.

• When the Contracting Officer or designated representative determines that work must stop due to the presence of archaeological artifacts.

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

• Contractor is responsible for the security of their tools and equipment at all times.

• All trash and loose materials shall be secured by the contractor daily.

• The Contractor is responsible for installing sediment control devices, such as straw wattles, to prevent sediment runoff to nearby areas. Excavation work shall not commence until sediment control devices have been installed and approved by the COR.

• The Contractor shall not use Government trash facilities without the COR’S approval.

• All construction debris remains the property of the Contractor and shall be properly disposed of off National Forest Land.

• The contractor will be able to utilize the Forest Service Roads; however, the Contractor will be responsible for any damage to the roads due to construction activities. The contractor shall be responsible for obtaining permission to use all other roads and staging areas.

• Contractor must comply with Caltrans Right-of-Way permit for waterline installation.

• Temporary traffic control is required on Hwy 89, including signage for Trucks Entering/Exiting, Work Zone, Flaggers, etc., per FP-14 Section 635.

• Contractor is responsible for protection of existing improvements and repairs of any damage caused by their operations.

6.0 Camping and Housing

Depending on project schedules and requirements, and with approval from the District Ranger, camping or the use of RV trailers may be permitted onsite at the Ash Creek Guard Station, at the nearby Cattle Camp Campground, or at other designated locations on National Forest lands. Permission to camp on Forest Service land is a privilege and may be revoked if the terms of the permit are not followed. Please note that the water systems serving the Ash Creek Helispot and the Cattle Camp Campground may be turned off during the winter to prevent freezing the piping.

7.0 Required Submittals

Submittals shall include all pertinent data required to understand the quality of components, dimensional relationships, integration with other materials, assembly techniques, structural aspects, color, finish, texture, and other such characteristics as may be necessary to fully describe the item and its intended use.

Submit one electronic copy to the Contracting Officer’s Representative (COR) of all submittals or shop drawings along with detailed submittal cover sheet outlining all contents and purpose of each submittal for approval prior to fabrication, installation, or order placement to allow for checking and coordination.

All rejected or returned submittals shall be resubmitted with corrections to the COR for approval.

Contractor Requirements

8.0 Technical Requirements / Tasks

8.1 Applicable Codes and Standards

All work shall comply with the latest adopted editions of applicable federal, state, and local codes, standards, and regulations, including but not limited to the following:

• Architectural Barriers Act (ABA) Accessibility Standards

• California Building Code (CBC)

• California Mechanical Code (CMC)

• California Plumbing Code (CPC)

• California Title 24 Energy Code

• Caltrans Standard Specifications and Plans

• Federal Highway Administration (FHA) Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14/24)

• National Electrical Code (NEC)

• National Electrical Safety Code (NESC)

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

• National Fire Protection Association (NFPA) Codes and Standards o NFPA 101 Life Safety Code

• USFS Region 5 Standard Design Drawings and Specifications

8.2 General Requirements

• The Contractor must possess a valid California Class A General Contractor license at the time of award and throughout the contract performance period.

• The Contractor shall verify existing site conditions prior to commencement of work and report any discrepancies to the Contracting Officer (CO).

• All work shall be performed in accordance with applicable federal, state, and local codes, including current building, electrical, plumbing, mechanical, and accessibility requirements.

• The Contractor shall be responsible for construction means, methods, techniques, sequences, and procedures, including site safety and protection of personnel and property.

• The Contractor shall maintain safe access to all work areas throughout construction.

• The Contractor shall be responsible for compliance with the USFS-supplied Caltrans Right-of-Way permit for this project.

8.3 Site and Civil Work

• Mobilization / Demobilization

• Clearing & Grubbing

• Over-excavation, scarification, fill placement, compaction, grading

• Aggregate Base placement (Class 2, Caltrans spec)

• Construction of reinforced concrete helipad (4000 psi PCC)

• Painting helipad designation markings (Ames elastomeric coating)

8.4 Water System Improvements

• Comply with Caltrans Right-of-Way permit for waterline installtion

• 3" Sch 80 PVC pipe installation

• Fire hydrant lateral installation

• Gate valves, swing check valves, double-check valve assembly

• Connection to existing 3" and 4" pipelines

• Water line marker installation

• Pressure/leak testing

• Waterline disinfection, sampling, and testing

8.5 Option Tasks

• Class 2 Aggregate Base for Loop Road

• Electrical & Communications duct bank under Loop Road

All technical specifications (FP-14/24, FSSS, ASTM, AWWA, Caltrans Standards, Safe-T-Cover enclosure specs, bedding requirements, tracer wire requirements, testing procedures) remain fully applicable.

