20Q-161-TO-55 Marion County Library Headquarters Reroof
Solicitation number
20-161-TO-55
Issued by
Marion County, Orlando City, Florida

About this file

Summary

This is a bid package and invitation to bid issued by Ausley Construction Company, LLC, serving as Construction Manager for the Marion County Board of County Commissioners (Owner), for roofing services at the Marion County Library Headquarters located at 2720 E Silver Springs Blvd, Ocala, FL. The project (20Q-161 TO 55) consists of recovering an existing 62,000 square-foot library headquarters building with removal and replacement of wet/damaged insulation identified by infrared survey, installation of Siplast Parasolo KEE Fleeceback PVC membrane over the existing modified bitumen roof, demolition of unused roof vents and curbs, installation of retrofit roof drains, and installation of walkway pads. The work includes roofing, plumbing, and electrical trades. A mandatory onsite pre-bid meeting is scheduled for July 24, 2026, at 10:00 AM EST. Requests for information (RFIs) are due by August 3, 2026, at 5:00 PM EST. Sealed bids must be submitted to Procurement Services via the Euna Procurement website no later than August 13, 2026, at 3:00 PM EST, with public bid opening occurring at the same date and time. The list of subcontractors must be submitted within 24 hours of the bid date. The tentative construction start date is October 1, 2026, with substantial completion anticipated by December 1, 2026.

The base bid includes an 80-mil Parasolo KEE Fleeceback PVC recover system with a 30-year manufacturer warranty. Bidders must provide alternates including replacement of existing roof area dividers with stainless steel dividers, replacement of painted metal parapet cap with Kynar-coated metal parapet cap, and a deduct alternate for a 60-mil system with 25-year warranty. Bidders must submit a 5% bid bond (AIA Document A310) and, upon award, provide a 100% Performance and Payment Bond. A schedule of values, unit prices for identified line items, man hours, lead times, and value engineering suggestions are required. Payment terms include monthly progress payments less 5% retainage, contingent upon receipt of payment from the Owner. Bidders must be pre-qualified by Ausley Construction Company, LLC at least five days prior to the bid date. All bidders must be licensed and registered in Florida, comply with Florida Statutes Section 287.133 (public entity crimes statement), and adhere to apprenticeship requirements under Florida Statutes Section 446.102 for contracts exceeding $25,000. Liquidated damages of $2,500 per calendar day apply for failure to achieve substantial completion within the contract time.

View the file

Other files

File Type Posted
2-Drawings and Specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

Ausley Construction Company, LLC

1521 SE 36th Ave | Ocala, FL 34471

352.629.8177 (Tel) | 352-629-6083 (Fax) www.ausleyconstruction.com

Cover Sheet

COVER SHEET

Project Name Marion County Library Headquarters Reroof Project Address 2720 E Silver Springs Blvd, Ocala, FL 34470

BID PACKAGE: DIV 7 - ROOFING

Table of Contents

TABLE of CONTENTS

Section Description A Invitation to Bid

B Instructions to Bidders

C Proposal Form

D Bid Bond

E Bid Proposal Affidavit

F List of Subcontractors

G Public Crimes Statement

H Not Used

I Standard Form of Agreement Between Contractor/ Subcontractor

J Schedule “A.1” General Requirements Schedule “A.2” Trade Scope of Work

K Schedule “B” Document List

L Exhibit-A Project Close-Out Requirements

M Exhibit-B Direct Purchase Procedure

N Exhibit-C Safety Rules and Regulations

O Exhibit-D Basic Security Guidelines

P Exhibit-E Environmental Policy

Q Exhibit-F Substance Abuse Policy

R Drawings/ Details/ Specifications/ Addendum

Section A - Invitation to Bid

SECTION A - INVITATION TO BID

Project Information:

Project Name: 20Q-161 TO 55 - Marion County Library Headquarters Reroof

Project Address: 2720 E Silver Springs Blvd, Ocala, FL 34470

Project Scope: This project consists of a recover of an existing 62,000 SF library headquarters building located in

Ocala, FL for the Marion County Board of County Commissioners. Scope includes removal and replacement of wet/damaged insulation in areas identified by infrared survey (allowance), installation of Siplast Parasolo KEE Fleeceback PVC membrane over existing modified bitumen roof, demolition of all unused roof vents and curbs, installation of retrofit roof drains, and installation of walkway pads. Trades include roofing, plumbing, and electrical.

Base Bid: 80 mil Parasolo KEE Fleeceback PVC recover system with 30-year manufacturer warranty.

Add Alternate 1: Replace existing roof area dividers with new stainless steel area dividers.

Add Alternate 2: Replace painted metal parapet cap with new Kynar-coated metal parapet cap.

Deduct Alternate 1: 60 mil Parasolo KEE Fleeceback PVC recover system with 25-year manufacturer warranty, in lieu of 80 mil base bid system.

Bid Information:

Bid Date: August 13, 2026, at 3:00 PM EST

Proposals for furnishing of all labor, materials, and equipment and performing all work necessary and incidental for the construction of the Marion County Library Headquarters Reroof shall be delivered to Procurement Services via the Euna Procurement website for the Marion County Board of County Commissioners, the Owner, no later than August 13, 2026, at 3:00 PM EST.

https://www.marionfl.org/agencies-departments/departments-facilities-offices/procurement-services/euna-procurement https://marionfl.bonfirehub.com/portal/?tab=openOpportunities

Bids MUST be submitted on the General Requirements, Proposal Forms and Trade Scope Forms. All boxes must be acknowledged and initialed so that the Forms are complete. Final pricing, alternates, and unit costs must be entered on the Proposal Form.

