The Statement of Work details the Upper Golden Trout Bridge Replacement project for the US Department of Agriculture Forest Service, located on Forest Route 22N24 in Plumas National Forest. The project involves removing the existing damaged bridge crossing the South Fork Feather River and constructing a new permanent bridge, including approaches and campground entrance reconstruction. The project has a defined performance period from October 1, 2025 to November 30, 2026, with an estimated value between $1,000,000 and $5,000,000 and is set aside for small businesses.
Key technical requirements include removing and disposing of the existing bridge structures, constructing a new bridge according to provided plans, reconstructing bridge approaches, and providing a biological monitor to oversee Threatened and Endangered Species protection. Environmental considerations are critical, with specific requirements for monitoring the foothill yellow-legged frog habitat and implementing Best Management Practice mitigations. The project requires consultation with the U.S. Fish and Wildlife Service prior to construction, and contractors must submit detailed documentation including a construction schedule, waste material disposal plans, and a biological monitoring plan.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project
General Information
1.0 Scope of Work
2.0 Background
3.0 Location
4.0 Estimated Start Date / Period of Performance
5.0 Drawings and Specifications
6.0 Restrictions on Work
7.0 Camping and Housing
8.0 Required Submittals
Contractor Requirements
9.0 Technical Requirements / Tasks
10.0 Government Furnished
11.0 Travel
12.0 Contractor’s Key Personnel
13.0 Security Requirements
14.0 Data Rights
15.0 Section 508 – Electronic and Information Technology Standards
Attachment
Project Upper Golden Trout Bridge Replacement
General Information
1.0 Scope of Work
The contractor shall furnish all materials, equipment, supplies and personnel necessary to remove and dispose of the existing Upper Golden Trout Bridge including the bridge span and structures, bridge abutments and approaches and replace with a new structure as specified in the project plans and specifications.
2.0 Background
In 2017, the existing bridge crossing the South Fork Feather River at Golden Trout was damaged when large tree traveling down river hit the metal I-Beam support on upstream side of bridge, causing the metal beam to spread apart 2” and causing a 10” crack to develop on the I-Beam support. A temporary repair was implemented until the bridge replacement design and funding could be completed and secured.
There is a Threatened & Endangered (T&E) species present within the stream, foothill yellow-legged frog (Rana boylii).
Also, pending the listing of the California spotted owl (Stix occidentalis occidentalis) noise restriction may occur but are not likely to be given since the owl PACs are farther than 0.25 miles from the bridge replacement project area. Best
Management Practice (BMP) mitigations will need to be in place to prevent habitat disturbance including possible silt fences, biological monitors, and/or other conservation measures needed to prevent species and habitat disturbance.
Further review of the technical project plans will need to be reviewed by the District Wildlife Biologist to ensure what conservation measures will need to be implemented. A Biological Assessment will need to be submitted to USFWS prior to implementation and conservation measures will be determined after consultation with USFWS. Construction will not be able to start until the consultation with USFWS is completed.
3.0 Location
Upper Golden Trout Bridge is located on Forest Route 22N24 approximately 3.4 miles from the intersection of Forest
Route 22N27 & 22N24. To arrive at the bridge, take CA-162 east of Oroville for approximately 8.2 miles. Turn right (East) onto Fobestown Road and continue for 6.2 miles. Turn left (North) onto Lumpkin Road and continue for 11.8 miles. Turn right on Forest Route 22N27 and continue for 9.6 miles. Turn right on Forest Route 22N24 and continue for 3.4 miles and arrive at the bridge. The bridge coordinates are 39.615992, -121.142517.
4.0 Estimated Start Date / Period of Performance
Estimated Period of Performance: October 1, 2025 – November 30, 2026.
5.0 Drawings and Specifications
• Upper Golden Trout Bridge Plans Final
• Upper Golden Trout Bridge FSSS Final
6.0 Restrictions on Work
• Work hours and workdays are not limited on this project
• In accordance with the fire plan, if included in Section J.
• When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
• For sites requiring biological monitoring, contractor must notify COR at least 24 hours prior to any ground disturbing activities and no ground disturbing activities may occur without a Forest Service biologist or approved biological monitor on site.
• Contractor is responsible for the security of their tools and equipment at all times.
• Contractor is responsible for removal and disposal of all excavated dirt and shall not leave excavated dirt scattered over the site, unless approved by the COR.
• All trash and loose materials shall be secured by the contractor daily.
• The Contractor is responsible for installing sediment control devices, such as straw wattles, to prevent sediment runoff to nearby areas. Excavation work shall not commence until sediment control devices have been installed and approved by the COR.
• All construction debris remains the property of the Contractor and shall be properly disposed of off National Forest Land.
• The contractor will be able to utilize the Forest Service Roads; however, the Contractor will be responsible for any damage to the roads due to construction activities. The contractor shall be responsible for obtaining permission to use all other roads and staging areas.
7.0 Camping and Housing
There is no housing located in the project area
Camping is not permitted in US Forest Service campgrounds. Contractor [ X ] will [ ] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.
8.0 Required Submittals
Construction Schedule Section 20302 – Waste Material Disposal Section 20307 – Waste Material Disposal Section 55201A – Structural Concrete Class A(AE) Section 55201B – Structural Concrete Class A(AE) Section 55502 – Structural Steel Superstructure Section 55601 – Steel Bridge Railing Section 62200 – Transportation of Materials and Equipment Biological Monitoring Plan
Contractor Requirements
9.0 Technical Requirements / Tasks
1. Remove and dispose of the existing Upper Golden Trout Bridge and its structures in accordance with the provided plans and specifications.
2. Construct a new permanent bridge and its structures to replace the removed bridge structures in accordance with the provided plans and specifications.
3. Construct new bridge approaches and reconstruct campground entrances to match existing in accordance with the provided plans and specifications.
4. Provide a Biological Monitor to monitor Threatened and Endangered Species in the project area in accordance with plans and specifications
10.0 Government Furnished
There are no Government Furnished items.
11.0 Travel
N/A
12.0 Contractor’s Key Personnel
a. Provide professional resume data and letters of commitment on the individuals who will be key personnel on the project team. Key personnel identified in this Section should be senior working-level people who will be involved in design and/or construction on a day-to-day basis, as opposed to departmental level supervisors or executives. By identifying these personnel, the Offeror is making a commitment that, barring unforeseen circumstances, they are the personnel who will be assigned to the project. If reassignment of personnel is considered possible, provide the names and resumes of the alternative individuals in each assignment. More than one position may be filled by the same person except the Project Manager. The following list shall be provided as a minimum:
i. Project Manager.
ii. Site (Construction)Superintendent.
iii. Quality Control Manager.
iv. Environmental/Pollution Control Manager
b. Information to be provided for each person includes:
i. Name and Title.
ii. Project Assignment(s).
iii. Years Experience: With This Firm, With Other Firms.
iv. Experience and Qualifications Relevant to the Project.
Except for the Project Manager, multiple positions listed above may be filled by the same person.
13.0 Security Requirements
The contractor is responsible for site security of their tools, equipment, material and supplies at all times.
14.0 Data Rights
15.0 Section 508 – Electronic and Information Technology Standards