Descriptions for Schedule of Items (SOI):

A) Mobilization Work shall be in accordance with Section 151 of FP-14 and shall include but not necessarily limited to the following:

a. Mobilization shall include preparatory work and operations necessary for the movement of personnel, equipment, supplies, traffic controls, and incidentals to the project site; utility notification/locate activities, and for the establishment other facilities necessary for the work; for premiums on bond and insurance for the work; and for other operations performed or costs incurred before the beginning of work.

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

b. Pre-final Inspections and punch list corrections.

c. Contractor shall be prepared for, and in compliance with, the project Fire Plan during the performance period of the contract. Refer to the Fire Plan in Attachment 6 to the contract.

d. The contractor will have direct access to the site from Hwy 89. It is imperative the contractor is aware of the traffic on Hwy 89 as it is a relatively busy, high speed two-lane transportation corridor with moderate commercial truck use. The contractor will be responsible for the security of their personnel, equipment and materials, as well as for the general protection of the public, including temporary traffic control safety measures on Highway 89 to alert the travelling public of the contractor’s ingress/egress activity associated with transport of materials and equipment to and from the work site.

e. Contractor must comply with terms of Caltrans Right-of-Way permit obtained by STNF for waterline installation.

f. Temporary traffic control safety measures shall include but not necessarily limited to the following:

furnish, place, operate, and maintain traffic advanced warning signage including but not necessarily limited to: Work Zone, Trucks Entering and Exiting, Watch for Left Turn Traffic, Flaggers, etc. Temporary traffic controls shall conform to Section 635 of FP-14.

g. Construction Survey Staking shall be the responsibility of the contractor. Measurement and payment for Construction Survey Staking shall be included in the various items of work in the Schedule of Items and no additional compensation will be allowed.

h. Demobilization.

i. Measurement and payment for Mobilization shall include the work described herein and as required in

Section 151 of FP-14 and no other compensation will be allowed.

B) Clearing and Grubbing Work shall be in accordance with Section 201 of FP-14 and shall include but not necessarily limited to the following follows:

a. Clearing and Grubbing

b. Screening of the upper 12” of soils is required for the removal of organic, deleterious or objectional materials from outside the limits of over-excavation for the project improvement area and out to the grading daylight limits as shown on the Grading and Paving Plan. Screening of the soils is also required for soil materials from within the borrow excavation area to be utilized for engineered fill.

c. Scarify to 12” below original ground outside the over-excavation limits and recompact in preparation for fill placement. This area is the same as for soil screening of upper 12” described in part “a” above.

Compaction Method 2 per FSSS.

d. The location, limits and depth of the Borrow Excavation area are depicted in the Borrow Excavation Exhibit included as Attachment 5 to the Contract.

e. Measurement and payment for Clearing and Grubbing shall include the work described herein, as shown on the Project Plans, and as required in Section 201 of FP-14 and no other compensation will be allowed.

f. Clearing and grubbing within the Overexcavation Area as Shown on the Project Plans will be paid for as described below for Overexcavation.

C) Overexcavation, Subgrade Preparation, Fill Placement, Compaction and Grading Work shall generally conform to the FP-14 for excavation, fill placement and compaction, and grading, and more specifically as follows:

a. Clearing and Grubbing per Section 201

b. Limits of over-excavation, soil scarification, fill placement and compaction are as shown on the Project

Plans. Note that the words compaction and re-compaction as described herein and on the Project Plans are synonymous and used interchangeably, but re-compaction is directed to the replacement of over-excavation materials.

c. 12” of soil scarification and compaction refers to the 12” of material below the over-excavation bottom.

d. Fill placement, grading and compaction shall be as required to meet final finish grade or to meet subgrade elevation in preparation to place aggregate surfacing or aggregate subgrade (for concrete helipad) as showed on the Project Plans.