All subcontractor sealed bids shall be delivered to Procurement Services via the Euna Procurement website before the due date and time listed above. Any Bids arriving late will be refused.

All submitted bids shall be opened during the public bid opening at Procurement Services.

Online access to Bid Opening via Microsoft Teams below:

Teams Link:

https://msteams.link/VVNH | Meeting ID: 292 641 460 734 13 | Passcode: HT3yW6Pa | Dial-in: +1 321-245- 5074,,749190962# (Phone Conference ID: 749 190 962#) http://www.ausleyconstruction.com/ https://www.marionfl.org/agencies-departments/departments-facilities-offices/procurement-services/euna-procurement https://marionfl.bonfirehub.com/portal/?tab=openOpportunities https://msteams.link/VVNH

Section A - Invitation to Bid

Bid/ Construction Schedule:

07/24/2026 Mandatory Onsite Pre-Bid Meeting, 10:00 AM EST https://maps.app.goo.gl/WzvJF48aTHKKypyg8

08/03/2026 RFI’s due to Ausley Construction by 5:00 PM EST

08/13/2026 Bids due to Procurement Services by 3:00 PM, EST

08/13/2026 Bid opening at Procurement Services at 3:00 PM, EST

10/01/2026 Tentative start building construction

12/01/2026 Tentative construction complete

All Bidders must be Pre-Qualified by Ausley Construction Company, LLC, the Construction Manager for the Owner five (5) days prior to bid date.

Bidders may obtain (1) complete set of Bidding Documents (set of drawings/ specifications and Bid Package/ Forms) from the Construction Manager, Ausley Construction Company, LLC, 1521 S.E. 36th Avenue, Ocala, Fl. 34471. Email John Ferris at jferris@ausleyconstruction.com for prequalification forms and bid documents. It will be the bidder’s responsibility to make hard copies of the plans/ specifications at their own expense.

Bids must be submitted on the Proposal Form as furnished in the Bid Package. The Bid Proposal Affidavit Form, Instructions to Bidders Form, List of Subcontractors Form, Public Crimes Statement, General Requirements Form, Trade Scope of Work Form, Project Close-Out Requirements Form, Safety Rules and Regulation Form, Basic Security Guidelines Form, Environmental Policy Form, Substance Abuse Policy Form, and Addendum Acknowledgement (Addendum Acknowledgement is part of the Proposal Form) are all required to be filled out and submitted with proposal.

A Performance and Payment Bond is required for Roofing, Plumbing, and Electrical trades. See Proposal Forms.

The Owner and Construction Manager reserve the right to waive all technicalities and informalities.

https://maps.app.goo.gl/WzvJF48aTHKKypyg8 mailto:jferris@ausleyconstruction.com

Section B – Instructions to Bidders

SECTION B

INSTRUCTIONS to BIDDERS

SECTION B - INSTRUCTION TO BIDDERS

1.01 DEFINITIONS:

A. Bidding Documents includes the specifications and bid package books containing the "Invitation to Bid", "Instructions to Bidders", “Proposal Forms”, “Bid Proposal Affidavit”, “List of Subcontractors”, “Public Crime Statement Form”, “Standard Form of Agreement Between Contractor/Subcontractor”, “Schedule A.1 General Requirements”, “Schedule A.2 Trade Scope of Work”, “Schedule “B” Document List”, “Exhibit-A Project Close-out Requirements”, “Exhibit-C Safety Rules and Regulations”, “Exhibit-D Basic Security Guidelines”, “Exhibit-E Environmental Policy”, and “Exhibit-F Substance Abuse Policy all as listed in the table of contents and related Drawing Schedules and Details. Any Addenda issued prior to the receipt of bids shall also become part of the Bidding Documents.

B. All definitions set forth in the Contract for Construction or in other Contract Documents are applicable to the Bidding Documents.

C. Addenda are written or graphic instruments issued by the Architect and Construction Manager prior to the execution of the Contract, which modify or interpret the Bidding Documents by additions, deletions, clarifications, or corrections.

D. A bid is a complete and properly signed proposal to do the work or designated portion thereof for the sums stipulated therein supported by data called for in the Bidding Documents.

E. Base Bid is the sum stated in the bid for which the bidder offers to perform the work described as the Base, to which work may be added or deducted for sums stated in any alternate bids.

F. An alternate bid (or Alternate) is an amount stated in the bid to be added to or deducted from the amount of the Base Bid, if the corresponding change in project scope or materials or methods of construction described in the Bidding Documents is accepted.

G. A Unit Price is an amount stated in the bid as a price per unit of measurement for materials or services as described in the Contract Documents.

H. A bidder is one who submits a bid for a prime Contract with the Construction Manager for the work described in the proposed Contract Documents. Each bidder must be Pre-qualified by the Construction Manager.

I. A sub-bidder is one who submits a bid to a bidder for materials or labor for a portion of the work. Each sub-bidder must have the qualifications described hereunder in Paragraph 1.02.

J. A surety is a corporate body, which is bound with and for the bidder, which is primarily liable and which guarantees the faithful performance of the Contract, if it is awarded to the bidder.

K. Construction Manager – Ausley Construction Company, LLC.

1.02 BIDDERS QUALIFICATIONS AND SPECIFICATIONS:

A. Sub-bidders Qualifications:

a. In order to be qualified, a Sub-bidder must be able to present evidence that its listed subcontractors are currently licensed and registered in the State of Florida and/or authority having jurisdiction.

b. If the bidder is a Corporation, it must be properly registered with the State of Florida.

c. Each bidder and sub-bidder is required to be familiar with all Federal, State and local laws, ordinances, rules and regulations that in any manner affect the work. Ignorance on the part of the bidder or sub-bidder will in no way relieve him/her from the responsibility.

