This is a Payment Milestone Schedule for Task Order 0001 under NASA Ames Research Center's Commercial Aviation Services—Airborne Science Support IDIQ contract (Snow4Flow EVS-4). The task order is a firm-fixed-price contract for the Snow4Flow 2027 Campaign Startup and represents the guaranteed minimum under the IDIQ vehicle.

Payment is structured around two milestones requiring Government acceptance by the Contracting Officer's Representative. Milestone 1 (M1), due February 25, 2027, covers Phase 1 completion, which includes instrument installation checkout and integration at the contractor's facility, engineering, fabrication, and certification support, interface verification, and airworthiness release of the configured aircraft. This milestone encompasses 3 at-base aircraft days and 1 engineering/fabrication/certification support job, all within CLIN 0001. Milestone 2 (M2), due March 2, 2027, covers Phase 2 completion, which includes transit to the Alaska deployment location and initial science flight operations, with flight and maintenance logs delivered. This milestone includes 14 flight hours, 5 deployed aircraft days, 2,240 gallons of fuel, and 1 per diem and travel job, all within CLIN 0001. Offerors must complete the Milestone Amount column by applying their proposed CLIN 0001 catalog rates to the stated quantities and their proposed other direct costs, with the total of both milestones equaling their proposed Task Order 0001 total firm-fixed price. Shop fees are excluded from milestone amounts and will be added by task order modification if incurred. No payment is made until written acceptance is received, and the task order is non-severable and fully funded at issuance.

View the file

Other files

File Type Posted
02_Solicitation - 80ARC026R0007.pdf PDF
06_TO0001_Attachment_1_SOW.pdf PDF
07_TO0001_Attachment_2_CDRL.pdf PDF
04_Attachment_J-2_CDRL_DRDs.pdf PDF
03_Attachment_J-1_SOW_IDIQ.pdf PDF
05_Attachment_J-3_Pricing_Tables.xlsx XLSX spreadsheet
01_RFP_Cover_Letter_80ARC026R0007.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rev.: 05/2026

Task Order 0001 Attachment 3 Solicitation 80ARC026R0007

PAYMENT MILESTONE SCHEDULE

National Aeronautics and Space Administration — Ames Research Center

Commercial Aviation Services — Airborne Science Support IDIQ (Snow4Flow EVS-4)

Task Order 0001 — Snow4Flow 2027 Campaign Startup — Firm-Fixed-Price

1. Purpose and Instructions to Offerors

This attachment establishes the payment milestones for Task Order 0001, which will be issued concurrent with contract award and satisfies the contract guaranteed minimum. Payment for this firm-fixed-price task order will be made upon completion and Government acceptance of the milestones below, in accordance with FAR 52.212-4(i), Payment. The

Contracting Officer’s Representative provides written acceptance of each milestone. Invoices must identify the contract number, task order number, milestone number, and amount.

OFFEROR: complete the Milestone Amount column. Milestone amounts must be derived from the offeror’s proposed

CLIN 0001 catalog rates applied to the quantities stated below and the offeror’s proposed other direct cost amounts, and the sum of the milestone amounts must equal the offeror’s proposed Task Order 0001 total firm-fixed price on the Attachment J-3, Pricing Tables, of the solicitation. Amounts entered here that do not reconcile to the Attachment

J-3, Pricing Tables, of the solicitation may render the offer unacceptable. The completed schedule of the successful offeror will be incorporated into Task Order 0001 at award.

2. Milestone Schedule

No. Milestone and completion criteria Government quantities Target date Milestone amount

M1 Completion of Phase 1 — instrument installation checkout and integration at the contractor’s facility, including engineering, fabrication, and certification support;

interface verification against the interface control documentation; and airworthiness release of the configured aircraft for flight.

Acceptance: Contracting Officer’s

Representative written acceptance of Phase

1 completion and the DRD-05 documentation.

3 at-base aircraft days;

engineering/fabrication/certification support, 1 job (all within CLIN

0001).

February 25, M2 Completion of Phase 2 — transit from the contractor’s facility to the Alaska deployment location and completion of initial science flight operations for the period of performance, with flight and maintenance logs delivered. Acceptance:

Contracting Officer’s Representative written acceptance of Phase 2 completion and the

DRD-01 and DRD-02 deliverables.

14 flight hours; 5 deployed aircraft days; fuel, 2,240 gallons; per diem and travel, 1 job (all within CLIN

0001).

March 2, TASK ORDER 0001 TOTAL FIRM-

FIXED PRICE

3. Notes

(a) The quantities stated above are the Government’s requirements for Task Order 0001 and are not estimates; the offeror prices these quantities at its proposed catalog rates.

(b) Shop fees are not included in any milestone. If shop fees are incurred, they will be added by task order modification and paid with the milestone in performance at the time the fees are incurred.

(c) No payment will be made for a milestone until the Contracting Officer’s Representative provides written acceptance.

(d) Task Order 0001 is non-severable and fully funded at issuance.