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

e. Fill placement and compaction and final grade shall be accomplished to the maximum lifts and compaction requirements and methods described on the Project Plans, the FP-14 and FSSS.

f. Borrow excavation for use as fill shall be from the source indicated above (within the site clearing area) and processed and placed as required herein and in the Project Plans as for engineered fill. Following borrow excavation area work, contractor shall blend affected by the borrow excavation area for smooth transition with adjacent grades. Grading transitions should be approximated to a 10:1 slope. A depression area of nominally 12” deep within the borrow excavated area is anticipated.

g. Grading shall include earthwork activities in conjunction with fill placement and compaction necessary to meet finish grade, setting subgrade elevations for receiving aggregate subbase and subgrade elevations for receiving aggregate surfacing.

h. Compaction shall be 95% relative compaction at optimum moisture content. Compaction Method 2 per

FSSS.

i. Measurement and payment for Overexcavation, Subgrade Preparation, Fill Placement, Compaction and Rough Grading shall include the work described herein, as shown on the Project Plans, and as required in the applicable Sections of the FP-14 and FSSS, and no other compensation will be allowed.

D) Furnish and Place Class 2 Aggregate Base (All areas except Loop Road) Work shall generally conform to the FP-14 and FSSS for furnishing, placement and compaction of aggregate base, and more specifically as follows:

a. Furnishing, placing, spreading, and compacting aggregate base (AB) of the type, gradation, locations, and thickness as shown on the plans. Unless stated otherwise on the Project Plans or in this statement of work, aggregate base shall be in accordance with Caltrans ¾” Class 2 Aggregate Base and no less than 6” in compacted thickness. Compaction shall be 95% relative compaction at optimum moisture content.

Compaction Method 2 per FSSS.

b. Class 2 Aggregate Base shall include the aggregate surfacing areas and the aggregate base material for the reinforced concrete helipad.

c. Measurement and payment for Furnish and Place Class 2 Aggregate Base shall include the work described herein, as shown on the Project Plans, and as otherwise required in the applicable Sections of the FP-14 and FSSS, and no other compensation will be allowed.

E) Construct Reinforced Concrete Helipad Work shall generally conform to the FP-14 and FSSS for furnishing and placement of reinforcement and concrete for the construction of the Helipad, and more specifically as follows:

a. Reinforcement shall be of the type, size, spacing, lap lengths, and locations as shown on the Project

Plans.

b. Reinforcement clearances shall be per industry standard, but generally placed at mid-point of concrete section.

c. Portland cement shall be Type II. Portland cement concrete (PCC) shall be 1-1/2 inch gradation aggregate with minimum concrete compressive strength of 4000 psi.

d. Sawcut concrete crack control joints (CCJ) shall be in accordance with the Project Plans and Details. Saw cutting for CCJs shall be made no later than 6 hours following concrete pour.

e. Fill CCJs with backer rod and seal with Sikaflex concrete joint filler as shown on Project Plan Details.

Submit product materials for COR approval prior to installation.

f. Measurement and payment for Construct Reinforced Concrete Pad shall include the work described herein, as shown on the Project Plans, and as otherwise required in the applicable Sections of the FP-14 and FSSS, and no other compensation will be allowed.

F) Paint Helipad Designation Markings

Work shall include pad preparation, furnishing materials and the painting of the Helipad markings, and more specifically as follows

a. Clean and prepare newly constructed concrete pad for application of paint.

b. Furnish and apply elastomeric coating “Maximum Stretch” as manufactured by Ames.

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

c. Color tint shall be Dark Green available from Ames Co.

d. Apply primer prior to final coating as recommended by manufacturer.

e. All lines shall be accurate, true and clean. Sloppy work will be rejected. Film thickness shall be as recommended by Ames for exterior application on prepared concrete surfaces.

f. Measurement and payment for Paint Helipad Designator Markings shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

G) Furnish and Install 3” Schedule 80 PVC Pipe & Fittings Work shall include but not necessarily limited to the following:

a. Coordination with COR for water system outage and shut off timing and duration of outage. Any single water system outage shall not exceed 4 hours. Coordinate with COR for posting of “Boil Water” notices when outage occurs and until water system disinfection is complete.

b. Cut, remove and dispose interfering portions of existing 3” (& smaller) PVC water line and appurtenances through limits shown on Project Plans. Abandon remaining water line in-place.

c. Furnish and install 3” Schedule 80 PVC pipe and fittings, GSP fittings (where applicable), including but not necessarily limited to trench excavation, pipe connections, couplings, pipe bedding, pipe supports, polyethylene wrap, joint sealant, tracer wire, backfill, locator tape and thrust blocks, complete.