B. Each bidder by making his/her bid represents that:

a. Bidder has read and understands the Bidding Documents and their bid is made in accordance therewith.

b. Bidder has visited the site and has familiarized themselves with the local conditions under which the work is to be performed and has correlated his observations with the requirements of the proposed Contract Documents.

c. Bidder’s bid is based upon the materials, systems and equipment described in the Bidding Documents without exception.

1.03 BIDDING DOCUMENTS:

A. Copies:

a. Bidders may obtain (1) complete set of Bidding Documents from the Construction Manager, Ausley Construction Company, LLC, Bid documents are available from John Ferris by email (jferris@ausleyconstruction.com). It will be the bidder’s responsibility to make hard copies of the plans and specifications at their own expense. Bidders are cautioned that they must comply with paragraph 1.03b as detailed below.

b. Bidders shall use complete sets of Bidding Documents in preparing bids; the Construction Manager and Owner do not assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents in preparing bids.

c. The Construction Manager in making copies of the Bidding Documents available on the above terms, does so only for the purpose of obtaining bids on the work and does not confer a license or grant for any other use.

d. No partial sets of drawings and/or specifications will be issued.

B. Interpretation of Correction of Bidding Documents:

a. Bidders and sub-bidders shall promptly notify the Architect through Ausley Construction Company, LLC at 352-629-8177 of any ambiguity, inconsistency, or error, which they may discover upon examination of the Bidding Documents or the site and local conditions.

b. Bidders and sub-bidders requiring clarification or an interpretation of the Bidding Documents shall make a written request to the Construction Manager through Procore or by email to John Ferris at jferris@ausleyconstruction.com by dates indicated in the Invitation to Bid

c. Any interpretation, correction, or change of the Bidding Documents will be made by addendum.

Interpretations, corrections, or changes of the Bidding Documents made in any other manner will not be binding, and bidders shall not rely upon such interpretations, corrections, and changes.

d. No oral explanations in regard to the meaning of the Bidding Documents will be made and no oral instructions will be given before the award of the Contract except as described in the sub-paragraph entitled "Pre-bid Conference" herewith.

C. Basis for Bidding -Trade Names:

a. When reference is made in the Contract Documents to trade names, brand names, or to the names of manufacturers, such references are made solely to indicate that products of the description may be furnished and are not intended to restrict competitive bidding. If it is desired to use products of trade or brand names or of manufacturer’s names which are different from those mentioned in the Contract Documents, application for the approval of the use of such products must be in receipt of the Architect within ten (10) days prior to the bid date. The latter provision is a restriction which applies only to the party making a submittal. Therefore, the aforesaid restriction does not inhibit the Architect from adding or deleting trade names, brand names or names of manufacturers by addendum. The burden of proving acceptability of a proposed product for use in place of a product or products designated by trade name or names, brand name or names, or by the name or names of manufacturers in the Contract Documents rests on the party submitting the request of approval. The written application for approval of proposed product must be accompanied by technical data, which the party requesting approval desires to submit in support of his application. The Architect will give consideration to reports from reputable independent testing laboratories, verified experience records showing the reputation of the proposed product with previous users, evidence of reputation of the manufacturer for prompt delivery, evidence of reputation of the manufacturer for efficiency in servicing its products, or any other written information that is helpful in the circumstances. The application to the Architect for approval of a proposed product must be accompanied by a schedule setting forth in which respects the materials or equipment submitted for consideration differ from the materials or equipment designated in the Contract Documents. The degree of proof required for approval of a proposed product as acceptable for use in place of a named product or named products is that amount of proof necessary to convince a reasonable person beyond all doubt to be approved, a proposed product must also meet or exceed all express requirements of the Contract Documents. If the submittal is approved by the Architect, an addendum will be issued by the Architect to all prospective bidders. Issuance of an addendum is a representation to all bidders that the Architect in the exercise of his professional discretion established that the product submitted for approval is acceptable and meets or exceeds all express requirements. In order for the Architect to prepare an addendum intelligently, an application for approval of a product must be accompanied by a copy of the published recommendations of the manufacturer for the installation of the product together with a complete schedule of changes in the drawings and specifications, if any, which must be made in other work in order to permit the use and installation of the proposed product in accordance with the recommendations of the manufacturer of a product. (The Contract requires the Contractor to do all cutting and fitting that might be required to make the several parts of his work come together properly and fit.) Unless requests for approvals or other products have been received and approvals have been published by addendum in accordance with the above procedure, the successful bidder may furnish no products of any trade names, brand names, or manufacturers; names except those designated in the Contract Documents with the exception of any changes or substitution that may be affected via Change Order in accordance with the Contract. Any party who alleges that rejection of a submittal is the result of bias, prejudice, caprice, or error on the part of the Architect may request a conference with a representative or the Owner, provided that the request for said conference, submitted in writing, shall have reached the Owner at least five (5) days prior to the date set for the opening of bids, time being of the essence.

D. Addenda:

a. The Architect and Construction Manager are responsible for addenda to be mailed or delivered to all who are known by the Architect and Construction Manager to have received a Bid Package or a complete set of Bidding Documents. The Architect and Construction Manager will not be responsible for the issuance or receipt of addenda forwarded to bidder by mail carrier.

b. Copies of addenda will be made available for inspection wherever Bidding Documents are on file for that purpose

c. Each bidder shall ascertain prior to submitting their bid that they have received all addenda issued, and they shall acknowledge their receipt in their bid.