d. Furnish and install tracer wire waterproofing splice kit for all tracer wire splices.

e. Backfill with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

f. Measurement and payment for Furnish and Install 3” Schedule 80 PVC Water Main shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

H) Join Existing 3” Water Line per Detail 1, Sheet 7

a. Check for valve isolation requirements and shut off before connection activity.

b. Locate, excavate, and expose existing 3” PVC water line. Cut and remove interfering portions of existing

3” water line and dispose.

c. Prepare existing 3” line for connection, including straight cuts, cleanup of pipe exterior, and cut burrs.

d. Furnish and Install Mueller 3” Swing Check Valve

e. Furnish and Install “Duralite” Valve Box per Project Plans and Details on Sheet 7 & 8.

Furnish and Install

f. 3” Schedule 80 PVC Pipe and related fittings, 3” GSP Nipples and Fittings, tracer wire and locator tape through to existing 3” join, trench excavation pipe bedding and backfill, transition couplings, PVC Solvent cement, unions, pipe thread sealants, couplings and adaptors, polyethylene wrap, and thrust blocks complete.

g. Furnish and install valve box bedding, ½” galvanized fabric (19 gauge), and pipe supports.

h. Furnish and install tracer wire waterproofing splice kit for all tracer wire splices.

i. Backfill with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

j. Measurement and payment for Join Existing 3” Water Line per Detail 1, Sheet 7 of 9 shall include the work described herein, as shown on the Project Plans, and as otherwise required in the

I) Furnish and Install Fire Hydrant Lateral with Gate Valve and Swing Check Valve per Details 4 and 5, Sheet 7

Work shall include but not necessarily limited to the following:

a. Furnish and install Mueller 2-1/8” dry barrel Fire Hydrant with two 2” Nozzles.

b. Furnish and install Mueller 3” threaded Gate Valve

c. Furnish and Install Mueller 3” Swing Check Valve

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

d. Furnish and Install “Duralite” Valve Box per Project Plans and Details on Sheet 7 & 8.

e. Furnish and install GSP Schedule 40 GSP nipples and related fittings, 3” Sch 80 PVC pipe & fittings, tracer wire and locator tape through to Fire Hydrant and continue through to proposed 3” Gate Valve Stub (Detail 4). Work also includes but is not necessarily limited to pipe preparation and connections, furnishing and installing pipe bedding and backfill, flexible couplings, PVC and GSP fittings, PVC Solvent cement, unions, pipe thread sealants, transition couplings and adaptors, reducers, polyethylene wrap on GSP materials, and thrust blocks complete.

f. Furnish and install valve box bedding, ½” galvanized fabric (19 gauge), and pipe supports.

g. Furnish and install tracer wire waterproofing splice kit for all tracer wire splices.

h. Backfill with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

i. Measurement and payment for Furnish and Install Fire Hydrant Lateral with Gate Valve and Swing Check

Valve per Details 4 and 5, Sheet 7 of 9 shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

J) Furnish and Install 3” Gate Valve & Stub per Detail 4, Sheet 7

a. Continue from Fire Hydrant lateral Tee and GSP Nipple.

b. Furnish and Install Valve Box per Project Plans and Details on Sheet 7 & 8.

c. Furnish and install GSP Schedule 40 GSP nipples and related fittings, 3” Sch 80 PVC pipe & fittings, tracer wire and locator tape. Work also includes but is not necessarily limited to pipe preparation and connections, furnishing and installing pipe bedding and backfill, flexible couplings, PVC and GSP fittings, PVC Solvent cement, unions, pipe thread sealants, transition couplings and adaptors, GSP cap, polyethylene wrap on GSP materials, complete.

d. Furnish and install valve box bedding, ½” galvanized fabric (19 gauge), and pipe supports

e. Backfill with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

f. Furnish and install tracer wire waterproofing splice kit for all tracer wire splices.

g. Measurement and payment for Furnish and Install 3” Gate Valve & Stub per Detail 4 Sheet 7 of 9 shall include the work described herein, as shown on the Project Plans, and as otherwise required in the

K) Construct Connection to 4” CIP per Detail 2, Sheet 7

The Work shall include but not necessarily limited to the following:

a. Locate, excavate, and expose existing 4” CIP water line at join location North of Hwy 89. Cut and remove existing interfering 3” PVC and 4” CIP as required. Dispose interfering portions of existing water line associated with the work to be installed.