1.04 BIDDING PROCEDURE(S):

A. Form and Style of Bids

a. One copy of the Bid Proposal shall be submitted using exact copy of the proposal form provided in Bid Packages. If necessary, copies of these forms or other documents may be obtained at the same location described in the “Invitation to Bid” for procurement of the Bidding Documents.

b. All blanks on the Proposal Form shall be clearly filled in by typewriter or manually printed in ink.

c. Where so indicated by the makeup of the Proposal Form, sums shall be expressed in both words and figures, and in case of discrepancy between the two, the amount written in words shall govern.

d. No interlineations, alteration, excisions, or special conditions shall be made; erasures shall be explained or noted over the signature of the bidder. Any unexplained omissions, erasures, alterations, information or request or other irregularities of any kind may constitute a cause for rejection of the bid by the Construction Manager.

e. Each copy of the bid shall include the legal name and full business address of the bidder and a statement that the bidder is a sole proprietor, a partnership, a corporation, or any other legal entity. Each copy shall be signed by the person or persons legally authorized to bind the bidder to a Contract. A bid submitted by an agent shall have a current Power of Attorney attached certifying the agent's authority to bind the bidder to a Contract. The Power of Attorney must then be signed by the Principal within ten (10) calendar days of bid submission and must refer to the specific project and bid.

f. Bids submitted by a corporation must be signed with the legal name and seal of the corporation followed by the name of the state of its incorporation and the manual signature and designation of an officer, agent or other person authorized to bind the corporation.

g. Bids submitted by a partnership shall show the names of all partners and must be signed in the partnership name by one of the partners. The partnership signature shall be followed by the manual signature of the partner signing.

h. In every case, the name of the person signing and their designation shall be typed or printed below his signature. A person, who affixes to their signature the words "President", "Secretary", "Agent", or other designation, without disclosing their principal, may be held to be individually responsible for such bid.

Satisfactory evidence of the authority of an officer, agent, attorney, or other person signing for a partnership or an individual shall be furnished.

B. Bid Security:

a. As stipulated in the "Invitation to Bid", each bid shall be accompanied by a Bid Security, Ausley Construction

Company, LLC shall be named Obligee (on AlA Document A310) in the amount of five percent (5%) of the Contract Sum listed on the bidders Proposal Form pledging that the bidder will enter into a Contract with the Construction Manager on the terms stated in his bid and will furnish Bonds as described hereunder in Paragraph 1.07 covering the faithful of all obligations arising there under.

b. The Bid Security shall be submitted with the understanding that it guarantees the bidder will not withdraw their bid for a period of ninety (90) days after the scheduled date and time for the receipt of bids described in the "Invitation To Bid”, that if their bid is accepted, they will enter into a written Contract with the Construction

Manager in accordance with the Form of Agreement described hereunder in Paragraph 1.07 will be given;

and that in the event of withdrawal of the bid within the stated withdrawal period, or failure to enter into the Agreement and furnish the Bonds within ten (10) days after they have received notice of acceptance of their bid or within any extended period the Construction Manager may grant, the bidder shall be in default and shall be liable to the Construction Manager for the full amount of the Bid Security as damages due the Construction Manager on the account of the default of the bidder in any particular hereof.

c. The Bid Security shall be returned to all bidders after the Construction Manager and the accepted bidder have executed the Agreement and Labor and Performance Bond has been approved by the Construction Manager.

d. If the required Agreement and Bonds described hereunder in Paragraph 1.07 have not been executed within ninety (90) days after the date of the opening of the bids, then the Bid Security of any bidder will be returned upon their request, provided they have not been notified of the acceptance of their bid prior to the date of such request.

e. If the Bid Security is in the form of a Bid Bond, the Surety Company furnishing the Bond shall be acceptable if it complies with the provisions described hereunder in Paragraph 1.07. Type or print the dollar amount of the Bond wherever required. The words “5% of the Bid" is sufficient. The Bid Bond shall be signed by a FL Licensed Resident Agent who holds a legal Power of Attorney from the Surety Company issuing the Bond.

1. Prepare one (1) copy of Bid Bond on AlA Document A310 for the Construction Manager.

2. Type or print bidder's and surety's names where required.

3. Type or print the dollar amount of the Bond where required. The words “5% of the Bid" is sufficient.

4. Date the Bond prior to the time of the bid opening.

5. Type or print the description of the construction in the same language as in the "Invitation to Bid".

6. Complete the signatures on the form. A corporate bidder shall sign in the following manner:

By: ____________________________ President, or Florida Registered Agent

The corporate seal must be affixed. Type or print the name of Surety on the line provided and affix its’ corporate seal.

7. Attach a copy of Surety's Florida Resident Agent's Power of Attorney. If not recorded, the copy of the Power of Attorney must have an original signature of the Secretary or Assistant Secretary of the Surety Company certifying to the copy. The Surety's corporate seal must be affixed.

C. List of Subcontractors:

Bidders shall:

a. In order that the Owner may be assured that only qualified and competent subcontractors will be employed on the project, each bidder shall submit a "List of the Subcontractors" who will perform the work for each applicable division or portion thereof, of the specifications, as indicated by the "List of Subcontractors" form as described in SECTION F – LIST OF SUBCONTRACTORS within twenty-four (24) hours of bid date.

b. The bidder shall have determined to their own complete satisfaction that each listed subcontractor has been successfully engaged in this particular type of business for a reasonable length of time, has successfully completed installations comparable to that which is required by this Project and qualified both technically and financially to perform that pertinent phase of this work for which they are listed, as described in Paragraph 1.02, A, of the "Instructions to Bidders". Only one subcontractor shall be listed for each division, or portion thereof, of the work. The full name and complete address of each and every subcontractor must be provided;

along with the identification of the division, or portion thereof, of the work, to be performed by that listed subcontractor.

c. No change shall be made in the list of Subcontractors, before or after the Award of a Contract, unless agreed to in writing by the Construction Manager, in conformance with the provisions of the contract and with the recommendation of the Architect.

D. Submission of Bids:

WARNING - USE ONLY THE BID DOCUMENTS INCLUDED WITH THIS BID PACKAGE. CHANGES OR

MODIFICATIONS TO THESE DOCUMENTS OR ATTACHMENTS NOT LISTED WILL DISQUALIFY THE BID.

a. At Bid Time: To be considered for the award of contract the following completed and properly executed forms will be required.

1. Proposal Form (all pages)

2. Addendum Acknowledgement (included in Proposal Form)

3. Bid Bond (AIA 310)

4. Bid Proposal Affidavit

5. List of Subcontractors (within twenty-four (24) hours of bid time)

6. Public Crimes Statement (Florida Statutes 287.133)

7. Schedule “A.1” General Requirements

8. Schedule “A.2” Trade Scope of Work

9. Exhibit-A Project Close-Out Requirements

10. Exhibit-B Direct Purchase Procedure

11. Exhibit-C Safety Rules and Regulations

12. Exhibit-D Basic Security Guidelines

13. Exhibit-E Environmental Policy

14. Exhibit-F Substance Abuse Policy

The one copy of the Bid Proposal Form and the single copies of the other required forms shall be emailed to John Ferris at jferris@ausleyconctruction.com or faxed to 352.624.0925.

b. If the bid is sent by mail or other courier service, the sealed envelope shall by enclosed in a separate mailing envelope with the notation “BID ENCLOSED” on the face thereof, and shall be delivered no later than one (1) day prior to bid date and within reasonable time to receive and transport the bid to the location of the bid opening and prior to the bid opening times established in the Invitation to Bid.

Deliver to: Ausley Construction Company, LLC Mail to: Ausley Construction Company, LLC 1521 S.E. 36th Avenue 1521 S.E. 36th Avenue Ocala, FL 34471 Ocala, FL 34471

c. Oral, telephonic, or telegraphic bids are invalid and will not receive consideration.

1.05 BID MODIFICATION AND WITHDRAWAL:

A. A bid may not be modified, withdrawn, or canceled by the bidder during the stipulated time period following the opening of bids as described in the “Invitation to Bid” and the bidder so agrees in submitting their Bid. Negligence on the part of the bidder in preparing the bid confers no right for withdrawal of the bid after it has been opened.

B. Prior to the time and date designated for receipt of bids, bids submitted early may be modified or withdrawn only by notice to the party receiving bids at the place and prior to the time designated or receipt of bids. Such notice shall be in writing over the signature of the bidder or shall be by telegram; if by telegram, written confirmation over the signature of bidder must have been mailed and postmarked on or before the date and time set for receipt of bids; it shall be so worded as not to reveal the amount of the original bid.

C. Withdrawn bids may be resubmitted up to the time designated for the receipt of bids provided that they are then fully in conformance with the “Instruction to Bidders”.

D. Bid Security, if any is required, shall be in an amount sufficient for the bid as modified or resubmitted.

1.06 CONSIDERATION OF BIDS:

A. Opening of Bids: Bid opening and review will be at the sole discretion of the CM and owner.

B. Rejection of Bids:

a. The Owner and Construction Manager shall have the right to reject any or all bids and in particular to reject a bid not accompanied by the required bid Security or any data required by the Bidding Documents or a bid in any way incomplete or irregular.

b. The Owner and Construction Manager shall have the right to reject any bidder who in its opinion has previously failed to perform properly to complete their work on time, who has habitually and without just cause neglected payments of bills or otherwise disregarded obligations or whose Surety has failed to meet its obligations on any public construction in the State of Florida.

c. Any or all Proposals may be rejected if there is reason to believe that collusion exists among the bidders and no participants in such collusion will be considered for future Proposals for the same work. Proposals in which the prices obviously are unbalanced may be rejected.

C. Acceptance of the Bid:

a. It is the intent of the Construction Manager to Award a Contract to the lowest responsible bidder provided the bid has been submitted in accordance with the requirements of the Bidding Documents and does not exceed the funds available. The Owner and Construction Manager shall have the right to waive any informality or irregularity in any bid or bids received, accept bids in any order or combination, accept or reject portions of bids, make modifications to the work after bidding and to accept the bid or bids which, in their judgment, are in their own best interests.

1.07 AWARD:

A. In the event the Contract is awarded to this bidder, the bidder shall enter into a formal written Agreement with the

Construction Manager in accordance with the accepted bid within ten (10) calendar days after said Contract is submitted to them and will furnish to the Construction Manager a Contract Performance and Payment Bond with good and sufficient sureties, satisfactory to the Construction Manager in the amount of 100% of the accepted bid.

The bidder further agrees that in the event of the bidders default or breach of any of the Agreements of this proposal, the said Bid Security shall be forfeited. And further, the Construction Manager then may either award the Contract to another responsible bidder, or re-advertise for bids, and may charge against the defaulting bidder the difference between the amount of the bid and the amount for which a Contract for the work is subsequently executed, irrespective of whether the amount due exceeds the amount of the Bid Bonds. If a more favorable bid is received by advertising, the defaulting bidder shall have no claim against the Construction Manager.