b. Prepare existing 4” CIP pipe for connection, including straight cuts, grind smooth exterior of 4” CIP, cleanup of pipe exterior, and grind cut burrs. Protect existing 4” CIP to remain.

c. Furnish and install 3” Schedule 80 PVC Pipe and related fittings, 3” GSP Nipples and Fittings, tracer wire and locator tape through to existing 4” CIP join. Work also includes but is not necessarily limited to pipe preparation and connections, furnishing and installing pipe bedding and backfill, 4” Smith-Blair Top Bolt coupling, 4” PVC and GSP fittings, PVC Solvent cement, unions, pipe thread sealants, transition couplings and adaptors, polyethylene wrap on GSP materials, complete.

d. Backfill with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

e. Furnish and install tracer wire waterproofing splice kit for all tracer wire splices.

f. Measurement and payment for Construct Connection to 4” CIP per Detail 2, Sheet 7 shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

L) Remove Existing 3” Gate Valve per Detail 3, Sheet 7

a. Locate existing valve box, excavate, and expose existing 4” CIP and 3” PVC water line transition at work location South of Hwy 89. Cut and remove existing interfering 3” PVC and 4” CIP as required and remove and dispose existing 3” Gate Valve. Dispose interfering portions of existing water line associated with the work to be installed.

b. Prepare existing 4” CIP pipe for connection, including straight cuts, grind smooth exterior of 4” CIP, cleanup of pipe exterior, and grind cut burrs. Protect existing 4” CIP to remain.

g. Furnish and install 3” Schedule 80 PVC Pipe and related fittings, 3” GSP Nipples and Fittings, tracer wire and locator tape through to existing 4” CIP join. Work also includes but is not necessarily limited to pipe preparation and connections, furnishing and installing pipe bedding and backfill, 4” Smith-Blair Top Bolt coupling, 4” PVC and GSP fittings, PVC Solvent cement, unions, pipe thread sealants, transition couplings and adaptors, polyethylene wrap on GSP materials, complete.

h. Backfill with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

i. Furnish and install tracer wire waterproofing splice kit for all tracer wire splices.

j. Measurement and payment for Remove Existing 3” Gate Valve per Detail 3, Sheet 7 shall include the work described herein, as shown on the Project Plans, and as otherwise required in the

M) Furnish and Install 3” Gate Valve, 3” Double Check Valve and Insulated DC Valve Enclosure per Detail 6, Sheet

The Work shall include but not necessarily limited to the following:

a. Coordination with COR for water system outage and shut off timing and duration of outage. Any single water system outage shall not exceed 4 hours. Coordinate with COR for posting of “Boil Water” notices when outage occurs and until water system disinfection is complete.

b. Locate, excavate, and expose existing 3” PVC water line. and new water line at location of previously completed and backfilled work. Cut and remove interfering portions of existing 3” water line and dispose.

c. Prepare existing 3” line for connection, including straight cuts, cleanup of pipe exterior, and cut burrs.

d. Furnish and install Mueller 3” threaded gate valve.

e. Furnish and install Watts 3” double check valve with non-rising stem (Model 757NRS) with 3” 90 deg CIP

Fittings and Spools & related fittings.

f. Furnish and install reinforced concrete slab for check valve assembly and enclosure.

i. Portland cement shall be Type II. Portland cement concrete (PCC) shall be 1-1/2 inch gradation aggregate with minimum concrete compressive strength of 4000 psi.

ii. Welded wire reinforcement shall be 6x6-W4.0xW4.0 and comply with ASTM A1064, placed at mid-point of concrete section.

iii. Place concrete on compacted CL-2 AB over compacted native material.

g. Portland cement shall be Type II. Portland cement concrete (PCC) shall be 1-1/2 inch gradation aggregate with minimum concrete compressive strength of 4000 psi.

h. Furnish and install insulated double check (DC) valve enclosure, “Safe-T-Cover” Model 300-AL (see additional technical specifications in Section 2 below).

i. Furnish and install valve boxes per Project Plans and Details on Sheet 7 & 8.

j. Furnish and install 2” Brass Dielectric Unions and Brass Nipples.

k. Furnish and install 3” and 2” GSP nipples and fittings, tracer wire and locator tape through to existing 3” join. Work also includes but is not necessarily limited to pipe preparation and connections, furnishing and installing pipe bedding and backfill, flexible couplings, PVC and GSP fittings, PVC Solvent cement, unions, pipe thread sealants, transition couplings and adaptors, GSP Reducers, polyethylene wrap on GSP and brass materials, and thrust block complete.

l. Furnish and install valve box bedding, ½” galvanized fabric (19 gauge), and pipe supports.