B. Unless waived by the Construction Manager, the successful bidder for each phase of the Project shall, within ten

(10) days of notification of selection, submit the following information to the Construction Manager:

a. Percentages of work to be performed by bidder with his/her own forces.

b. Proprietary names of the suppliers or principal items, or systems of material and equipment proposed for the work.

c. Insurance Certificates. AUSLEY CONSTRUCTION COMPANY, LLC. AND THE OWNER (MARION

COUNTY BOARD OF COUNTY COMMISSIONERS) ARE TO BE LISTED AS ADDITIONAL INSURED.

d. Submittal and Schedule Outline.

e. Schedule of Values in a form acceptable to Owner, Construction Manager and Architect.

1.08 ADDENDUM:

A. Acknowledgement shall be made for receipt of the addenda issued during the bidding period on the Form Proposal.

1.09 TIME OF COMPLETION:

A. The time of completion of the Project is of great importance to the Owner. It is highly desirable that the Project be substantially completed and ready for occupancy at the earliest possible time. Work shall commence when the Trade Contractor is given written Notice to Proceed and is to be Substantially Complete within the time established in each Bid Package from Notice to Proceed. The work shall reach Final Completion within thirty (30) calendar days after the date of Substantial completion. See Tentative Construction Schedule for milestone dates for each Bid Package.

B. Time of completion will be written into the basic Contract, unless different times of completion are mutually agreed upon in writing by the Trade Contractor and The Construction Manager prior to the execution of the Contract.

C. The Trade Contractor shall furnish sufficient forces, construction plant and equipment, and to work such hours, including overtime operations, as may be necessary to insure the prosecution of the work, to allow the Substantial Completion and Final Completion of the Project within the specified times. Normal inclement weather will not be sufficient reason to allow an extension of time on the Project, only exceptional weather conditions or acts of God which might cause delay in the work, or other factors outlined in the Contract agreement between Construction Manager and Trade Contractor, will be considered as justifiable reasons for an extension of time.

D. Failure on the part of the Trade Contractor to comply with the conditions of the basic Contract concerning the time in which the Project is to be completed will be considered by the Construction Manager as a justifiable reason to invoke the conditions of the Contract relating to termination; or, at its sole option, to avail itself of the rights per the contract concerning Liquidated Damages.

E. Bidders are informed that the following paragraphs concerning Liquidated Damages will be inserted in the basic Contract.

a. Trade Contractor and Construction Manager agree that time is of the essence and that Construction Manager will suffer financial loss if the Work is not substantially completed within the Contract Time, as said Contract Time may be adjusted as provided for herein. In such event, the total amount of the Construction Manager’s damages, will be difficult, if not impossible, to definitely ascertain and quantify. It is hereby agreed by the parties that is appropriate and fair that the Construction Manager receive liquidated damages from the Trade Contractor, if the Trade Contractor fails to achieve Substantial Completion of the Work within the required Contract Time. Should Trade Contractor fail to substantially completion of the Work within the required time period, Construction Manager shall be entitled to assess, as liquidated damages, but not as a penalty $2,500 for each calendar day thereafter until Substantial Completion is achieved. Trade Contractor hereby expressly waives and relinquishes any right which it may have to seek to characterize the above noted liquidates damages as a penalty, which the parties agree represents a fair and reasonable estimate of Construction Manager’s actual damages at the time of contracting if Trade Contractor fails to substantially complete the Work in a timely manner.

If awarded this Construction Contract, the Trade Contractor agrees to complete the work covered by the Contract as follows:

1. Substantially Complete within the time established in each Bid Package from Notice to Proceed.

2. Completion in thirty (30) consecutive days from Substantial Completion.

b. The provision for liquidated damages for delay shall in no manner affect the Construction Manager's right to terminate the Contract, as provided in the Trade Contractor's Agreement or elsewhere in the Contract Documents and Construction Manager's exercise of the right to terminate shall not release the Trade Contractor from his/her obligations to pay the liquidated damages, the amount hereinbefore set out. The liquidated damages shall be payable in addition to any excess expenses or costs payable by the Trade Contractor per the contract and shall not exclude recovery of damages by the Construction Manager under other provisions of the Contract.

1.10 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND:

A. Construction Manager's Right to Require Bonds:

a. The Construction Manager shall require the bidder to furnish a Performance Bond and Labor and Material Payment Bond (Ausley Construction Company, LLC, shall be named as Obligee) covering the faithful performance of the Contract and the payment of all obligations arising there under equal to 100% of the Contract amount with such sureties secured through the bidders usual sources as may be agreeable to the parties. The cost shall be separate and not included in the Trade Contractors Base Bid.

1. The Bonds shall be kept current with the full amount of the Contract.

2. The Bonds shall extend as a Maintenance Bond for one (1) year after final acceptance of the Project by the Owner.

B. Time and Delivery and Form of Bonds:

a. The bidder shall deliver the required Bonds to the Construction Manager no later than the date of execution of the Contract.

C. Execution of the Bonds:

a. The Trade Contractor's Performance and Labor and Material Payment Bond shall be executed on behalf of the Trade Contractor in the same manner as the Contract was executed and by the same person or persons who executed the Contract and it shall not be dated earlier than the Agreement.

b. The Bond must be accompanied by a duly authenticated or certified document evidencing that the person executing the Bond on behalf of the Surety had the authority to do so on the date of the Bond. In the usual case, the conferring of that authority has occurred prior to the date of the Bond; and the document showing the date of the appointment and the enumeration of the powers of the person executing the Bond is accompanied by a certification that the appointment and powers have not been revoked and remain in effect.

The date of that certification cannot be earlier than the date of the Bond.

c. Such certificate must be manually signed or be accompanied by a duly attested Resolution adopted by a Board of Directors, stating that the signatures of officers and the seal of the company may be affixed to any Power of Attorney or to any certificate relating thereto by facsimile; and that such facsimile signature will be valid and binding upon the company.