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

m. Backfill with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

n. Furnish and install tracer wire waterproofing splice kit for all tracer wire splices.

o. Measurement and payment for Furnish and Install 3” Gate Valve, 3” Double Check Valve and Insulated

DC Valve Enclosure per Detail 6, Sheet 7 shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

N) Furnish and Install Water Line Marker per Detail 7, Sheet 7

a. Furnish and install a Water Line Marker per Caltrans Standard Plan A73B and as detailed in the plans.

The signs will be installed to mark the water line at locations to be coordinated in the field between contractor and COR.

b. Measurement and payment for Furnish and Install Water Line Marker per Detail 7, Sheet 7 shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

O) Pressure/Leak Test Water Line

a. Performing water line pressure test and leak testing as described elsewhere in these specifications.

b. Failure to satisfy the requirements of the testing will require the contractor to employ means of locating the leak(s) and making associated repairs until testing requirements are satisfied.

c. Making repairs and re-testing of waterline will be subject to all requirements of original installation, such as traffic controls, materials, backfill and resurfacing, as applicable.

d. Measurement and payment for Pressure /Leak Test Waterline shall include the work described herein, as shown on the Project Plans, and as otherwise required in the contract and no other compensation will be allowed.

P) Disinfect, Sample & Test Potable Waterline

a. Disinfect, sample and test water system for bacterial contamination until results indicate absence of Total Coliform and E. Coli. Repeat as necessary.

b. Measurement and payment for Disinfect, Sample & Test Potable Waterline shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

Option Items

Q) Furnish and Place Class 2 Aggregate Base (For Loop Road only)

Work shall generally conform to the FP-14 and FSSS for furnishing, placement and compaction of aggregate base, and more specifically as follows:

a. Furnishing, placing, spreading, and compacting aggregate base (AB) of the type, gradation, locations, and thickness as shown on the plans for the loop road section of the project. Unless stated otherwise on the Project Plans or in this statement of work, aggregate base shall be in accordance with Caltrans ¾” Class 2 Aggregate Base and no less than 6” in compacted thickness. Compaction shall be 95% relative compaction at optimum moisture content. Compaction Method 2 per FSSS.

b. Measurement and payment for Furnish and Place Class 2 Aggregate Base for the Loop Road section shall include the work described herein, as shown on the Project Plans, and as otherwise required in the applicable Sections of the FP-14 and FSSS, and no other compensation will be allowed.

R) Furnish and Install Electrical and Communications Duct Bank (Under Loop Road)

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

a. Furnish and install 3” Schedule 80 PVC electrical conduit pipe, sweeps and fittings, PVC solvent cement, and sealants, including trench excavation, conduit bedding, backfill, and locator tapes, complete.

b. Furnish and Install “Duralite” Pull Box per Project Plans and Details on Sheet 7 & 8.

c. Backfill trench with clean native material and compact to 90% RC but rocks greater than 3 inches will not be allowed.

d. Measurement and payment for Furnish and Install Electrical and Communications Duct Bank shall include the work described herein, as shown on the Project Plans, and as otherwise required in the Contract and no other compensation will be allowed.

9.0 Government Furnished

Government will provide site access, existing site and utility information, and Caltrans Right-of-Way permit for waterline installation. Contractor is solely responsible for security of equipment, materials, and possessions. Government assumes no liability for contractor use of staging or laydown areas.

10.0 Deliverables / Schedule

Item No.

Deliverable Description Frequency Delivery Format

Due By

1 Project Schedule Baseline construction schedule showing sequencing, durations, and critical path

One-time (initial)

Electronic

(PDF)

Within 10 calendar days after Notice to Proceed

2 Schedule Updates Updated schedule reflecting progress, delays, and changes

Monthly Electronic

(PDF)

With each monthly progress report

3 Submittal Register Log of all required submittals and status tracking

One-time (initial), updated as needed

Electronic (Excel/PDF)

Within 10 calendar days after Notice to Proceed

4 Product Submittals Shop drawings, product data, and material specifications for review

As required Electronic

(PDF)

Prior to installation of applicable materials

5 Construction Work Plan

Description of planned construction approach, sequencing, and site logistics

One-time Electronic

(PDF)

Within 10 calendar days after Notice to Proceed

6 Health and Safety Plan

Site-specific safety plan addressing hazards and risks

One-time Electronic

(PDF)

Prior to start of field work

7 Quality Control Plan

Plan describing inspection procedures and quality control measures

One-time Electronic

(PDF)

Prior to start of field work

8 Monthly Progress Report

Summary of work completed, upcoming work, schedule status, and issues

Monthly Electronic

(PDF)

By the 5th calendar day of each month

9 Inspection and Test Reports

Documentation of required inspections and testing results

As required Electronic

(PDF)

Within 5 calendar days of completion of inspection/test

10 As-Built Drawings Record drawings reflecting final constructed conditions

One-time (final)

Electronic

(PDF)

Prior to final acceptance

11 Operation and Maintenance Manuals

Manuals for installed equipment and systems

One-time (final)

Electronic

(PDF)

Prior to final acceptance

12 Warranty Documentation

Manufacturer and contractor warranties for installed systems

One-time (final)

Electronic

(PDF)

Prior to final acceptance

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

11.0 Travel

The Contractor shall be responsible for all travel necessary to perform the work under this contract, including travel to and from the Ash Creek Helispot project site. The project site is located in a remote area with limited nearby services, including food, fuel, and lodging. The Contractor shall plan and coordinate all travel, lodging, and logistical needs necessary to support construction activities.

No separate payment will be made for travel costs. All travel, mobilization, and associated expenses shall be included in the Contractor’s bid price. Any travel by Contractor personnel to Government offices or off-site meetings shall be coordinated in advance with the Contracting Officer or Contracting Officer’s Representative (COR).

12.0 Contractor’s Key Personnel

Contractor must possess a valid California Class A General Contractor license at the time of award and throughout the contract performance period.

Key personnel must demonstrate experience in:

• Heavy civil construction

• Waterline installation

• Concrete helipad construction

• Utility trenching and compaction

• AWWA testing and disinfection procedures

The Contractor shall provide qualified personnel necessary to successfully perform the work described in this contract.

At a minimum, the Contractor shall designate the following key personnel:

• Project Manager:

Responsible for overall project management, coordination, scheduling, and communication with the Government.

• Superintendent:

Responsible for on-site supervision of construction activities, coordination of subcontractors, and daily site operations.

• Safety Officer (or Competent Person):

Responsible for implementation and enforcement of the project safety plan, including compliance with applicable safety regulations and hazard mitigation requirements.

• Qualified Mechanical/Plumbing Personnel:

Responsible for installation and commissioning of mechanical and plumbing systems.

The Contractor shall ensure that all personnel performing work are appropriately licensed, certified, and experienced for their respective trades. Key personnel substitutions shall not be made without prior approval of the Contracting Officer.

Resumés may be requested by the COR.

13.0 Security Requirements

The Contractor shall comply with all applicable site security requirements while performing work at the Ash Creek Helispot

• No security clearance is required for this project.

• The Contractor shall ensure all personnel are authorized to access the project site and comply with all posted site restrictions.

• The Contractor shall be responsible for securing all tools, materials, and equipment during construction.

• The Contractor shall not interfere with ongoing operations at the ranger station and shall coordinate work activities with the Contracting Officer’s Representative (COR) as necessary.

• The Contractor shall report any incidents, damage, or security concerns to the COR.

14.0 Data Rights

All drawings, reports, and other documents produced under this contract shall become the property of the Government upon completion of the work.

USDA Forest Service | Shasta-Trinity National Forest – Ash Creek Helispot Project – Phase 1 | SOW | July 2026

• The Government shall have unlimited rights to use, reproduce, and distribute all deliverables produced under this contract.

• The Contractor shall not release, publish, or disclose project information without prior written approval of the Contracting Officer.

• Any proprietary information provided by the Contractor shall be clearly identified and protected in accordance with applicable regulations.

15.0 Site Visit

Project site is accessible and can be visited at will on Highway 89. Location description is contained in Section 3.0 of this Statement of Work.