D. Acceptable Surety Companies:

a. To be acceptable as Surety for Bid Bond and Performance and Payment Bonds, the Surety Company must, at a minimum, comply with the provisions described below. In addition, the Owner may reject any surety due to prior performance issues.

b. The Surety Company must be admitted to do business in the State of Florida and shall have a Florida Resident Agent.

c. The Surety Company shall have been in business and have a record of successful continuous operations for at least five (5) years.

The Surety Company shall have at least the following minimum ratings:

1. CONTRACT AMOUNT AND REQUIRED FINANCIAL RATINGS:

$0 TO 375,000 BBB

$375,001 to 500,000 BBB+ $500,001 to 750,000 AA $750,001 to 1,000,000 AA+ $1,000,001 to 1,250,000 AAA $1,250,001 to 1,500,000 AAA+ $1,500,001 to 2,000,000 AAAA $2,000,001 to 2,500,000 AAAA+ $2,500,001 to more AAAAA

2. Best's policyholder's rating of A, A- (which signifies “excellent” based upon good underwriting, economic management, adequate reserves for undisclosed liabilities, net resources for unusual stock and sound investment) or an equivalent rating from the Insurance Commissioner if not rated by Best's.

d. The Surety Company shall not expose itself to any loss on anyone risk in an amount exceeding ten percent (10%) of its surplus to policyholders, provided.

1. Any risk or portion of any risk which shall have been reinsured (in which case these minimum requirements contained herein also apply to the reinsuring carrier) in assuming insurer authorized or approved by the Insurance Commissioner to do such business in this State shall be deducted in determining the limitations of risk prescribed in the Section.

2. In the case of a Surety Insurance Company, there shall be deducted, in addition to the deduction for reinsurance, the amount assumed by and co-surety, the value of any security deposited, pledged or held subject, to the content of the Surety and for the protection of the Surety.

1.11 FORM OF AGREEMENT BETWEEN CONSTRUCTION MANAGER AND TRADE CONTRACTOR:

A. Form to be used: Unless otherwise provided in the Bidding Documents the Agreement for the work will be written on the Construction Contract Form of Agreement between Contractor and Subcontractor where the Basis of Payment is a Stipulated Sum. This form is included in bid package. This is the contract that will be executed as issued. Submission of a bid signifies that Trade Contractor has read contract and agrees with all terms included. If Trade Contractor has issues with any of the terminology in the contract it must be addressed by RFI prior to the bid.

1.12 NON-DISCRIMINATION CLAUSE:

A. The non-discrimination clause contained in Section 202, Executive Order 11240, as amended by Executive Order 11373, relative to Equal Employment Opportunity for all persons without regard to race, color, religion, sex or national origin, and the implementing rules and regulations prescribed by the Secretary of Labor, are incorporated herein.

1.13 APPRENTICE EMPLOYEE REQUIREMENTS:

A. Bidder's attention is called to the State Public works Compliance Act, Paragraph 446.102, and Florida Statutes.

The Bureau of Apprenticeship in the Division of Labor, Florida Department of Commerce, will assist bidders in the determination of actual or anticipated need in complying with the statutory requirements of this law.

B. The following pertinent Contract clauses from the Act shall be the conditions of each State of Florida Contract in excess of $25,000.00. The bidder agrees, if awarded Contract.

a. To hire, for their performance of the Contract, a number of apprentices in each occupation which bears to the number of the journeymen in that occupation to be employed in the performance of the Contract the ratio of at least one apprentice or trainee to every five (5) journeymen

b. That they will, when feasible, assure that twenty-five percent (25%) of such apprentices or trainees are in their first year of training, except when the number of apprentices or trainees to be hired is fewer than four (4). Feasibility here involves a consideration of the availability of training opportunities for first year apprentices or trainees, the hazardous nature of the work for beginning workers and excessive unemployment of apprentices or trainees in their second and/or subsequent years of training.

c. That during the performance of the Contract, they will make diligent efforts to employ the number of apprentices or trainees necessary to meet the requirements of subparagraphs a and b above; however, on the job training programs shall only be established in non- apprentices trades or occupations, to meet the requirements of Section 446.101, Florida Statutes.

C. The bidder agrees to return records of employment by trade of the number of apprentices or trainees, by first year of training and of journeymen and the wages paid and hours of work of such person, on a form as prescribed by the Bureau of Apprenticeship of the Office of Labor Relations, Florida Department of Commerce, at three (3) month intervals. Submission of duplicate copies of forms submitted to the United States Department of Labor shall be sufficient compliance with the provisions of this section.

1.14 FLORIDA PRODUCTS AND LABOR:

A. The bidder's attention is called to section 255.04, Florida Statutes, which requires that on public building contracts, Florida products and labor shall be used wherever price and quality are equal.

1.15 TAXES AND PERMITS:

A. The Trade Contractor is responsible for all state and local permits and business privilege taxes.

B. The owner is Florida sales and use tax exempt. Only Materials listed in Section M-Exhibit B to qualify for tax exemption.

C. The Owner is not subject to:

a. Federal excise taxes on materials or appliances that are incorporated into and become a part of the completed improvement.

b. Cost of municipal or county building permits.

D. In every case of a purchase of materials to be incorporated in the work, which are subject to Federal excise tax, the Owner will furnish to the Trade Contractor the necessary Federal excise tax exemption certificate upon receipt of a copy of the supplier's invoice showing the item or items, the net price and Federal excise tax separately.

E. The Owner will furnish certain material and equipment items as outlined in this section.

1.16 PROGRESS PAYMENTS:

A. Based upon Applications for Payment submitted to and acceptable to the Architect and Construction Manager by the Trade Contractor, the Construction Manager shall make monthly progress payments to the Trade Contractor as provided in the Agreement.

1.17 ENGINEERING:

A. Each bidder must include in their proposal all costs for verifying the suitability of the work by others which affects the Trade Contractor's work, and to perform all engineering, and surveying and field measurements which may be required to complete the work. Destruction and displacement of monuments by the Trade Contractor will make said Trade Contractor liable for all cost to reestablish the monuments.

B. Basic reference points and benchmarks will be provided by Construction Manager and Owner. Subsequent surveying and field measurements from these points will be the responsibility of each Trade Contractor.

1.18 OWNER'S OPTION TO DIRECT PURCHASE MATERIALS:

A. The Owner is tax exempt and exercises his right to purchase directly various construction materials, supplies and equipment that may be a part of this Contract. The Owner may exercise this option at no additional cost. The Owner will, via his purchase orders, purchase the materials, and the Trade Contractor shall assist the Owner in the preparation of purchase orders. The materials shall be purchased from the vendors/suppliers selected by the Trade Contractor, for the price originally negotiated by the Trade Contractor. Enclosed in the bid package is Exhibit B Direct Purchase Guidelines with list of the equipment and materials to be direct purchased by the Owner. The Trade Contractor shall provide the Owner with the information necessary to issue the purchase order.

B. The Contract amount shall be reduced by the net, undiscounted amount of the purchase orders plus all sales taxes. Issuance of the purchase orders by the Owner shall not relieve the Trade Contractor of any of his/her responsibilities regarding material purchases, or installations, with the exception of the payments for the materials so purchased. The Trade Contractor shall remain fully responsible for coordination, correct quantities ordered, submittal, protection, storage, scheduling, shipping, security, expediting, receiving, installation, cleaning and all applicable warranties.

C. The material supplier may be required to provide a Supply Bond in the amount of 100% of the purchase order price. The Bond shall be from a qualified surety company authorized to do business in the State of Florida and acceptable to the Owner. Verifying that a designated material supplier can furnish a Supply Bond (if required) will be the responsibility of the Trade Contractor.

1.19 OTHER OWNER - FURNISHED EQUIPMENT:

A. Certain items scheduled in the Contract Documents are to be furnished directly by the Owner, to the project site unless otherwise indicated, and are to be received and installed by the Trade Contractor.

B. Within five (5) calendar days after receipt of notification of selection for the Award of a Contract for the Work, the

Trade Contractor shall submit to the Construction Manager a schedule, giving desired dates for delivery of Owner-furnished items. Approved dates of delivery shall be confirmed to the Trade Contractor thirty (30) days prior to delivery by the Owner. The Trade Contractor shall accept delivery on the established dates or be responsible for any damage resulting from his failure to take delivery of the shipment on established dates.

Promptly upon delivery, the Trade Contractor, jointly with the Construction Manager shall inspect the materials or equipment for possible shortage or damage in transit, if shortage or damage is found, the Trade Contractor shall follow the instructions of the bill of lading for reporting to the carrier. The Trade Contractor shall submit a complete receiving report acceptable to the Construction Manager.

C. The Trade Contractor shall receive, store, protect, secure and unload the items, sign for, provide additional transportation required, uncrate, assemble for operation and use, and clean for Final Inspection. For details of construction and installation of each item, see drawings and standard details. Installation or connection shall be in accordance with specifications for such work, including fitting to adjacent work and any additional labor and material required. All materials/equipment received shall be property and legibly listed and signed for on Owner's

"Receiving Ticket" form, as well as Shipper's packing slip. The receiving person's name and company must be legibly shown on all such documents.

1.20 BID PROTESTS:

A. In the event that a properly qualified bidder submits a valid bid, supported by all necessary documentation required by these specifications, and said bidder lodges a "bid protest” due to perceived irregularities in procedures or documents, said bidder shall submit, in writing, the exact cause of such protest within 72 hours of the bid opening time.

B. The Construction Manager will review the written protest to determine the nature and justification of protest, and will notify the protesting bidder within seven (7) days of receipt of protest of any and all actions that will serve the best interests of the Construction Manager. Informalities, such as typographical errors, will not be viewed as valid grounds for protest.

C. IN THE EVENT A PROTEST IS LODGED AND THE PROTEST IS DETERMINED TO BE NULL AND VOID, THE

BIDDER LODGING SUCH PROTEST SHALL BE LIABLE TO THE CONSTRUCTION MANAGER FOR ALL

DAMAGES RESULTING FROM THE PROTEST.

Company Name Address City, State Zip Name-Signature Name-Printed Title Email Phone Date

Proposal Form: Div 7A - Roofing

SECTION C

PROPOSAL FORM

Fill in gray shaded areas

DIV 7A - ROOFING

Date:

Proposal From:

City, State Zip

Proposal To: Ausley Construction Company, Inc.

Address 1521 SE 36th Ave.

City, State Zip Ocala, FL 34471

I, _________________________________________, the undersigned, hereby declare that we have carefully examined the site and have become familiar with the conditions affecting the construction of the proposed work and the contract documents. Price includes all taxes, permit fees, etc. We do hereby agree to furnish all materials, transportation, equipment, apparatus systems, labor, and supervision required to do all work in strict accordance with the contract documents for the following Base Bid price:

Total bid price for all work, complete, in accordance with the contract documents inclusive of the above referenced Bid Package.

Base Bid shall include but is not limited to all materials, equipment, and labor for all Roofing as described in all the bid documents.

BASE BID

Base Bid 01 Base Bid

Dollars $

Base Bid 02 Performance and Payment Bond (do not include in Base Bid above)

ALTERNATES (including Perf.